Procedure, Cosel Power Supply, Retrofit Kit, DAC 2200
Page 2 of 9
Document No
126603 Rev-A
Form # 117140-B
1.0 Purpose To provide instruction for installing the Cosel power supply retrofit kit.
2.0 Scope This procedure is for the field support personnel who are replacing the power supply in the
DAC-2200.
3.0 Definitions
DVM – Digital Volt Meter
PS – Power Supply
EDS - Electronic Discharge System
4.0 Tools
Philips screw driver
Electronic Discharge System
5.0 Safety
5.1 LOTO requirements
5.1.1 Locate the shipboard breaker providing power to the DAC-2200
5.1.2 Lock Out and Tag Out this breaker.
5.1.3 Using a DVM ensure no power on the outlet side of the breaker.
5.1.4 Make sure you have been properly grounded with an EDS.
6.0 Cosel Power Supply Retrofit Installation Procedure
6.1 Removal of existing DAC-2200 equipment.
6.1.1 Unscrew face-plate screws and slide DAC 2200 out of rack
6.1.2 Take off existing connections from the back (AC POWER, RF IN, ANTENNA, M&C,
NMEA, SHIP GYRO)
ÅRemove all 4
face-plate screws
↑↑↑↑↑↑
AC POWER RF IN ANTENNA M&C NMEA SHIP GYRO