Meyer Burger WHITE User manual

Valid for the following Meyer Burger photovoltaic modules:
MEYER BURGER BLACK
MEYER BURGER WHITE
MEYER BURGER GLASS
Installation and
operating manual

1
1. Introduction 2
1.1 General information 2
1.2 Intended use 2
2. Electrical planning, design and wiring 3
2.1 Scope 3
2.2 CerticationandtechnicaldataofPVmodules 4
2.3 Electrical design and planning 4
2.4 Series connection 4
2.5 Parallelconnection 4
2.6 Combined connection 4
2.7 Safety during electrical installation 5
2.8 Electrical installation 5
2.9 Equipotentialbonding,groundingandlightningprotection 5
3. Technical planning and installation of PV modules 6
3.1 Handling and transport 6
3.2 Installation location 6
3.3 Module positioning 7
3.4 Freedomfromshade 7
3.5 Substructure 7
3.6 Clamping system 8
3.7 Installation types 9
3.8 Fire protection 15
4. Maintenance and cleaning 15
4.1 Maintenance 15
4.2 Cleaning 15
5. Troubleshooting 16
6. Dismantling and recycling 16
Contents

2
1. Introduction
Congratulationsonthepurchaseofyourhigh-eciency
photovoltaicmodule(hereinaerreferredtoasPVmodule)
fromMeyerBurgerIndustries(hereinaerreferredtoasMBI).
MeyerBurgerPVmodulesoerparticularlysustainableand
climate-friendlyenergyproduction,asnogreenhousegases
areproducedinthesolarcellsduringpowergeneration.
MBIstrivesforsustainableproductionofPVmodules.
ThisiswhyMBIfocusesfromtheverystartonhigh-quality
materials,resource-conservingproductionprocesses,
maximumrecyclabilityinthesenseofthecirculareconomy,
reliableandtransparentsupplychainsandoptimisedtransport
routes.MBIPVmodulesenableenvironmentallyfriendly
conversionofsolarenergydirectlyintoelectricalenergy
indenitelyandforseveraldecades.
Alldataandspecicationsinthisinstallationmanualare
preliminaryandsubjecttochangeatanytime.
Thelatestversionisalwaysavailableat
www.meyerburger.com.
1.1 General information
•Beforeinstallingthephotovoltaicsystem(PVsystem),
requestinformationfromtherelevantlocalauthorities
andenergysuppliersabouttheapplicableguidelinesand
approvalrequirements.Takingtheserequirementsinto
accountistheonlywaytoensureeconomicsuccess.
•Keeptheinstallationmanualfortheentireservicelifeof
thePVmodules.
•Makesurethatthisinstallationmanualisaccessibletothe
operator at all times.
•Handovertheinstallationmanualtoanysubsequentowner
oruserofthePVmodules.
•Pleaseobservetheotherapplicabledocuments.
•Removetheadhesivetapeontherearforsecuringthe
cables and connectors before installation.
1.2 Intended use
ThisinstallationmanualisvalidinAfrica,Asia,Europe,
LatinAmericaandSouthAmerica.Theinstructionsprovide
informationonhowtohandleMBI’shigh-performance
crystallinePVmodulessafely,aswellasoninstallation,
assembly, cabling, maintenance and recycling.
NOTE
Deviations from the installation manual and modications
to the module will invalidate the warranty and guarantee.
Please refer to the warranty conditions for further details.
Toensurethatyoucanusethefullpower
oftheMBIPVmodules,pleaseread
andobservethefollowinginstructions
carefully. Failuretoobservethe
instructions can lead to personal injury
and material damage.Thisinstallation
manualdescribesthesafeinstallationof
theMBIPVmodules.
Observeallrequiredlocal,regional
and national (safety)regulationsand
ordinances,aswellasalltechnical,
electrical and structural standardswhen
designingandinstallingthePVsystem.
Occupational safety regulations must be
observedandoccupationalhealthand
safety must be guaranteed at all times.
Aphotovoltaicmoduleisanelectrical
product.Thereisariskofelectricshock
intheeventofincorrecthandlingand
installation.Allworkmayonlybecarried
outbyqualiedspecialistpersonnel.

