SNIB2 Quick Installation Guide Revised 4/16/2014
Standoff Mounting
Holes
RS232 Connector
Status
LEDs
SW3 DIP
switch bank
SW1
ON
RS485 RS232
SW3
ON
1
2
3
4
5
6
G - RX + - TX+ G RX TX V
1
2
Expansion Board
Interface Cable
Connector (EBIC5)
SW1 DIP
switch bank
RS485
Connector
SW2
ON
1
2
P1
P2
P3
7
8
3
4
3
4
SW2 DIP
switch bank
RJ-45 Ethernet connector
Ethernet daughterboard
P1
P2
MAC Address label
Never detach the daughterboard
from the SNIB2 motherboard.
P1
P2
P3
(Refer to the SNIB2
Troubleshooting Guide)
S3
1
Addr S4 S5 S6 S7 S8
OFF OFF OFF OFF OFF ON
2 OFF OFF OFF OFF ON OFF
3 OFF OFF OFF OFF ON ON
4 OFF OFF OFF ON OFF OFF
5 OFF OFF OFF ON OFF ON
6 OFF OFF OFF ON ON OFF
7 OFF OFF OFF ON ON ON
8 OFF OFF ON OFF OFF OFF
9 OFF OFF ON OFF OFF ON
10 OFF OFF ON OFF ON OFF
11 OFF OFF ON OFF ON ON
12 OFF OFF ON ON OFF OFF
13 OFF OFF ON ON OFF ON
14 OFF OFF ON ON ON OFF
15 OFF OFF ON ON ON ON
16 OFF ON OFF OFF OFF OFF
17
Addr
OFF ON OFF OFF OFF ON
18 OFF ON OFF OFF ON OFF
19 OFF ON OFF OFF ON ON
20 OFF ON OFF ON OFF OFF
21 OFF ON OFF ON OFF ON
22 OFF ON OFF ON ON OFF
23 OFF ON OFF ON ON ON
24 OFF ON ON OFF OFF OFF
25 OFF ON ON OFF OFF ON
26 OFF ON ON OFF ON OFF
27 OFF ON ON OFF ON ON
28 OFF ON ON ON OFF OFF
29 OFF ON ON ON OFF ON
30 OFF ON ON ON ON OFF
31 OFF ON ON ON ON ON
32 ON OFF OFF OFF OFF OFF
33 ON OFF OFF OFF OFF ON
34 ON OFF OFF OFF ON OFF
35 ON OFF OFF OFF ON ON
36 ON OFF OFF ON OFF OFF
37 ON OFF OFF ON OFF ON
38 ON OFF OFF ON ON OFF
39 ON OFF OFF ON ON ON
40 ON OFF ON OFF OFF OFF
41 ON OFF ON OFF OFF ON
42 ON OFF ON OFF ON OFF
43 ON OFF ON OFF ON ON
44 ON OFF ON ON OFF OFF
45 ON OFF ON ON OFF ON
46 ON OFF ON ON ON OFF
47 ON OFF ON ON ON ON
48 ON ON OFF OFF OFF OFF
49 ON ON OFF OFF OFF ON
50 ON ON OFF OFF ON OFF
51 ON ON OFF OFF ON ON
52 ON ON OFF ON OFF OFF
53 ON ON OFF ON OFF ON
54 ON ON OFF ON ON OFF
55 ON ON OFF ON ON ON
56 ON ON ON OFF OFF OFF
57 ON ON ON OFF OFF ON
58 ON ON ON OFF ON OFF
59 ON ON ON OFF ON ON
60 ON ON ON ON OFF OFF
61 ON ON ON ON OFF ON
62 ON ON ON ON ON OFF
63 ON ON ON ON ON ON
Network Address Settings (S3 - S8 in Switch Bank 3)
S3 S4 S5 S6 S7 S8
1900 Carnegie Ave., Bldg. B
Santa Ana, CA 92705-5520
(949) 250-8888
www.hirsch-identive.com
Installations with NET*MUX4s support up to 63 controllers. Installations without NET*MUX4s are
limited to 16 controllers, which can have any address in the range 1-63. Where possible, limit your
multi-drops to 16 units for optimum speed and performance. Even at 9600 bps, two 16-unit
configurations outperform one 32-unit configuration.
For more information on setting up this SNIB2,
refer to the SNIB2 Troubleshooting Guide and
the SNIB2 Configuration Guide (SUPP09).
(for direct host connections, not dial-up)
(for downstream
multi-drop
connections)
(for upstream 10/100 Mbps connections)
To mount the SNIB2 expansion board:
1. Turn all system power off: remove the connector for the standby battery, then disconnect the
AC power connector or the power supply fuse.
2. Install the new SNIB2 board into the upper left corner of the enclosure using the supplied
screws. If there are additional expansion boards to install, install them first using the supplied
standoffs. Install the SNIB2 board last so that it is at the top of the stack.
3. Connect the EBIC5 connector. Reconnect the AC power connector (or power supply fuse), then
reconnect the standby battery connector. The controller board’s yellow test LED should light;
the other lights go through a start up sequence. When the sequence is complete, the yellow test
LED goes out and the other lights stabilize.
4. If required, connect an RJ-45 network cable to the SNIB2 Ethernet connector.
Mounting the Board
Connect
screws to
the board.
If you stack boards, make sure the
SNIB2 is on top of the stack, so you
can wire the board, configure its DIP
switches, and view its status LEDs.
If a MEB/BE, MEB/CE, or MEB/CB board is installed, do
not remove it. Removing any of these boards will cause
the controller to malfunction and requires a system cold
start. This will erase all additional information in their
memory and requires complete system download.
!
14
OFF
OFF
S2
ONOFF
ON
bps 9600 38400
S1
Baud Rate Settings (S1 –S2 in SW3)
OFF
57600 115200
ON
ON
6. Tighten the screws until the wire is securely fastened in the slot.
7. If you removed the green connector in step 3, push the green
connector into the appropriate socket until it locks into place. The
connector and socket are keyed, so there is only one way to plug it in.
8. Reconnect the system power by first connecting the AC power
connector, then connecting the standby battery connector.
Wiring the Board
Insert wires into
green connectors
Before installing the SNIB2, you should set the required DIP switches on its three switch banks:
OFF
ON
Switch Bank 1 (SW1)
This SNIB2 is first (master) or last (termination) in the multidrop sequence.
This SNIB2 is in the middle of a multidrop sequence.
S1 - S4
Setting Up the Board
OFF
ON
Switch Bank 2 (SW2)
