Installation
Placement
Leave the packaging on the cabinet during handling until
the cabinet is in place. (This is to reduce the risk of
damage to the large side panels.) The floor under the
cabinet may have a drop of max. ±1°. The cabinet
should be positioned so that the waste water can flow
freely from the discharge pipe to the drain in order to
minimise the risk of slipping. Check that the cabinet is
stable.
Note: the cabinet shall be welded on to a founda-
tion. Make sure that the cabinet is installed in level
and that the door closes in a proper way after
welding.
Electrical connection
Electrical connection work must be carried out in ac-
cordance with all relevant standards and regulations.
On installation, the machine must be connected via a
main circuit breaker to keep it separate from the mains,
with a break length of at least 3 mm. Not included in
the delivery.
· Check the rating plate to ensure that the machine’s
operating voltage matches the mains voltage.
· Check that the distribution box is capable of carrying
the required current and that it is adequately earthed.
· Both the power and pilot circuit (where appropriate)
should be fused.The fuses should have the required
rated current in order to deliver the required power to
the cabinet.
· The connection cable must have suffitient length in
order to be able to fold the electrical box forward.
· If you are in any doubt about the effectiveness of the
earthing provisions then the installation must be
checked by a qualified electrician.
· Connect the electrical cables as indicated by the
cable markings and wiring diagram.
· The connection cable must be oil resistant, class
H07RN-F.
· Once the machine has been connected and switched
on, you should check that the mains voltage does
not fluctuate more than 10% from the rated voltage.
Water connection
Cold water with min. pressure 100 kPa (1 bar), max.
pressure 700 kPa (7 bar) and min. flow capacity 0.1 m3/h.
DN15 (G 1/2”) int. thread. Incoming water pipe should
be fitted with a shut off valve. Connected water should
be decalcified.
Basic adjustment of the radiator coupling
Open the valve extremely little. The flow have to be 1 l /
min.
Drainage connection
The cabinet should be placed so that the discharge wa-
ter can flow freely from the discharge pipe to the floor
drain or some other drainage system.
Brine cooling connection
Connect the fluid pipes Ø22 to the brine cooling system
. The installation should be designed to allow effective
ventilation. Make sure that suffitient Brine flow is
reached. for example: Hycool 45: min. 360l/h at Brine
temp. 14°F (-10°C)
Testing
The Selector switch in position 1:
· Both fans start at low speed..
· The steam generator is emptied, before being refilled.
· After 5 min. voltage is supplied to the cooling cir-
cuit’s solenoid valve and the cabinet temperature is
lowered to 36°F(+2°C).
The Selector switch in the cleaning position:
· Both fans start at high speed.
· The steam generator is emptied, before being refilled.
· The steam generator and the air heater start to give
off heat.
Note! The Selector switch should be allowed to stand
for at least 3 min. in one position before being
changed to the other. (See Operation manual)
Accessories
See the Operation manual.
Other documentation
Manufacturer’s Declaration
Operation manual