Normally, once the depth has been reached, the position should be highlighted by
the pile-driver tool so that there is a precise reference point for the penetration of all
the other posts.
4. Installing the posts
Having followed the recommendations above, positioning the poles becomes quick
and precise since:
- the longitudinal width is given by the position of the holes on the beams laying
on the ground
- alignment is guaranteed by the line
- the depth of penetration is given by the reference point on the pile-driver.
The vertical height of the head of the post can be out by +/- 1 cm since there are
special slots for correctly installing the 2-wave beam.
Care should be taken that the pole is absolutely straight in the two directions, and
this achieved using movements shifts of the pile-driver.
5. Installation of the guardrail
The 2-wave beam is then lifted (starting from the bottom of the tract so as to obtain
the correct overlap of the beams).
The bolt for the next post is positioned only when the next beam is overlapped; these
connections are formed of an M12 bolt, a nut, a washer and a rectangular slot
covering plate to be positioned in front of the 2-wave beam.
At this point, it is also possible to fix the bolts (M16x30 TE) joining the beams (8,
complete with nut and washer).