RVE SMP-12 User manual

RECHARGE VÉHICULE ÉLECTRIQUE2
TABLE OF CONTENTS
INTRODUCTION 3
DIAGRAM OF PANEL ENCLOSURE 4
DIMENSIONS 5
DESCRIPTION 6
INSTALLATION STEPS 6
INSTALLATION EXAMPLES 9
ENGLISH
WARNING
Field electrical installers must follow proper safety precau-
tions and all local electrical code requirements during elec-
trical installation, wiring, and CT installation. During normal
operation of this device, hazardous voltages are present
which can cause severe injury or death. It is strongly recom-
mended that only qualified, properly trained personnel should
perform installation and servicing.
NO-RESPONSIBILITY DISCLAIMER
The information presented in this publication has been care-
fully checked; however, Recharge Véhicule Électrique (RVE)
assumes no responsibility for inaccuracies. The information
provided in this document is subject to change without notice.
AFTER-SALES SERVICE
To report any issue, please contact RVE by email at
support@rve.ca. Prior to returning any merchandise to RVE,
a return material authorization (RMA) number should be ob-
tained from RVE.
STATEMENT OF CALIBRATION
The accuracy and calibration of the instruments presented
in this document are traceable to Measurement Canada, a
division of Innovation, Science and Economic Development
Canada.
CONFIGURATION
The Smart Metering Panel can only be configured by Intellime-
ter Canada Inc. at its factory and according to the customer’s
provided panel schedule.
INSTALLATION CHECKLIST
Make sure that you have received the right SMP as per your
order and packing list. If you receive a damaged product,
possible.
INSTALLATION DISCLAIMER
RVE does not accept any responsibility and will not be liable
for any loss, damage or expense of any kind whatsoever and
howsoever caused by improper installation of its products,
be it indirect, special, incidental or consequential damages
(including but not limited to damages for loss of business,
loss of profits, interruption or the like). The SMP is compa-
tible with the majority of Electric Vehicle Supply Equipment
(EVSE) available on the market, however it is the customer’s
responsibility to ensure the compatibility of all the EVSEs
functionalities with the panel’s load shedding.
REGULATORY REQUIREMENTS
Installer is responsible for ensuring that all safety and local
electrical codes are followed.
WARRANTY
Internet connection required (minimum 1 Mbps upstream
and downstream) to access the panel’s power consump-
tion reports and activate the manufacturer’s warranty. The
warranty is valid against defects in the built-in controls for
one year from the date of delivery, provided that the panel
is connected to the Internet and can be accessed remotely.
The warranty is limited to the equipment and components
supplied by RVE Inc. The installer of the panel is responsible
for providing after-sales service to the end customer and for
on-site visits if necessary.

RECHARGE VÉHICULE ÉLECTRIQUE3
Computer Module
(DCU)
Meter Module
(Measurement Canada certified)
Relay BoardRelay Controller EVSE
Main CTs
CT
CT
Support service and consumption
reports sent by email
INTRODUCTION
The Smart Metering Panel, hereafter referred to as SMP, ma-
nages Electric Vehicle Supply Equipment (EVSE) power flow
to optimize existing electrical assets and maintains opera-
tional power limits. The SMP consists of a meter module,
relay controller and relay panel (see image below). The typical
system has one 3Φ main meter and up to twenty-one (21) 2Φ
meters with 2Φ power relays
FIGURE 1. SMP
SMP

RECHARGE VÉHICULE ÉLECTRIQUE4
CT43, L1
CT43, L1
CT44, L2
CT44, L2
CT45, L3
CT45, L3
+
-- +
#01
#03
#05
#07
#09
#11
#13
#15
#02
#04
#06
#08
#10
#12
#14
EV ENTRANCES
ENTRANCES
EXITS
BOTTOM
RELAYS
LED
GROUNDING
BAR
GROUNDING
BAR
SM45-31
GROUDING
LUGS
TOP
RELAYS
GROUDING
LUGS
SMP-15
PORT
PROGRAM
PORT
DISPLAY
PORT BPORT DPORT APORT C CT44
CT43
MODBUS
POWER
SUPPLY POWER
SUPPLY
DCU
TERMINAL BLOCK FOR
RELAYS 01 TO 15
CT45
L1
L2
L3
N
#01
#01
#03
#03
#05
#05
#07
#07
#09
#09
#11
#11
#13
#13
#15
#15
#02
#02
#04
#04
#06
#06
#08
#08
#10
#10
#12
#12
#14
#14
DIAGRAM OF PANEL ENCLOSURE
IMAGE 2. SMP-15

RECHARGE VÉHICULE ÉLECTRIQUE5
DIMENSIONS
IMAGE 3. DIMENSIONS OF THE SMP GENERATION 1.5
24"
48"
8"
24"
8"

