17
INSTALLERUSER
MAINTENANCE TECHNICIAN
1.19 FLUES, CHIMNEYS, CHIMNEY POTS
AND TERMINALS.
e ues, chimneys and chimney pots for the
evacuation of combustion products must be in
compliance with applicable standards. Chimneys
and roof-installed exhaust terminals must com-
ply with the outlet height and with the distance
from technical volumes set forth by the technical
standards in force.
Positioning the wall ue exhaust terminals. e
wall ue exhaust terminals must:
- be installed on external perimeter walls of the
building;
- be positioned according to the minimum dis-
tances specied in current technical standards.
Combustion products exhaust of natural
draught or fan assisted appliances in open-top
closed environments. In spaces closed on all
sides with open tops (ventilation pits, court-
yards etc.), direct combustion product exhaust
is allowed for natural draught or fan assisted gas
appliances with a heat input range from 4 to 35
kW, provided the conditions as per the current
technical standards are respected.
1.20 SYSTEM FILLING.
Once the boiler is connected, proceed with sys-
tem lling via the lling valve (Fig. 2-2). Filling
is performed at low speed to ensure release of air
bubbles in the water via the boiler and central
heating system vents.
e pump may be noisy on start-up due to the
presence of air. is noise should stop aer a
few minutes of functioning and however aer
having correctly bled the air contained in the
hydraulic circuit.
e boiler has a built-in automatic venting valve
on the boiler circulator. Check if the cap is loose.
Open the radiator vent valves.
Close radiator vent valves when only water
escapes from them.
Close the lling cock when the boiler pressure
gauge indicates approx. 1.2 bar.
N.B.: during these operations, turn on the circu-
lating pump at intervals using the main switch
on the control panel. Vent the circulation pump
by loosening the front cap and keeping the motor
running and assuring that the liquid that escapes
cannot cause injury/damage to persons/objects.
Tighten the cap aer the operation.
1.21 CONDENSATE TRAP FILLING.
On rst lighting of the boiler, ue gas may come
out the condensate drain; aer a few minutes’
operation check that this no longer occurs. is
means that the drain trap is lled with conden-
sate to the correct level preventing the passage
of ue gas.
1.22 GAS SYSTEM STARTUP.
To start up the system, refer to the technical
standard in force: is divides the systems and
therefore the start-up operations into three
categories: new systems, modied systems, re-
activated systems.
In particular, for new gas systems:
- open windows and doors;
- avoid presence of sparks or open ames;
- bleed all air from the pipelines;
- check that the internal system is properly sealed
according to the specications set forth by
technical regulations in force.
1.23 BOILER START UP IGNITION.
In order to issue the Declaration of Conformity
required by the laws in force, one must full
the following requirements to commission the
boiler (the operations listed below must only
be performed by qualied personnel and in the
presence of professionals only):
- ensure the internal system is properly sealed
according to the specications set forth by
regulations in force;
- make sure that the type of gas used corresponds
to boiler settings;
- Check that there are external factors that may
cause the formation of fuel pockets;
- switch the boiler on and check correct ignition;
- make sure that the gas ow rate and relevant
pressure values comply with those given in the
manual (Par. 3.22);
- ensure that the safety device intervenes in the
event of gas supply failure and check the relative
intervention time;
- check the intervention of the main switch
located upstream from the boiler and in the
boiler;
- check that the intake/exhaust concentric
terminal (if tted) is not blocked.
e boiler must not be started up even if only
one of the checks should be negative.
N.B.: only upon completing commissioning by
an installer, may an authorised rm carry out an
initial inspection of the boiler, which is required to
activate the Immergas warranty. e test certicate
and warranty is issued to the user.
1.24 DOMESTIC HOT WATER STORAGE
TANK UNIT.
e Victrix Zeus 26 2 ErP storage tank unit has
a capacity of 45 litres. It contains a large coiled
stainless steel heat exchanger pipe, which allows
to notably reduce hot water production times.
ese storage tank units constructed with stain-
less steel casing and bottoms, guarantee long
duration through time. e assembly concepts
and welding (T.I.G.) are implemented to the
minimum detail to ensure maximum reliability.
e lower inspection ange ensures practical
control of the storage tank unit and the coiled
heat exchanger pipe and easy internal cleaning.
e domestic hot water connections are placed
on the ange cover (cold inlet and hot outlet)
along with the Magnesium Anode support cap
including the same, supplied as standard for
internal protection of the storage tank unit from
possible corrosion.
N.B.: have the eciency of the storage tank Mag-
nesium Anode checked annually by a qualied
rm. e storage tank unit is prepared for intro-
duction of the domestic hot water pump tting.
1.25 KITS AVAILABLE ON REQUEST.
• System shut-off valve kits with or without
inspection lter (on request). e boiler is
designed for installation of system interception
cocks to be placed on ow and return pipes
of the connection assembly. is kit is very
useful for maintenance because it allows to
empty just the boiler without having to empty
the entire system. Moreover, the version with
lter preserves the functioning characteristics
of the boiler thanks to its inspectionable lter.
• System zone control unit kit (on request). If
the heating system is to be divided into several
zones (max. three), in order to interlock them
with separate adjustments and to keep water
ow rate high for each zone, Immergas supplies
zone system kits by request.
• Polyphosphate dispenser kit (on request). e
polyphosphate dispenser reduces the forma-
tion of lime-scale and preserves the original
heat exchange and domestic hot water pro-
duction conditions. e boiler is prepared for
application of the polyphosphate dispenser kit.
• P.C.B. to a relay (on request) e boiler is pre-
pared for the installation of a P.C.B. to a relay,
which allows to control the main zone using
the CAR (optional).
• Cover kit (on request). If installed outdoors in a
partially protected place with direct air intake,it
is compulsory to mount the appropriate top
protection cover for the correct functioning
of the boiler and to protect it from adverse
weather conditions.
• Recirculation kit (on request). e boiler stor-
age tank unit is prepared for application of the
pump kit. Immergas supplies a set of ttings
and attachments to connect the storage tank to
the domestic hot water system. e pump kit
attachment is also envisioned on the template.
e above-mentioned kits are supplied complete