ww w. daxib.c om
INSTALLATION GUIDE DAX-8180
01 02 03
04
07
05
08
06
09
Spirit level Teflon tape Pencil
S6 Allen key
(Provided)
S2.5 Allen key
(Provided)
Drill Goggles Spanner
Protection sheath
Inlet base
Hole
Hexnut
Spring shim
Flat shim
Expansion bolt
Spirit level
Longitudinal level detection
Horizontal level detection
Cold water inlet
Plug
Flange
Locking screw
Allen key
Hot water inlet
Cold water inlet
Flow water
Flow water
Hot water inlet
Faucet body
Inner pipe
Protection sheath
Escutcheon
Prepare and check the following tools.
Insert expansion bolts into holes on the floor
(Note:cold water inlet which printed with
“COLD” mark on inlet base faces to the bath-
tub),adjust the top surface of inlet base to level
position with spirit level and tighten with
hexnut.
Unscrew locking screw,remove flange and plug.
Put on protection sheath for paving floor tiles
(Note:the height of tiles should be at the same
level or a bit higher than the top surface of
protection sheath).
Take off protection sheath from inner pipe of
faucet body,put on escutcheon carefully to
avoid scratch to the surface of faucet body. Fix
flange(the side with counter bore back against
faucet body) with locking screw to faucet body
firmly.
Connect inlet base with cold and hot water
inlet pipe,cold water inlet faces to bathtub,
hot water inlet back against bathtub(means
front cold and back hot),wrap connectors
with teflon tape.Note to flow water to
get rid of dirt in pipes.Remove protection
sheath,insert plug into outlet of inlet base and
fix with flange.
Flow water for pressure test, ensure each
connection has no leakage occurs.
Take 4 mounting holes on inlet base (No-
te:ensure cold water inlet which printed with
“COLD” mark faces to bathtub)as benchmark
to draw line and drill 4 Ø12 holes on the floor. Install 4 expansion bolts to inlet base and
slightly tighten with hexnut.