3
2. Electrical planning, design and wiring
2.1 Scope of application
ThePVmodulesaresuitableforthefollowingapplications:
•Operatingambienttemperature-40°Cto+45°C
•Moduleoperatingtemperature-40°Cto+85°C
•Pressureloadsofmax.6,000Paandtensileloadsofmax.
4,000Pa(includingsafetyfactor1.5)*
TheassemblytakesplaceonasubstructureforPVmodules.
*dependingonassemblyvariants(see3.7Installationtypes)
Le side: MEYER BURGER GLASS–Dimensions
Right side: MEYERBURGERBLACK/WHITE–Dimensions
Observeallrequiredlocal,regional
and national (safety)regulations and
ordinances,aswellasalltechnical,
electrical and structural standardswhen
designingandinstallingthePVsystem.
1200
Cable length
8x3.5 (8x)
Drain holes
Ø4.5 (8x)
Grounding
holes
1041
17
115
115
Dimensions
in mm
1722
11
22
35
1041
26
(Distance between mounting
and grounding holes)
989
115
1200
Cable length
Dimensions
(mm)
8x3.5 (8x)
Drain holes
Ø4.5 (8x)
Grounding
holes
Ø9 (4x)
Mounting
holes
115
(distance between mounting holes) 320
1127
1767
12
35
35

4
2.2 Certication and technical data of PV modules
ThePVmodulesaretestedandapprovedaccordingto
IEC61215-2016andIEC61730-2016.Pleaserefertothe
correspondingdatasheetsforthefurtherlistofcurrent
availablecerticates,aswellasalltechnicalandelectricaldata.
Thesecanbefoundonourwebsite
www.meyerburger.com.
2.3 Electrical design and planning
•MeyerBurgerPVmoduleshavethreepre-installedbypass
diodes(non-replaceable)thatensureprotectionand
improvedperformanceintheshade.
•ItisadvisabletoonlyconnectPVmodulesofthesame
module line and performance class.
•Whendesigningthephotovoltaicsystem(PVsystem)and
itscomponents,asafetyfactorof1.25fortheelectrical
variables(VOC, ISC)mustbeobserved,asamodulecan
supplyahighercurrentand/orhighervoltagethanunder
standardised test conditions due to special ambient
conditions.FortheMEYERBURGERGLASSmodule,use
highersafetyfactorsdependingontheapplicationdueto
thebifaciality.
•ItisrecommendedtouseUVresistantPVcables.These
musthaveaminimumcross-sectionof4mm2(12AWG)
andbeheat-resistantuptoatleast90°C(194°F).
•Identicalconnectionplugs(samemanufacturer,
sameplugtypes)mustbeusedfortheextensionand
connectioncables.MBIusesdierentplugtypes.
Theseareindicatedbynumberingonthemodulelabel.
Pleaserefertotheexplanationonthedatasheetforthe
corresponding plug type.
•Shadingmustbeavoidedinordertoachieveoptimalsolar
radiation and maximise yield.
•Theindividualsystemcomponents(PVmodules,fuses,
inverters,etc.)mustbecoordinatedaccordingtotheir
datasheets.
2.4 Series connection
•ThePVmodulescanbeconnectedinseriestoachieve
thedesiredtotalvoltage.
•Thecurrent(IMPP)ofthePVmodulesconnectedinseries
shouldbeidentical,asthemaximumcurrentisdetermined
bythemodulewiththelowestcurrent.
•Themaximumsystemvoltagemustbeobservedandcan
befoundinthecorrespondingmoduledatasheet.
2.5 Parallel connection
•ThePVmodulescanbeconnectedinparalleltoachieve
thedesiredtotalcurrent.
•Thevoltage(VMPP)ofthePVmodulesconnectedin
parallelshouldbeidentical.
•Thecablecross-sectionoftheextensioncablemustbe
adaptedtothemaximumcurrentcapacityofthewiring.
•Topreventreversecurrent,anovercurrentprotection
deviceisalsorequired(e.g.blockingdiodesorstringfuse).
• Withoutstringfuse,amaximumoftwostringsmaybe
connectedinparallel.Pleaseobservethevaluespeciedin
therelevantdatasheetfortheovercurrentprotectionrating.
2.6 Combined connection
•Allcomponentsmustbecoordinatedwitheachother.
Theindividualconnectioninstructions,seriesandparallel
connection,mustbeobserved.
•ThesamenumberofPVmodulesmustbeconnectedin
series(identicalstringvoltage).
• Additional safety precautions must be implemented to
protectthecablesandPVmodulesfromreversecurrent.
Observeallrequiredlocal,regional
and national (safety)regulations and
ordinancesaswellasalltechnicaland
electrical standardswhendesigningthe
PVsystem.

