2.0 INSTALLATION
2.1 MECHANICAL
The BA-200 is installed to a water line by a 2 inch internal diameter tee that is welded or threaded into the
line. Although the BA-200 may be mounted in any orientation, it is suggested that it be mounted
horizontally with the name plate on top. On the tee (Schedule 40 pipe only) is welded a 150-pound (10
bar) Navy, ANSI or DIN flange. The flange is located on the tee so that when the probe body of the BA-
200 is inserted, it will protrude 1/4 to 1/2 inch into the inside diameter of the water line. (Refer to Figure 2
and Figure 11). In the design process, insure that the BA-200 will never sample air and be far enough
down the line so that any air bubbles generated by a pump have time to dissipate. This may mean in
gravity systems the installation of the unit be at a low point in the pipe run or installed in a "trap"
arrangement. Sediment build up will shorten the life of the seals. Insure that the Sensor opening is clear
of any protective covering such as tape. The flanges are then appropriately bolted together. This
completes the mechanical installation.
2.2 ELECTRICAL
* * * * WARNING * * * *
INSURE POWER IS REMOVED FROM ALL WIRING BEFORE ELECTRICAL INSTALLATION IS
ATTEMPTED
* * * * CAUTION * * * *
THIS UNIT CONTAINS STATIC (ESD) SENSITIVE PARTS. OBSERVE PROPER GROUNDING
TECHNIQUES FOR HANDLING OF EQUIPMENT.
The user of the BA-200 must provide a 3/4 inch NPT strain relief that will accommodate their cabling
requirements. The strain relief is inserted into the 3/4" NPT threaded hole in the base plate of the BA-
200. Next refer to Figure 3. With the cover removed, insert the power and external alarm cables through
the strain relief located in the base plate. Route the cables underneath the chassis, around to motor and
locate the connector screw terminal blocks at the rear of the BA-200. Whether using 120 VAC 3 wire or
230 VAC 3 wire, connect the ground (safety, earth) to the ground (#4) screw terminal. If using 120 VAC
50/60 Hz, connect the hot (black) wire to the #6 screw terminal and the neutral (white) wire to the #5
terminal. If using 230 VAC, 50/60 Hz connect the +120 VAC (as measured to ground-safety, earth-) to
the #6 screw terminal. Connect the -120 VAC (as measured to ground-safety, earth-) to the #5 screw
terminal. Tighten all screws. Cabling to the external alarms relay contacts should now be made
according to user requirements to screw terminals NC, NO, and COM (screw terminal 1,2 and 3
respectively). Tighten all screws as required and finally the cable strain relief. The cover should then be
carefully replaced and power applied to the unit. This completes the installation of the BA-200.
The 4-20mA option DOES NOT REQUIRE EXTERNAL POWER. It is self powered; therefore do not
apply 24 or 48 VDC to the 4-20mA leads.
Note: The BA-200 has been calibrated at the factory to you specifications. There is no need to re-
calibrate the unit during pre or post installation. Attempts to re-calibrate the unit may lead to voiding of
the warranty.
4