The SNIB2 communicates with the host PC in XNET 2 using the encryption
keys stored in memory.
Return the encryption keys to their default settings. If this switch is set when
the SNIB2 powers up or reboots after a firmware upgrade, the keys reset.
This switch can be turned off after the LED patterns begin to light. See the
SNIB2 Troubleshooting Guide. If this is the master SNIB2, you must also
‘Reset Encryption’ on the Velocity Port settings. All downstream units must
also have their encryption keys reset. If this is a downstream unit, the master
SNIB2 automatically detects that the encryption keys have been reset.
S1
OFF
Normal operation.
This SNIB2 is not first in the multidrop sequence, or you have only one
controller.
S2 - S3 OFF
S4
ON This SNIB2 is first in the sequence (master) and is connected to the host via
Ethernet or direct RS-232 connection (not dial-up). This SNIB2 controls polling.
Baud rates only apply to the SNIB2’s RS-485 and RS-232 ports. The SNIB2’s Ethernet port is used
for host-to-controller connections and runs at 10/100 BaseT speeds. All SNIBs/SNIB2s in an RS-485
multi-drop sequence must be set to the same speed, and if connected to a host PC using RS-232 direct
connection, the same speed must also be used. For example, if any SNIB2 in the sequence is set to
9600, all other SNIBs and SNIB2s (and the RS-232 host connection, if used) must be set to 9600.
If you plan to multidrop SNIBs/SNIB2s, the cable between the first (Master)
controller and the second must be wired as shown here:
RX- to TX-
RX+ to TX+
TX- to RX-
TX+ to RX+
Ground
Subsequent controllers on the same chain are wired point-to-point.
Address 1 Address 2
Master SNIB2 Subordinate SNIB2/SNIB This controls the baud rate for the RS-485 multi-drop
line and the RS-232 connection. 57600 and 115200 bps
are only available if your RS-485 cables are made from
Cat5/Cat6 data grade wire. These speeds are not
recommended for installations using:
· RS-232 connections to host
· 18- to 22-gauge shielded twisted-pair cable
· NET*MUX4s
· Mixed SNIBs and SNIB2s
Standard Cable
SNIB2 RS-485 installations with standard 18-,
20-, and 22-gauge shielded twisted-pair cable
should use 9600 or 38400 bps. Do not use
higher speeds. If you have communication
problems at 38400 bps, reduce it to 9600 bps.
Installations with NET*MUX4s are limited to
9600 bps.
Cat5 Cable
For new SNIB2-to-SNIB2 RS-485 installations,
we recommend making your cables with Cat5 or
equivalent grade cable to the appropriate 5-pin
green connectors. Pick one color wire, such as
brown, to use for Ground. Distances up to 4000
feet can be achieved with this RS-485 cabling
type. If there is no NET*MUX4 involved, you
can use 57600 or 115200 bps.
Communications become less robust as baud rates increase, wire gauge decreases, and
distances increase. Most tables in the DIGI*TRAC Systems Design and Installation
Guide for wire gauge and distance are based on 9600 baud. At higher baud rates,
maximum distances are decreased and minimum wire gauge is increased. It may not be
possible to implement the higher baud rates supported by the SNIB2 if you have long
wire runs or small wire gauges. Higher baud rates are also more dependent on the
number of twists per foot, so capacitance specifications must be strictly followed: total
wire run per port is not to exceed 100,000 pf per foot.
To connect RS-485 serial cables between SNIB2s:
1. Turn all system power off by first removing the connector for the standby battery, then
disconnect the AC power connector or the power supply fuse.
2. Punch out the knockout in the controller enclosure where you plan to route the RS-485 cable.
You can either route this wire through the same opening you’re using for controller board
connections, or knock out a new opening.
3. Route the wires through the opening. If it makes serial wiring easier, detach each green connector
from the board as needed.
4. Loosen the screws on each RS-485 connector plug you will be using.
5. Remove insulation from the wire and insert the specified wires into the green connectors at the
required slots as shown to the right.
CCM and SNIB2 Firmware Upgrade Paths:
· Upgrade the CCM firmware and physically replace a SNIB with a SNIB2: Upgrade the CCM
firmware first, then replace the SNIB with the SNIB2.
· Upgrade the CCM firmware and either upgrade the SNIB2 firmware or physically replace a SNIB2
with a different SNIB2: It doesn’t matter which you upgrade first.
Firmware Download Rules:
· Do not download CCM and SNIB2 firmware simultaneously on the same port.
· Do not download CCM or SNIB2 firmware to the master SNIB2 at the same time as downstream
units on the same port. We recommend upgrading the master before upgrading downstream units.
· Do not download firmware to more than two downstream CCMs or three downstream SNIB2s on
the same port at the same time. The firmware download time multiplies with each additional
controller downloading. 3
2
ON Only when resetting this SNIB2 to the factory default settings.