5
2.8 Electrical installation
• Thecablesandplugsmustberoutedsothattheyare
protected against moisture.
• Thecablesandplugsmustnotlieonthesubstrate,
theroofsurfaceortheground.
• Thecablesandplugsmustberoutedsothattheyare
protectedagainstUVradiation.
• Thecablesandplugsmustbeprotectedagainst
animal bites.
• Connectionsthatarenotpluggedinmustbeprotected
from dirt and moisture during transport, storage and
duringtheinstallationperiod,asonlyplugged-in
connectionsmeettheirrespectiveprotectionclass.
• Observethepolarityofthecablesandplugsduring
connection.
• PVmodules,junctionboxes,cablesandplugs
mustbecheckedfordamageandcontamination.
Only undamaged components may be installed.
• Theminimumbendingradiusofthecableandstrainrelief
mustbetakenintoaccount.
• Thecablesmustnotberoutedoversharpedgesand
cornerswithoutprotection.
• Alwaysconnectthecableswithasuitableidenticalplug,
donottrapthemandprotectthemfrommechanicalstress.
• Ensurethatthecablesareroutedsothatthereare
noloops(minimisetheriskofinductionduring
thunderstorms).
• ItisrecommendedtoplacePVmoduleswiththesame
orientationandinclinationinastringtoachieve
maximum yields.
• Connectthemodulestringtoaninvertersuitable
forthelayout.
2.9 Equipotential bonding, grounding and lightning
protection
•Therearegroundingholesonthemoduleframesfor
connectingthePVmodulegroundingandtheseare
markedassuch.Pleaserefertothecorrespondingmodule
datasheetforthepositionofthegroundingholes.
Properequipotentialbondingofthe
system components must be ensured
inaccordancewiththelocallyapplicable
guidelines, regulations and standards.
ThePVmodulegrounding must be
implementedinaccordancewithnational,
regional and local guidelines, regulations
and standards.
2.7 Safety during electrical installation
Thefollowingsafetyinstructionsmustbeobserved
atalltimes:
• Workmayonlybecarriedoutbyqualiedpersonnel.
• Theapplicablesafetyinstructionsandregulations
mustbeobserved.
• Evenwithlowlighting,theopencircuitvoltage(VOC)
is applied.
• DonottouchthePVmoduleswithbarehands.
• Donotwearmetallicjewellerywhenworkingwiththe
PVmodules.
• Usedryandinsulatedtoolsandinsulatinggloves.
• ThePVmodulesmustbedry,cleanandfreeof
damage during installation.
• DonotmodifythePVmodules.
• NeverconnectordisconnectPVmodulesunderload.
Thereisariskofelectricarc.
Theexistinglightningprotectionconcept
ofthebuildingmustbeobserved.
ThepotentialintegrationofthePVsystem
intothelightningprotectionconcept must
beagreedwiththecorrespondinglightning
protection expert. National, regional and
local guidelines, regulations and standards
mustbecompliedwithatalltimes.
Recommended mounting type for grounding connection
M4 screw
Washer
Serrated washer
Grounding cable lug
Washer
Washer
M4 nut

