Modulift CMOD 250 User manual

User Instructions
The CMOD Spreader Frame is modular in span and every frame consists of 4 Corner Units,
with intermediate Struts that can be bolted into the assembly to achieve dierent spans.
Personnel using this system should be suitably trained, competent and have a clear
understanding of Safe Slinging procedures.
The use of Modulift equipment must be in accordance with the procedures laid down in
‘Lifting Operations and Lifting Equipment Regulations 1998’ (LOLER).
Never exceed stated WLL – Adhere to WLL in Table 2 for particular sling angle used.
The top sling length is critical to the safe use of the spreader – Ensure you refer to the correct table.
WARNING!
β = Sling to vertical angle (STV)
CMOD 250 Spreader Frame
CMOD 250 has an assembled span ranging from 2m by 2m to 20m by 20m and all spans inbetween.
CMOD 250 Frame Specication
Rated at a maximum of 300 tonnes WLL.
Please see Table 2 for WLL at specic spans.
‘Sling to Vertical’ angle, β, 45 degrees or less.
Corner Units are rated at 75 tonnes each
(300 tonnes combined capacity).
Bolt tightening torque: 250Nm. Spanner size required: 36mm.
Recommended additional equipment: Torque Wrench, Podger Spanner and Ring Spanner.
P8P2–P6
Span
β
P7
P1 P9
Table 1 – Component List
Part Ref. Description Weight/item
P1 Corner Unit(length 1m each) 1190kg
P2 6.0m Strut 860kg
P3 3.0m Strut 495kg
P4 2.0m Strut 375kg
P5 1.0m Strut 255kg
P6 0.5m Strut 192kg
P7 150t Heavy Duty Shackle 160kg
P8 125t Wide Body Shackle 92kg
P9 M24 x 80, Grade 8.8, HT Bolts, Nuts & Washers
Strut Corner Unit
Assembled
Frame
Fig. 1 – Typical CMOD Spreader Frame Assembly

User Instructions
Should you nd your equipment is no longer of use,
please dispose of in a responsible manner. Please
contact Modulift if you need further guidance
Table 2 – Load v Span
First pick the span required for your frame (e.g.
2m x 5m) and the Sling Angle (we recommend 30°
STV where possible), then check the WLL via the
appropriate table. Read the table by locating the
lower span on the y axis of the chart and the larger
on the x. The cell which you are referred to, will
indicate the WLL for your chosen span. If your exact
span is not noted in the table, then please round up
or down to the values that will give you the lowest
WLL (to ensure no overloads are applied). Please
contact Modulift for conrmation on your WLL if
required. WLL given in tonnes.
© Copyright 2019 Modulift.
All rights reserved.
Assembly Procedure
Check the ID plates on each Modulift component to
ensure the correct size is used.
Lay out the Struts and Corner Units in the correct
conguration.
Check that all anges are clear from debris, sand etc.
before connection.
Bolt the components together* using bolts, nuts & washers
provided. Tighten the bolts to torque as shown overleaf.
Loop the top Shackles through the bows of the Corner
Units so they contact ‘bow-to-bow’. The eye of the top
slings can then be passed through the jaws of the Shackles
and the pins replaced.
Loop the bottom Shackles through the eyes of the drop
slings and connect to the bottom of the Corner Unit with
the Shackle pin.
Attach the lower slings to the load to be lifted.
The assembled Spreader Frame and lifting rig must be
thoroughly checked by a competent person prior to lifting.
*The use of a Podger Spanner will aid in assembly by helping
to align the bolt holes by forcing it through.
Do’s & Don’ts
Do ensure that the frame is only loaded at the Corner Units
and they are all equally loaded.
Do ensure enough clearance between frame and the load
to prevent the load hitting the frame. Any collision could
cause failure of the frame.
Do not undertake a lift without the correct use of
appropriate top slings.
Do not hang any loads from the Strut tube or anges.
Do not exceed the stated WLL for your span.
Do not rig the lower slings more than 6° from vertical.
WARNING!
Do not under any circumstances hang load(s) from the
tube or anges – the Spreader Frame is designed for
compression – not bending.
Ensure that the top Shackle contacts the bow of the corner
plate ‘bow-to-bow’.
The CMOD system is designed in accordance with BS
EN13155: Cranes, Safety, Non- xed Load Lifting Attachments.
Max number of Struts allowed in assembly: 5 per side
Assemble longer Struts in the centre of the conguration
Sling angle is crucial to safe use of frame.
The top sling must be positioned centrally in the Shackle
pin to ensure even loading. Contact your Modulift
supplier for supply of loose spacers where required.
CMOD 250 UK JAN 2019
CMOD 250 Spreader Frame
20 170
19 190 165
18 210 185 160
17 230 205 180 155
16 245 225 200 175 155
15 265 240 215 195 170 150
14 280 255 230 210 190 165 145
13 295 270 245 225 205 185 165 140
12 300 280 260 240 220 200 180 160 140
11 300 295 270 250 230 210 195 175 155 135
10 300 300 280 260 240 225 205 190 170 150 135
9300 300 290 270 250 235 215 200 185 165 150 130
8300 300 300 280 260 245 225 210 195 180 165 145 130
7300 300 300 285 265 250 235 220 205 190 175 160 145 125
6300 300 300 290 270 255 240 230 215 200 185 170 155 140 125
5300 300 300 290 275 260 245 235 220 210 195 185 170 155 140 125
4300 300 300 290 275 265 250 240 230 215 205 195 180 165 155 140 120
3300 300 300 290 275 250 235 220 210 200 195 190 185 180 165 150 135 120
2300 300 300 265 235 215 200 195 185 185 180 175 175 170 170 165 150 135 120
Span
(m) 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
CMOD 250: WLL / tonnes @ 30° STV
20 95
19 105 95
18 120 105 90
17 130 115 100 85
16 140 125 115 100 85
15 150 135 120 110 95 85
14 160 145 130 120 105 95 80
13 170 155 140 125 115 105 95 80
12 170 160 150 135 125 115 100 90 80
11 170 170 155 140 130 120 110 100 85 75
10 170 170 160 150 135 125 115 105 95 85 75
9170 170 165 155 140 135 120 115 105 95 85 75
8170 170 170 160 150 140 125 120 110 100 95 80 75
7170 170 170 160 150 140 135 125 115 105 100 90 80 70
6170 170 170 165 155 145 135 130 120 115 105 95 85 80 70
5170 170 170 165 155 150 140 135 125 120 110 105 95 85 80 70
4170 170 170 165 155 150 140 135 130 120 115 110 100 95 85 80 65
3170 170 170 165 155 150 145 140 135 125 120 115 105 100 95 85 75 65
2170 170 170 160 155 150 145 140 135 130 125 120 115 105 100 95 85 75 65
Span
(m) 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
CMOD 250: WLL / tonnes @ 45° STV
Popular Industrial Equipment manuals by other brands

Sonny's
Sonny's Pendulum 807W Combo owner's manual

Festo
Festo DHEF A-RA1 Series instructions

ABB
ABB XAC25849 Operation manual

Ansul
Ansul AUTOMAN II-C Installation, operation and maintenance manual

MADDALENA
MADDALENA ArrowWAN MVM wM-Bus 169 Instructions for installation, use and maintenance

Siemens
Siemens ASK41NF04SP Mounting instructions