manuals.online logo
Brands
  1. Home
  2. •
  3. Brands
  4. •
  5. defencell
  6. •
  7. Construction Equipment
  8. •
  9. defencell PROFILE 300 Instruction sheet

defencell PROFILE 300 Instruction sheet

Installation Guidelines
PROFILE 300
DEFENCELL
Prole 300 1.25m high:
Five layers - Prole 300:11 to 300:07
PAS68 - 7500(N2):64/90:0/0
Prole 300 1.50m high:
Six layers - Prole 300:11 to 300:06
PAS68 - 7500(N3):80/90:2.5/0
PROFILE PANEL SIZES Unit Prole
300:04
Prole
300:05
Prole
300:06
Prole
300:07
Prole
300:08
Prole
300:09
Prole
300:10
Prole
300:11
Panel Length mm 4970
Panel Width mm 1273 1591 1909 2227 2546 2864 3182 3500
DEFENCELL Prole 300
Introduction
The DEFENCELL Prole 300 Protection System is a textile,
cellular, containment system which can be lled with
various materials (sand, gravel, soil and small rocks) to
build a variety of structures for perimeter security and
HVM protection.
Site Preparation
The ground should be level and compact to CBR value
of <5%. Where soft spots occur (CBR value of >5%)
the material will be excavated and replaced with 6F1
material compacted in 150mm layers. If the soft spot
locations are extensive, the material will be tested for
its CBR value. In addition, a trial pit will be excavated
to a depth of 1.5m and the sub-strata re-examined and
tested for its CBR value. Appropriate remediation of the
soft spot will be determined by the engineer.
DEFENCELL is to be lled using suitable granular ll with
a maximum stone size 40mm with no clays.
Landscape and Ecology
The designer should ensure that the berm proles takes
into account the following local material (soil) properties
and environmental conditions:
• Compaction: the consolidation of soil (under its own
weight) overtime.
• Erosion: the carrying away or displacement of solids
through weathering or living organisms.
• Slump: gravity causing material to slide down slope.
• Stability: the consistency of the berm form under
loading and over time.
Construction time
A team of four on an average 8 hour shift, with a 16T
excavator with 1m3ditching bucket plus operator, may
achieve the following:
Using the frame method
(Using two Prole frames)
Can complete 25-35 linear metres per shift.
(Not including landscaping.)
Note: These are a guide to installation of Prole300. The
production rate will increase or decrease depending on
the following:
• Distance excavator has to haul the ll
• Type of excavator used and bucket capacity
• The ow and size of granular ll used
• The experience of the excavator operator
• The climatic conditions
• The number of teams available
• Number of frames or pins available
Using the pin method
(Using enough pins for two panels at once)
Can complete 10-15 linear metres of Prole 300 per shift.
(Not including landscaping)
Installation
Prole 300 should be installed on compacted level
ground as per instruction above with consideration
given to drainage. The installation of Prole 300 can be
achieved in six stages:
Stage 1 - Panel Placement
The base layer of any Prole 300 PAS 68 design is the
P300:11. Identify the panel by its label which can be
found on either end.
Once the correct Prole 300 is selected, build the
corresponding Prole 300 frame by following the Frame
Installation Guide and position it on your building
site with the long side along the direction of your
construction.
Next identify the female end of the Prole 300. The
female end of a P300:11 has 11 cells while the male end
has only 10 cells.
Start with the labelled corner of the female end, lift the frame
up and place the corner cell onto the two corner pins.
2
368mm
368mm
318mm
318mm
300:06 300:07 300:08 300:09 300:10 300:11
38 40 42 44 46 48
Work your way across, lift the frame slightly and push the
Profile 300 down under the pin and back up so the pin is
located inside the cell. Move along to the next cell and repeat.
Repeat the process along both sides.
Finish at the diagonally opposite corner ensuring that
the male cells at this end protrude halfway past the end
of the frame as shown below.
Using Pins
If the frame is not used the same can be achieved by
using pins.
Using a building line as a guide, pins can be placed into
the ground along the long sides of the construction at
368mm centres and across the ends at 318mm centres.
In the same way as when using a frame, the cells are
placed over the pins until the Prole 300 is tight and
symmetrical. Start with the labelled corner of the female
end then working along both sides and nish with the
male end.
Pin Quantities Required
Note: If you have more than one frame or sets of pins
available, it is recommended you set up more base units.
3
Stage 2 - Subsequent Panels
Ideally, several panels should be pinned out or framed at
anyonetime whichwillallow for thelling machine(front
end loader, excavator, etc.) to continue immediately to
the next panel, therefore keeping momentum of the
installation.
Using frames
Once the rst frame is in position the next frame is tted
with the Prole 300 and positioned in the direction of
construction, so that the male end on the rst frame
interlocks with the female on the second frame. This is
completed by butting the two frames together.
Using Pins
The same can be achieved using pins.
Once the rst Prole 300 is in position, the next Prole
300 is opened out and aligned in the direction of
construction, with the female end of the new Prole
300 interlocked with the male end of the rst. Pin out
the new Prole as previously until the Prole is tight and
symmetrical.
Stage 3 - Filling
Fill should be distributed evenly across the panel width
taking care not to dump ll in one area.
Even distribution of the ll and levelling with the
excavator will aid the compaction process and reduce
manual spreading.
Some manual leveling may be required with some ll
materials.
Once the panel is full and ready for compaction the
frame should be removed by carefully lifting. Use four
people, one on each side of the frame.
If using pins ensure that all are removed before