6
3. Technical planning and installation of PV modules
3.1 Handling and transport
•Modulepalletsshouldonlybeloadedandmovedusing
suitableforklis.
•Theforklitruckmusthaveaminimumforklengthof
1.20m,aforklengthof1.75misrecommended.Theforks
mustbeselectedandplacedsothattheydonotcomeinto
contactwiththePVmodulesunderanycircumstances.
•Rideoverunevensurfacesslowly.
•Itisrecommendedtomovethepalletsoneatatimeand
notinadoubledeck.
•Palletsmaybestoredonadoubledeck(maximum2pallets
ontopofeachother).OnlytheoriginalMeyerBurger
palletsarepermittedforstacking.Itisessentialtoensure
thatthepalletsarepositionedexactlyontopofeachother.
•Nothird-partyproductsmaybeplacedorstackedonthe
palletsandPVmodules.
•Furthertransportrecommendationscanberequested
from Meyer Burger.
•ThePVmodulesmayonlybetouchedonthemodule
framewithcleangloves.
•WhenunpackingthePVmodules,thefrontsidemustbe
protectedagainstscratches,etc.
•ThecablesofthePVmodulesmustnotbeshort-circuited
(connected)underanycircumstances.
•Itisprohibitedtohandleandcarrythemodulebythe
cables and junction boxes.
•ClimbingonthePVmodulesandotherpointloads
(e.g.carryingthePVmodulesbytheirheadorback)
isprohibited,asthiscanleadtoirreversibledamage
tothePVmodules.
•Donotplacetoolsorotherobjectsontopofordropthem
ontothePVmodules.
•ThePVmodulesmustbestoreddryandprotectedfromthe
weatheruntilinstallation.Thetransportpalletsdonotprovide
sucientprotectionforoutdoorstorageofthePVmodules.
•WhenunpackingthePVmodulesfromthepallet,the
stabilityofthePVmodulesandpalletmustbeensured.
ThepalletandPVmodulesmustbesecuredagainst
fallingover.
•Thepackagingmustbedisposedofproperly.
3.2 Installation location
Thefollowinginformationontheinstallationlocationmustbe
observed:
ThePVmodulesmustnotbeinstalled:
• In enclosed spaces
• Over2,000mabovesealevel*
• Onwatersurfaces*
• Inplaceswherewatercanaccumulate(e.g.ooding)
• Nearhighlyammablegasesorvapours
(e.g.gastanksorllingstations)
• Inplaceswherecontactofchemicalsubstances
(e.g.oilorsolvents)withpartsofthePVmoduleispossible
• Nearopenamesorammable/explosivematerials
• Intheimmediatevicinityofairconditioning
andventilationsystems
• ThePVmodulesmustnotbeusedasareplacement
forroofcoveringsorfacades.
• Forinstallationscloserthan500mtothesea,special
precautionsmustbetakenwithregardtogrounding,
maintenance and cleaning.
• ThePVmodulesmustnotbeindirectcontactwithsaltwater.
• Thereisanincreasedriskofcorrosionwheninstalling
PVmodulesinsaltyorammonia/sulphurousenvironments.
• UseofPVmodulesonmobileunitssuchasvehiclesand
shipswillvoidanyliabilityandwarrantyclaims.
• TheuseofPVmodulesforBIPVapplications(building-
integratedphotovoltaics)isnotpermitted*.
• TheuseofPVmodulesinconcentratedlightapplications
isprohibited.
*Installationabove2,000mabovesealevel,onwatersurfacesorinBIPVapplications
requiresconsultationwithandexplicitapprovalfromthemanufacturer.

7
3.3 Module positioning
•ThePVmodulescanbeinstalledinlandscapeorportrait
format.
•Ensurethatthereisnowaterbuild-up.Rainandmeltwater
must be able to drain freely.
•Thedrainageopeningsinthemoduleframemustnotbe
coveredorsealed.
•ThePVmodulesmustbeinstalledwithaminimum
inclinationangleof5°.
•Themaximumpermittedinclinationanglemustbe
determinedinaccordancewiththelocallyapplicable
regulations.
•Aninclinationanglegreaterthan20°hasapositiveeect
ontheself-cleaningofthePVmodules.
•Theremustbenoobjects(airoutlets,antennas,etc.)
onthebackofthemodulethatcouldleadtopointloads
whenthePVmodulesbend.
3.4 Freedom from shade
Optimalsolarradiationresultsinmaximumenergyyield:
•InstallthefrontofthePVmodulesfacingthesolar
radiation.Theelectricalconnectionboxislocatedonthe
rearofthePVmodule.
•Shadingandpartialshading(e.g.trees,chimneys,buildings,
dirt,snow,overheadlinesetc.)shouldbeavoided.
•InthecaseofbifacialPVmodules,itmustbeensuredthat
shadingcausedbythesubstructureontherearofthe
moduleisavoidedorminimised.
•Inthecaseofstrongorinhomogeneousshading,theuse
ofoptimizersinthesystemmaybeadvantageous.
3.5 Substructure
•ThestructureorsubsurfaceonwhichthePVsystemis
installedmustbeabletoabsorbtheresultingstaticloads.
•Thesubstructuremustbeabletoabsorbtheforcesacting
onthemodule.
•Thestaticsofthesubstructuremustbedesigned
accordingtothelocalsnowandwindloads.
•Inadditiontothewindandsnowloads,noforces
mayactonthemoduleviathesubstructure.
• Thesubstructuremustbeproperlyxedtotheroof
ortheoor.
• Unevensnowloads(e.g.snowoverhangs,snowdris)
thatleadtolocalincreasesinloadsmustbeeliminatedor
preventedbytechnicalmeasures.
• Thesubstructuremustensureadequatecoolingthrough
rearventilationofthePVmodules.
• Thexingmustbestress-freetoallowfortemperature-
relatedchangesinlength.
• Aminimumdistanceof5mmbetweenthePVmodulesis
recommended.
• ThePVmodulescanbefastenedusingclampsorinsert
rails.TheMEYERBURGERWHITEandMEYERBURGER
BLACKPVmodulescanalsobefastenedusingascrew
connection(pointconnection)(seetableinSection3.7).
• Theremustbenocomponentsbetweentheprolesofthe
substructureandthePVmodules.
• Sharpedgesandpointloadsofthesubstructureunderthe
PVmodulesmustbeavoided.
• Additionalstressesandtorquesatthemountingpositions
arenotpermitted.Itmustbeensuredthattheclampsor
insertionrailsdonottouchtheglass,evenunderload.
• Adistanceofatleast50mmfromthesubstructureand
otherhardstructuresunderthejunctionbox(exceptfor
mountingvariantCP2)mustbeensured.
• Makesurethatthecablescannotbepinchedbetween
laminateandcarrierrailunderhighcompressionload.
Routingthecablealongthemoduleframeisrecommended.
• Contactbetweendierentmetallicmaterialsmustbe
avoided(contactcorrosion,observeelectrochemical
series),e.g.itmustbeensuredthatthefasteningscrews
andwashershavethesamematerialproperties.
• Corrosion-resistantscrewsandwashersmustbeusedfor
installation.
Local,country-specicbuilding
regulationsmustbeobserved.