6
DESCRIPTION
The SMP is an integrated switching control and measuring
system with current transformers for the submetering
modules (or branch modules), magnetic latching power
relays of up to 240/60A and current transformers for mete-
ring the main power supply of the distribution panel (distri-
bution panel not included).
METERING DEVICE
The metering device is an i-meter-45 which is configured to
have a three-phase main meter and a two-phase meter per
branch.
LOAD CONTROL
The SMP is designed to optimize the use of the building’s
electrical infrastructure by ensuring that it does not exceed
the operational limits of the building’s electrical infrastruc-
ture while powering up to 21 EVSE. SMPs sharing a common
power source can be paired together.
The SMP is compatible with Level 2 EVSE: 208/240VAC,
maximum 32A.
* For EVSE up to 48A, please contact us.
INSTALLATION STEPS
STEP 1
Unpack the SMP. Warning: the panel is attached to the ship-
ping pallet with 4 screws ;
STEP 2
2.1 Turn the mounting brackets 90° (vertically) ;
Before After
2.2 Install the SMP on the wall ;
2.3 Check solidity.
STEP 3
Switch off the power supply to the distribution panel.
STEP 4
Drill the holes in the enclosure. (Avoid area marked in red
below)
STEP 5
5.1 Connect the ground ;
5.2 Connect the power cable of the SMP to a 15A
three-phase circuit breaker, an the neutral conductor to the
terminal block provided. Follow the phase order indicated
on the SMP ;
CT43, L1
CT43, L1
CT44, L2
CT44, L2
CT45, L3
CT45, L3
+
-- +
#01
#03
#05
#07
#09
#11
#13
#15
#02
#04
#06
#08
#10
#12
#14
L1
L2
L3
N
PorT
program
PorT
disp lay
port bport Dport Aport C CT44
CT43
modbus
CT45

RECHARGE VÉHICULE ÉLECTRIQUE7
5.3 Connect the distribution panel according to the order of
the phase indicated on the terminal blocks in the SMP ;
5.4 Connect the EVSE from the power relays (terminal blocks
T1, T2) .
STEP 6
Install the current transformers to the 3 main power phases
of the distribution panel and connect them into the SMP
terminal blocks provided for this purpose.
* For larger capacity current transformers, please contact us.
Extension of Current Transformer Wires: The current
transformers that are supplied have a 3m wiring;
however, it is possible to extend the wires. Additional
wiring must be 300V, minimum 16 AWG (1.5mm²), 2
conductors shielded (1 pair) (ex: 16/1PR PVC FT4 or
equivalent). A maximum distance of 100 feet between
the SMP and the distribution panel must be respected.
STEP 7
Connect a network cable providing Internet access to the
Ethernet port (RJ45) on the black computer module of the
SMP .
NOTE
It is important to note the number of each
parking space associated with the SMP panel branch
number. This information will make it easier for the
customer to use the electricity metering reports.
NOTE
It is important to note that these are 0-400A* solid core
current transformers. They cannot be installed without
disconnecting the main electrical conductors from the
distribution panel.
Panel SMP
Max.
100 feet

RECHARGE VÉHICULE ÉLECTRIQUE8
STEP 8
8.1 Open the service entrance circuit breakers (3-poles) and
the charging station circuit breakers (2-poles) in the distri-
bution panel ;
8.2 Turn on power to the distribution panel.
STEP 9 (OPTIONAL)
The hardware required to allow the SMP to be locked with a
lock is supplied (lock not included). If needed, please refer
to the instructions included with the supplied hardware for
installation.
The maximum amperage set point is configured at the
factory according to the information you provided when
placing the order. RVE’s technical support team can
validate and modify this threshold remotely; please email
support@rve.ca if needed.
IMPORTANT NOTICES
Ensure that the Ethernet connection is active by
checking that the Ethernet port LEDs are flashing.
When the system starts up, you will hear the relays
gradually open and close.
There is a 5-minute delay between the activation
of each relay to allow time for a vehicle potentially
connected to a EVSE to the maximum charging
current. This ensures that the maximum amperage set
point of the SMP is not reached before moving on to
the next relay.

RECHARGE VÉHICULE ÉLECTRIQUE9
INSTALLATION EXAMPLES
EV Charger(s)
up to 21 depending
on the model)
Panel
SMP
ELECTRICAL
INFRASTRUCTURE CHARGING
INFRASTRUCTURE
Electricity
meter Transformer
3 phases 208/120V
MAX
200A
MAX
125A
SMP-15 with
MAIN PANEL
EV Charger(s)
up to 21, depending
on the model)
Panel
SMP
ELECTRICAL
INFRASTRUCTURE CHARGING
INFRASTRUCTURE
Electricity
meter Transformer
3 phases 208/120V

RECHARGE VÉHICULE ÉLECTRIQUE10
ELECTRICAL
INFRASTRUCTURE
Electricity
meter
Transformer
3 phases 208/120V
EV Charger(s)
(up to 21, depending
on the model)
Panel
SMP
CHARGING
INFRASTRUCTURE
EV Charger(s)
(up to 21, depending
on the model)
Panel
SMP
Electricity
meter
EV Charger(s)
(up to 21, depending
on the model)
SMP
Transformer
3 phases 208/120V
Panel
ELECTRICAL
INFRASTRUCTURE CHARGING
INFRASTRUCTURE
This manual suits for next models
3
Table of contents
Popular Control Unit manuals by other brands

TECHCON SYSTEMS
TECHCON SYSTEMS TS5624DMP user guide

Pfeiffer Vacuum
Pfeiffer Vacuum HPU 001 operating instructions

TechShop
TechShop Bee HC-05 user manual

HELIX
HELIX GRANVILLE-PHILLIPS Convectron ATM instruction manual

Velleman
Velleman VMA318 user manual

Bardiani
Bardiani BBYQ Instruction, use and maintenance manual

General Pump
General Pump RA2 quick start guide

Lauda
Lauda LRZ 918 Operation manual

Siemens
Siemens SIMATIC TIM 3V-IE DNP3 System manual

Eaton
Eaton Cutler-Hammer PanelMate ePro PS Series user guide

Symmons
Symmons 7-210-CK Operation & maintenance manual

Azbil
Azbil ACTIVAL VY51 Series Specifications & instructions