CAUTION! Wear appropriate PPE when working with chemicals. Backow prevenon required.
Venturi Sanitize Foam
Quick Start Guide
M2444 - SLX-MS2-VS-VF Quick Start Guide
Last Updated: 01/20/2023
A. Take hold of spray wand for either system
B. Open discharge ball valve
C. Open water supply valve - unit will spray
D. Verify water pressure is at least 35 PSI
E. [Foamers] Open air supply valve - unit will foam
F. [Foamers] Adjust air pressure to alter foam quality
G. Foam equipment, from boom to top, and rinse
before it dries
H. Sanize from top to boom
I. When complete, turn o supply valves
J. Store hose depressurized, with discharge valve
open, and coiled properly to prevent kinks
3Operaon
WATER SUPPLY (35 - 125psi)
3/4" NPT CONNECTION
AIR SUPPLY
AIR PRESSURE GAUGE
AIR REGULATOR
AIR SUPPLY BALL VALVE
FOAMER SUPPLY BALL VALVE
SANITIZER SUPPLY BALL VALVE
FOAMER WATER PRESSURE GAUGE
SANITIZER WATER PRESSURE GAUGE
DOOR LOCK
SANITIZER CHEMICAL INLET
SANITIZER SOLUTION LINE WITH
STRAINER & CERAMIC WEIGHT
FOAMER SOLUTION LINE WITH
STRAINER & CERAMIC WEIGHT
FOAMER
SANITIZER
FOAMER DISCHARGE HOSE (BLUE)
SANITIZER DISCHARGE HOSE (RED)
FOAMER DISCHARGE BALL VALVE
SANITIZER DISCHARGE BALL VALVE
FOAMER CHEMICAL INLET
Example Installaon
A. Select a metering p for desired diluon rao
B. Install the metering p by screwing it onto the hose
barb for each chemical inlet
C. Install chemical sucon lines to hose barbs
D. Connect sucon lines to chemical soluons
2Diluon
Metering Tip Calculator
Mobile App:
A. Mount SLX enclosure
to wall
B. Flush supply lines
C. Install backow
prevenon per local
guidelines
D. Connect supply lines:
• Compressed air
(1/4” FNPT)
• Water (3/4” FNPT)
E. Connect discharge
hoses
F. Place chemical
containers below unit
1Install and
Connect