8
3.6 Clamping system
Clampsthatmeetthefollowingrequirementsmustbeused:
• Minimumclampingwidth40mm
• Clampingheightfor35mmframeheight
• Clampingdepth7–11mm
• Staticrequirementsoftherespectivesite
• Long-termstableclamps
• Theclampsmustnottouchthefrontglass.
• Theclampsmustnotcastshadeonanycells.
• Theclampsmustnotdamageordeformtheframe
ofthemodule.
• Clampsmustbeattachedtothesubstructureasspecied
bythesubstructuremanufacturer,includingspecic
hardwareandtorquerequirements.Amaximumtorque
of20Nmmustnotbeexceeded.
• Themoduleframemustnotberemovedormodied.
Drillingadditionalholesonthemoduleframeisnot
permitted.Changesofanykindwillvoidthewarranty.
Clamp depth
Clamp width
Clamp height
Middle clamp
End clamp
Example of end and middle clamp

9
3.7 Installation types
Theoverviewtableshowsallpermissibleinstallationtypes
includingtheassociatedtestloadsaccordingtoIEC61215.
Thefollowingtablesshowindetailthedierentassembly
variants(sketches),thepermissibleassociatedxingareas
andthecorrespondingmaximumpressureandsuctionloads.
Suitablefasteningvariantscanbedevelopedinconsultation
withMBIforassemblywithunspeciedinstallationtypesor
withincreasedloads.
Legend:
CP: Clamppoint
CL: Clampline
MP: Mountingpointonframe
IP: Installationprole/Insertionprole
…1: Installationonlongmoduleside
…2: Installationonshortmoduleside
Module Installation type Design load Test load (1.5x safety)
WHITE BLACK GLASS Name L [mm] W [mm] Pressure [Pa] Suction [Pa] Pressure [Pa] Suction [Pa]
x x x CP1
320 4000 2666 6000 4000
200-450 3600 1600 5400 2400
0-550 1600 1600 2400 2400
x x x CP1a
200-450 3200 1600 4800 2400
0-550 1600 1600 2400 2400
x x x CP2 160-210 1600 1600 2400 2400
x x x CP2a 0-300 1600 1600 2400 2400
x x x CL1
320 3600 2666 5400 4000
200-450 3600 1600 5400 2400
0-550 1600 1600 2400 2400
x x x CL2 0-300 1600 1600 2400 2400
x x x IP1 3600 2666 5400 4000
x x x IP2 1600 1600 2400 2400
x x MP1 320 4000 2666 6000 4000
x x MP1a 320 3600 1600 5400 2400