compaction.
4
D
O
N
O
T
E
N
T
E
R
T
H
I
S
A
R
E
A
Stage 4 - Compaction
Once the cells are lled (or slightly over lled depending
on ll material) the frame is removed and the ll
compacted. A mechanical plate compactor is ideal.
This can be carried out whilst the excavator is lling
the next frame however you must ensure that the
compactor does not enter into the excavator bucket
operating radius at any time.
Compaction of the material is achieved with three passes
of a plate compactor.
Note: Care must be taken not to over compact otherwise
the outer cell walls may be crushed which will aect the
overall cell/berm height.
If the level of ll is too high once compaction is complete
this must be removed before the next layer is laid.
Stage 5 - Subsequent Layers
Once the base level is complete or you have nished a
section (depending on your construction plan) move to
the next layer.
Using frame
First change the frame to the next size down as per the
frame guide. Place on the fabric panel as previously
instructed.
Position the frame on top of the layer below, checking
it is central to the berm. This will give you spacing of
160mm either side of the panel below or roughly half a
cell. Position the end directly in line with the layer below.
Using pins
Pins are placed in the outer cells of the lled layer.
Position them centrally in the cell and step back half
a cell (160mm) from the edge to achieve the desired
angle/prole required for the berm.
Note: It is recommended that sequential panels are laid
to maintain momentum of the lling process.
Panel joints. Prole 300 1.25m
Stagger panel joints by using half panels at each end of
the berm to create an interlock between the panels.
Note: Half panels are required on layers 2 and 4
5
This is best achieved by carefully marking a line along
the centre of the panel, using a felt-marker or line-
paint, so you are left with complete cells in the same
conguration as a normal panel end.
It is advisable to cover the end cells with a scaold plank or
similar. Fill to the edge of the plank, leaving the cells below
the plank empty.
Then remove plank and cut cells next to the glue joints.
Remove the frame as usual and keep the unlled section
of Prole 300. Use this at the end of the run to complete
the layer.
Then place a new Prole panel on the frame and join to
the lled half panel.
Prole 300 1.50m
There are three distinct dierences between the Prole
300 1.25m high and the 1.50m high during construction;
1.The Prole 300 1.50m has an extra layer, using the
Prole 300:06 on top.
2. Connect all the end cells between panels with a cord
tied with a reef knot.
The same can be achieved when using pins.
3. Panel joints should be staggered by cutting the end
panels on each layer of a construction. Each layer should
be cut 1m shorter than the layer below to achive the
staggered joints.
6
Stage 6 - Landscaping
Once the berm is completed to the required specication
it can be landscaped.
The berm can be landscaped by topsoil being placed
on the front/rear face of the berm. Once this is done
the berm can be cut into the required angle using the
bucket of the excavator.
Note: Check the angle using a prole board set to the
required angle.
Berm Attack Face: - The granular material chosen for
the berm prole should be graded to between 54-57
deg. This should allow the berm to settle over time but
not below 50 deg. as required.
Top of Berm: - The nished berm level is to be minimum
of 1.25m or 1.50m above existing ground levels after
compaction depending on design.
Berm non attack face: - The granular material chosen
for the berm prole can be sloped at any angle required,
or as instructed by the Engineer on site.
To prevent erosion, the berm can be lined with seed
impregnated hessian with either grass seed/ wild grass
or turf can be laid. This will also allow it to blend in and
be more aesthetically pleasing.
End walls / walk ways and integration of Vehicle
Security Barriers (VSB)
During the construction of the berm, several things may
have been incorporated into the design:
• End berm wall
• Pedestrian aperture
• Integration with Vehicle Security Barrier
Pedestrian aperture can be installed within the berm but
must not be any closer than 10m from end of the berm
and a maximum of 1.2m wide.
Disclaimer
The information contained in this leaet is provided
by DEFENCELL (J & S Franklin Ltd or it’s aliates and
associates) in good faith. While DEFENCELL has made
reasonable eorts to ensure the accuracy, completeness
and appropriateness of such information, any reliance
on such information is entirely at the risk of the
party using it. The installation and conguration of
any of DEFENCELL’s products by a third party is not
DEFENCELL’s responsibility and DEFENCELL (or its
employees, distributors or contractors) shall not be liable
for any failure of any of DEFENCELL’s products caused by
improper installation or subsequent misuse.
7
Prole 300 Universal Frame
Assembly Guide
1. The Prole Frame consists of four
corner pieces and six sets of four cross
pieces. The six dierent cross pieces
match the six dierent size Prole 300
panels and are colour coded.
The frame parts all have long pins pre-
tted which are inserted into the Prole
300 cells.
2. Assemble the two side bars using two
corner pieces on each side and connect
using the short nuts and bolts supplied.
3. Insert the four cross pieces (two end
and two centre) and connect using the
short nuts and bolts. The all yellow cross
pieces are used for the Prole 300:11.
4. For subsequent smaller Prole
panels, change the cross pieces to the
corresponding size.
5. After use, disassemble and clean the
frame and return to packing case.
11
10
9
8
7
6
PROFILE
6
7
8
9
10
11
PROFILE
11
10
9
8
7
6
6
7
8
9
10
11
JOINT LINE
JOINT LINE
PROFILE 6
PROFILE 7
PROFILE 8
PROFILE 9
PROFILE 10
PROFILE 11
Tel: +44 (0) 207 836 5746
email: info@defencell.com
www.defencell.com
DEFENCELL
© 2016 J&S FRANKLIN LTD. PROFILE 300 INSTALLATION V04/16

