CHAPTER 3 - SETUP AND INSTALLATION
POWER CONNECTION
It is very important to check that the unit is set to the correct voltage setting for your
application before applying AC power. Located on the rear of the unit you will find a rotary
110/220 VAC switch. Using a coin or small screwdriver, gently turn the switch to the
appropriate power position as required for your installation (110 or 220VAC).
INSTALLATION
Connect the main input data feed source into theINPUT port DB-15 female connector.
The output ports are markedPORT 1 through PORT 8. Connect from one to eight DTE
V.11 (X.21) compliant devices into the sub-channels ports on the back of theDBU-V11.
CASCADING AND TERMINATION RESISTORS
If more than oneDBU-V11’s are to receive Data, Clock and Indicate from the same
source, a shielded DB-15 one-to-one extension cable with a male DB-15 on one end and a
female DB-15 on the other end can be used to link theDBU-V11's together. The box
furthest from the source of the data and clock should have jumpers JMP2,JMP3 and
JMP4 moved to theopposite position of the factory default setting for proper termination.
High quality shielded cables are recommended for box to box cascading. The cabling should be twisted pair
with a wire mesh shield. All signal pairs should be kept together for clean quality signals. We recommend
Beldon 9833 or equivalent cable with metal hoods.
EQUIPMENT GROUNDING
Jumper JMP1 provides for grounding interconnection in those systems requiring a
connection between Pin #1 (frame ground) and Pin # 8 (signal ground). Please reference
the PCB chart at the end of this document for further strapping details.
FORCED INDICATE TO INPUT PORT