69
ES
PT
ENG
and deposits, the use of inhibitors such as
Sentinel X100 or Fernox Protector F1 is
recommended after cleaning the system.
It is important to check the concentration
of the inhibitor after each system modifica-
tion and during maintenance following the
manufacturer’s instructions (specific tests
are available at your dealer).
The safety valve drain must be connected to
a collection funnel to collect any discharge
during interventions.
If the heating system is on a higher floor
than the boiler, install the on/off taps sup-
plied in kit optional on the heating system
delivery/return pipes.
WARNING: Failure to clean the heat system
or add an adequate inhibitor invalidates
the device’s warranty.
Gas connections must be made in accordan-
ce with current standards and regulations.
When dimensioning gas pipes from the
meter to the module, both capacity volume
(consumption) in m
3
/h and gas density must
be taken into account.
The sections of the piping making up the
system must be such as to guarantee a sup-
ply of gas sufficient to cover the maximum
demand, limiting pressure loss between the
gas meter and any apparatus being used to
not greater than:
– 1.0 mbar for family II gases (natural gas);
– 2.0 mbar for family III gases (butane or
propane).
An adhesive data plate is sticked inside the
front panel; it contains all the technical data
identifying the boiler and the type of gas for
which the boiler is arranged.
2.3.1 Filter on the gas pipe
The gas valve is supplied ex factory with an
inlet filter, which, however, is not adequate
to entrap all the impurities in the gas or in
gas main pipes.
To prevent malfunctioning of the valve, or in
certain cases even to cut out the safety devi-
ce with which the valve is equipped, install
an adequate filter on the gas pipe.
2.5 SYSTEM FILLING (fig. 4)
Filling of the boiler and the system is done
by the system filling (11).
The charge pressure, with the system cold,
must be between 1 and 1.5 bar.
During system filling you are recommended
to keep the main switch turned OFF.
Filling must be done slowly so as to allow
any air bubbles to be bled off through the
air valves.
Should the pressure have risen well above
the limit expected, discharge the over pres-
sure by opening the pressure-relief valve.
2.5.1 Emptying the system (fig. 4)
Use the drain tap to empty the system (7).
Turn off the boiler before doing this.
2.6 FLUES/CHIMNEYS
A chimney or flue for the evacuation of the
combustion products into the atmosphere
must correspond to the requisites prescri-
bed by the laws in force.
2.11 ELECTRICAL WIRING
If you must replace the electric power cable
supplied with the boiler, order it exclusively
from Sime.
The power supply must be single-phase
230V - 50 Hz through a main switch pro-
tected by a fuse with a distance of at least 3
mm between contacts.
The boiler must be connected with an effi-
cient grounding system. SIME shall not be
held liable for injury or damage resulting
from failure to ground the boiler.
ATTENTION: Before every intervention on
the boiler, cut off the electricity supply by
means of the main switch of the system,
since even if the boiler is “OFF”, the elec-
trical panel remains connected to the elec-
tricity.
2.11.1 Chronothermostat connection
Connect the chronothermostat as indica-
ted in the boiler electrical diagram (see
paragraph 2.12) after having removed the
existing bridge.
The chronothermostat to be used must be
of a class conforming to the standard EN
607301 (clean electrical contact).
2.11.2 Remote control SIME HOME
connection (optional)
The boiler is designed for connection to a
remote control unit SIME HOME, supplied
on request (code 8092280/81).
The remote control unit SIME HOME allows
for complete remote control of the boiler.
The boiler display will show the following
message:
For installation and use of the remote con-
trol, follow the instructions in the package.
NOTE: Ensure PAR 10 set to 1 (PAR 10 = 1).
2.11.3 External sensor connection
The boiler is designed for connection to an
external temperature sensor, supplied on
request (code 8094101), which can auto-
matically regulate the temperature value of
the boiler output according to the external
temperature. For installation, follow the
instruction in the package.
1. Visualizzazione temperatura esterna
solo con sonda esterna collegata
2. Visualizzazione temperatura sonda
riscaldamento (SM)
3. Visualizzazione temperatura sonda
sanitario (SS) solo per caldaie istantanee
4. Visualizzazione temperatura sonda
ausiliaria o sonda bollitore (SB)
6. Visualizzazione temperatura
riscaldamento riferita al primo circuito
7. Visualizzazione temperatura
riscaldamento riferita al secondo circuito
13. Visualizzazione codice errore
penultima anomalia
14. Visualizzazione numero totale
delle anomalie
10. Visualizzazione ore di funzionamento del bruciatore in h x 100 (es. 14.000 e 10)
11. Visualizzazione numero di accensioni del bruciatore x 1.000 (es. 97.000 e 500)
12. Visualizzazione codice errore
ultima anomalia
15. Contatore accessi parametri
installatore (es. 140 accessi)
5. Visualizzazione temperatura sonda
fumi
8. Visualizzazione corrente
di ionizzazione in µA 16. Contatore accessi parametri
OEM (es. 48 accessi)
9. Visualizzazione corrente al
modulatore in mA