Popular Construction Equipment manuals by other brands

Sky Climber SKY STAGE ULTRA instruction manual

Sky Climber

Sky Climber SKY STAGE ULTRA instruction manual

Bomag BW 219 DH-4 Service training

Bomag

Bomag BW 219 DH-4 Service training

EZG MIXER EZG7 owner's manual

EZG

EZG MIXER EZG7 owner's manual

Ruger RC1000 Operator's manual

Ruger

Ruger RC1000 Operator's manual

Garbin TZ OPTIC FIBER 400 Use and maintenance manual

Garbin

Garbin TZ OPTIC FIBER 400 Use and maintenance manual

Makita RP1800 instruction manual

Makita

Makita RP1800 instruction manual

REED 00 C50SS manual

REED

REED 00 C50SS manual

Textron GREENLEE 766 M5 instruction manual

Textron

Textron GREENLEE 766 M5 instruction manual

Bosch Professional GRW 140 Original instructions

Bosch

Bosch Professional GRW 140 Original instructions

Renova moniroll MR 100 operating instructions

Renova

Renova moniroll MR 100 operating instructions

Crytec TCR650 manual

Crytec

Crytec TCR650 manual

Sealey PH10 instructions

Sealey

Sealey PH10 instructions

Baileigh Industrial RDB-150-AS Operator's manual

Baileigh Industrial

Baileigh Industrial RDB-150-AS Operator's manual

PROAIM P-WV-2PP Assembly manual

PROAIM

PROAIM P-WV-2PP Assembly manual

Scantool PV 35 manual

Scantool

Scantool PV 35 manual

CUSTERS CR 700 instruction manual

CUSTERS

CUSTERS CR 700 instruction manual

Farmi Forest FARMI 4571 OPERATION, MAINTENANCE AND SPARE PARTS MANUAL

Farmi Forest

Farmi Forest FARMI 4571 OPERATION, MAINTENANCE AND SPARE PARTS MANUAL

JLG R1532i Operation and safety manual

JLG

JLG R1532i Operation and safety manual

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.