10
INSTALLATION TYPE CP1
Fasteningwith4moduleclampsonthelongmoduleside,
pointmountingwithcontinuoussubstructurerails
PERMISSIBLE LOADS (PRESSURE, SUCTION)
CP1 Design load Test load (1.5x safety)
Module L [mm] Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
320 4000 2666 6000 4000
200-450 3600 1600 5400 2400
0-550 1600 1600 2400 2400
INSTALLATION TYPE CP1a
Fasteningwith4moduleclampsonthelongmoduleside,
pointmountingwithoutcontinuoussubstructurerails
PERMISSIBLE LOADS (PRESSURE, SUCTION)
CP1a Design load Test load (1.5x safety)
Module L [mm] Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
200-450 3200 1600 4800 2400
0-550 1600 1600 2400 2400
= Clamp point
LL
= Clamp point

11
INSTALLATION TYPE CP2
Fasteningwith4moduleclampsontheshortmoduleside,
pointmountingwithcontinuoussubstructurerails
PERMISSIBLE LOADS (PRESSURE, SUCTION)
CP2 Design load Test load (1.5x safety)
Module W
[mm]
Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
160-210 1600 1600 2400 2400
INSTALLATION TYPE CP2a
Fasteningwith4moduleclampsontheshortmoduleside,
pointmountingwithoutcontinuoussubstructurerails
PERMISSIBLE LOADS (PRESSURE, SUCTION)
CP2a Design load Test load (1.5x safety)
Module W
[mm]
Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
0-300 1600 1600 2400 2400
W W
= Clamp point
= Clamp point

12
INSTALLATION TYPE CL1
Fasteningwith4moduleclampsonthelongmoduleside,
linemountingalongthelongmoduleside
PERMISSIBLE LOADS (PRESSURE, SUCTION)
CL1 Design load Test load (1.5x safety)
Module L
[mm]
Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
320 3600 2666 5400 4000
200-450 3600 1600 5400 2400
0-550 1600 1600 2400 2400
INSTALLATION TYPE CL2
Fasteningwith4moduleclampsontheshortmoduleside,
linemountingalongtheshortmoduleside
PERMISSIBLE LOADS (PRESSURE, SUCTION)
CL2 Design load Test load (1.5x safety)
Module W
[mm]
Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
0-300 1600 1600 2400 2400
L
W
= Clamp point
= Clamp point

13
INSTALLATION TYPE IP1
Fasteningvialinemountingwithinsertprolerails
onthelongmoduleside
PERMISSIBLE LOADS (PRESSURE, SUCTION)
IP1 Design load Test load (1.5x safety)
Module Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
3600 2666 5400 4000
INSTALLATION TYPE IP2
Fasteningvialinemountingwithinsertprolerails
ontheshortmoduleside
PERMISSIBLE LOADS (PRESSURE, SUCTION)
IP2 Design load Test load (1.5x safety)
Module Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK,
GLASS
1600 1600 2400 2400

14
INSTALLATION TYPE MP1
Fasteningtothemountingpointsonthelongmoduleside,
pointmountingwithcontinuoussubstructurerails
PERMISSIBLE LOADS (PRESSURE, SUCTION)
MP1 Design load Test load (1.5x safety)
Module L
[mm]
Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK 320 4000 2666 6000 4000
INSTALLATION TYPE MP1a
Fasteningatthemountingpointsonthelongmoduleside,
linemountingalongthelongmoduleside
PERMISSIBLE LOADS (PRESSURE, SUCTION)
MP1a Design load Test load (1.5x safety)
Module L
[mm]
Pressure
[Pa]
Suction
[Pa]
Pressure
[Pa]
Suction
[Pa]
WHITE,
BLACK 320 3600 1600 5400 2400
RecommendedmountingmethodatthemountingpointsoftheMP1andMP1ainstallationvariants
M8 nut
M8 bolt
Retaining ring
Washer
Washer
Mounting rail
L
L
= Mounting point
= Mounting point

