7-2. Logger installation
1. Installation
Logger should be set in dried and ventilation situation. It can be
set on the wall or put level place. If it is set on the wall, there will
be 2 installing holes which can be used to fix.
2. Power protection
Please set the socket and breaker basing on the local rules.
7-3. Connect to monitored devices
1. RS485 line make method
Please make the RS 485 +(A) and 485 –(B) and GND connect to
RJ45 Line 4 and Line 5 and Line 8 point. This 485 line length will
be longer than the distance between logger and devices.
2. Connect the RS485 port to monitored devices with RS485
line .About line and port, please consult the installation manual.