Popular Computer Hardware manuals by other brands

Simplex 4100-3109 IDNet 2 installation instructions

Simplex

Simplex 4100-3109 IDNet 2 installation instructions

Aphex 230 Quick setup guide

Aphex

Aphex 230 Quick setup guide

ArduCAM 16MP Autofocus Getting started

ArduCAM

ArduCAM 16MP Autofocus Getting started

MF DIGITAL Ripstation series Quick connect guide

MF DIGITAL

MF DIGITAL Ripstation series Quick connect guide

Arctic F8 PWM PST Welcome guide

Arctic

Arctic F8 PWM PST Welcome guide

Opal-RT OP4510 V2 Installation

Opal-RT

Opal-RT OP4510 V2 Installation

Texas Instruments DP83867E user guide

Texas Instruments

Texas Instruments DP83867E user guide

Dialog Audio MP3244 user guide

Dialog Audio

Dialog Audio MP3244 user guide

SpinCore Technologies PulseBlasterESR-PRO SP18A owner's manual

SpinCore Technologies

SpinCore Technologies PulseBlasterESR-PRO SP18A owner's manual

Telit Wireless Solutions LE910C Series WE866C Series user guide

Telit Wireless Solutions

Telit Wireless Solutions LE910C Series WE866C Series user guide

Commell UniChrome Pro HE-760 user manual

Commell

Commell UniChrome Pro HE-760 user manual

AMD ADA3800DAA5BV Product data sheet

AMD

AMD ADA3800DAA5BV Product data sheet

Moxa Technologies CI-104J Quick installation guide

Moxa Technologies

Moxa Technologies CI-104J Quick installation guide

Kontron aFLAT Series manual

Kontron

Kontron aFLAT Series manual

Magtek ExpressCard 2000 manual

Magtek

Magtek ExpressCard 2000 manual

SIIG Parallel Pro Installation

SIIG

SIIG Parallel Pro Installation

Omron JUSP-NS300 datasheet

Omron

Omron JUSP-NS300 datasheet

Primare P30 user guide

Primare

Primare P30 user guide

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.