15
3.8 Fire protection
• Wheninstallingontheroof,thePVmodulesmayonly
beinstalledoverare-resistantroofcover("hardroof").
Thisexcludesthein-roofinstallationofthePVmodules.
4. Maintenance & cleaning
4.1 Maintenance
•Itisrecommendedtohavethesystemcheckedregularly
(annually)byaninstaller.Theinspectionintervalmayvary
depending on local circumstances/conditions/regulations.
•Checkglasssurface,frameandconnectionsfordamage.
•Checktheelectricalcomponentsforcorrosionandgood
connection contact.
•Ifamoduleneedstobereplaced,observetheinstructions
fordisassemblyandassembly(seeSections3and6).
Thereplacementmoduleshouldhavethesameelectrical
properties.
•Aeranunusualweatherevent(storm,hail,alotofsnow,
etc.),themodulesmustbecheckedfordamage.
•ThevegetationunderthePVmodulesmustbecutback
regularlytoavoidshadingonthePVmodules.
4.2 Cleaning
•Usesucientwaterandasoclothtocleanthe
PVmodules.
•ThePVmodulesmustonlybecleanedmanually.
•Donotusehigh-pressurecleanersforcleaning.
•AllowthePVmodulestocooldownbeforecleaning.
•Nevertouchglasswithbarehandsasthismayleave
ngerprints.
•Theuseofaggressivecleaners,ethanolandisopropanol,
dilutedalcohol,acetoneandanychemicalcleaning
agentsisnotpermitted,asthismaydamagetheanti-
reectivecoating(ARC)ofthemodule.
•Theuseofacids,alkalis,bleachpowdersandstrongbases
is not permitted.
•Theingredientsofcleaningproductsshouldbechecked
before use.
•Donotusedeionizedwaterforcleaning.
•Theuseofabrasivecleaningagentssuchassanding
powder,steelwool,scrapersandsteelcleaning
equipment is not permitted.
•Careshouldbetakenwhencleaningifsandorheavy
soilingispresenttoavoidscratches.
•Toremoveheavysoiling,usegenerousamountsofwater
beforewipingtheglasssurface.Stubborndirtshouldbe
soakedifnecessary.
•Carefullyremoveleaves,snow,iceorotherloosedirtwith
asobroom.
•Damagetotheanti-reectivecoating(ARC)dueto
impropercleaningwillvoidtheperformancewarranty.
Improper installation can lead to res/
rehazards.Observeallnecessarylocal,
regional and national buildingandre
protectionregulations,ordinancesaswell
asalltechnical,electricalandstructural
standardswhendesigningandinstalling
thePVsystem.

16
5. Troubleshooting
Contact details can be found at www.meyerburger.com
6. Dismantling and recycling
•Whendisassemblingthesystem,the(dis)assembly/
installationmanualfortheotherinstalledsystem
componentsmustbeobserved.
•Thevesafetyrulesofelectricalengineeringmust
beobserved.
•Theinvertermustbeswitchedoanditsswitch-otime
intervalobserved.
•ThePVmodulesmustbedisconnectedfromtheinverter.
Itisessentialtoensureandcheckthattheinverteris
de-energised.
•Theplugsmustonlybedisconnectedwithsuitable
specialist tools.
•Checkthecomponentsfordamage.
•PVmodulesandsubstructuremustbedisassembled
withsuitablespecialisttools.
•PVmodulesandothercomponentsmustbepackaged
forsafetransport.
•Themodulesmustbedisposedofinaccordance
withlocalregulations.
•ThefollowingappliesinGermany:PVmodulesare
collected at recycling centres and recycled by our partner
taken-e-away.www.take-e-away.de
Meyer Burger (Industries) GmbH
Carl-Schiner-Strasse17
09599Freiberg
Germany
www.meyerburger.com WEEEreg.no.DE18170271
Asof:December2022Revisionnumber:2.1
Theworkmayonlybecarriedout
byqualiedpersonnel.
Theinstallerorthetechnicalcustomer
serviceofMBImustbecontactedinthe
eventofamalfunctionofthePVsystem.
Nevertrytoremedythefaultyourself,
especiallyintheeventofglassbreakage.
Thereisariskofelectricshock.
This manual suits for next models
2
Table of contents
Popular Solar Panel manuals by other brands

Photonic Universe
Photonic Universe SWD-FWP-60M instruction manual

Solaria
Solaria PowerXT R-PD Series Safety, installation, and operation manual

Yingli Solar
Yingli Solar YGE G/G 60CL/F Series Installation and user manual

Wasserstein
Wasserstein Solar Panel for Blink Video Doorbell user manual

Anker
Anker PAP 22 installation manual

ReVIVE
ReVIVE Solar ReStore XL+ user guide

FuturaSun
FuturaSun FU M ZEBRA Series Safety and installation manual

evergreensolar
evergreensolar Cedar Line Operation manual

Sun Power
Sun Power SPR-E Series Safety and installation instructions

Sun-Tech
Sun-Tech STP410S-A manual

Cool-sky
Cool-sky Apricus installation manual

CanadianSolar
CanadianSolar BiHiKu6 Mono CS6Y-550MB-AG manual