SIGNIFY GARDCO DuraForm FLDS User manual

Flood
DuraForm
FLDS/FLDM/FLDL Flood Family
6/7/2019 page 1 www.gardcolighng.com 442295030941 Rev A
Electrical Connecon:
• Connect the black xture lead to the input voltage supply or Hot 1 (208V/240V/480V wiring).
• Connect the white xture lead to the neutral supply or Hot 2 (208V/240V/480V wiring).
• Connect the Green ground lead to the incoming ground wire.
• If DIMD or WLDC external controls opons are selected, connect the purple dimming posive lead to the control’s dim-
ming posive lead and the grey dimming negave lead to the control’s dimming negave lead.
STEP 1:
Remove splice cover screws and splice cover to access wire
splice area.
STEP 2:
Route the supply wire through the tenon. Secure the supply wire
to keep from sliding back down the pole. Route wire through slip
fitter arm into splice area.
STEP 3:
Holding routed wires in splice area, carefully lower luminaire onto
tenon. Check to ensure that wires are not pinched between inside
of slip fitter and top of tenon and that luminaire and wires rotate
freely.
SLF—Slip Fier Mount
Note: Tenon must be 3.75” or longer.
Note: 7 pin NEMA Twist Lock Receptacle opon aiming
restricted to 0-90o per ANSI C136.10

DuraForm Installaon Instrucons
6/7/2019 page 2 www.gardcolighng.com 442295030941 Rev A
SLF—Slip Fier Mount
Note: Tenon must be 3.75” or longer.
HORIZONTAL ANGLE ADJUSTMENT
STEP 4:
Secure the luminaire on the tenon. Using a 3/16" Allen wrench, hand
tighten the Slip fitter set screws until the tip of the screws engage the
tenon. (Do not fully tighten). Using the built in aiming sight at the top
edge of the luminaire rotate the luminaire horizontally until the desired
aiming target is centered in the aiming window. Tighten the set screws
to 20 ft.-lbs when the final horizontal position is set.
STEP 5:
Make electrical connections per Electrical Connection section (pg. 1)
inside the splice area. When complete replace the splice cover and
screws removed in Step 1. Ensure that the gasket is correctly in place
before tightening splice cover and screws.
SLF—Slip Fier Mount
Note: Tenon must be 3.75” or longer.
VERTICAL ANGLE ADJUSTMENT
NOTE: Angle adjustment can be made before luminaire in-
stallation.
STEP 6:
After the luminaire is installed, the vertical angle of the lumi-
naire can be adjusted within the limits of the aiming diagram
(pg.1) in 5° increments.
STEP 7:
To adjust the vertical angle, loosen the 1/2–13 X 1.75” socket
cap bolt located in slip fitter Arm. (Do NOT remove bolt.)
Loosen only enough to allow rotation of cast teeth.
STEP 8:
Using the aiming sight and the degree indicators shown as a
guide, rotate vertically the luminaire to the desired position
and retighten the bolt loosened in Step 7 to 47 ft.-lbs.

6/7/2019 page 3 www.gardcolighng.com 442295030941 Rev A
SFC—Slip Fier Mount with Cord
Note: Tenon must be 3.75” or longer.
HORIZONTAL ANGLE ADJUSTMENT
STEP 1:
Carefully lower luminaire onto the tenon and secure the luminaire on
the tenon. Using a 3/16" Allen wrench, hand tighten the Slip fitter set
screws until the tip of the screws engage the tenon. (Do not fully tight-
en). Using the built in aiming sight at the top edge of the luminaire ro-
tate the luminaire horizontally until the desired aiming target is cen-
tered in the aiming window. Tighten the set screws to 20 ft.-lbs when
the final horizontal position is set.
STEP 2:
Route the supplied cord to the electrical junction box provided by oth-
ers. Make electrical connections per the Electrical Connection section
(pg.1) inside junction box. Replace junction box gasket and cover.
NOTE: Electrical connections can be made after installation.
VERTICAL ANGLE ADJUSTMENT
NOTE: Angle adjustment can be made before luminaire in-
stallation.
STEP 3:
After the luminaire is installed, the vertical angle of the lu-
minaire can be adjusted within the limits of the aiming dia-
gram (pg. 1) in 5° increments.
STEP 4:
To adjust the vertical angle, loosen the 1/2–13 X 1.75” sock-
et cap bolt located in slip fitter Arm. (Do NOT remove bolt.)
Loosen only enough to allow rotation of cast teeth.
STEP 5:
Using the aiming sight and the degree indicators shown as
a guide, rotate vertically the luminaire to the desired posi-
tion and retighten the bolt loosened in Step 7 to 47 ft.-lbs.
SFC—Slip Fier Mount with Cord
Note: Tenon must be 3.75” or longer.
DuraForm Installaon Instrucons

6/7/2019 page 4 www.gardcolighng.com 442295030941 Rev A
YOK—Yoke Mount
Note: 7 pin NEMA Twist Lock Receptacle opon aiming
restricted to 0-90o per ANSI C136.10
STEP 1:
Place Yoke bracket in location desired and secure to surface with a minimum of qty. 2 1/2”
bolts or studs provided by others. See yoke mount detail above and mount using 12” or 20”
spacing depending on luminaire size. Note that 0.78” O.D. (25/32” or 20mm) center hole can
also be used for mounting in addition to BUT NOT EXCLUSIVELY WITHOUT other two bolts.
STEP 2:
Route the supplied cord to the electrical junction box provided by others.
STEP 3:
Make electrical connections per Electrical Connection section (pg. 1) inside junction box.
STEP 4: Replace junction box gasket and cover.
NOTE: Electrical Connections can be made after installation is finished.
DuraForm Installaon Instrucons

6/7/2019 page 5 www.gardcolighng.com 442295030941 Rev A
YOK—Yoke Mount
VERTICAL ANGLE ADJUSTMENT
NOTE: Angle adjustment can be made before luminaire installation.
STEP 5:
After the luminaire is installed, the vertical angle of the luminaire can be adjusted within
the limits of the aiming diagram on pg. 4.
STEP 6:
To adjust the vertical angle, loosen both 1/2”–13 X 1.25” hex head bolts attaching Yoke
Arm. (Do NOT remove bolts.) Loosen only enough to allow rotation of the luminiare.
STEP 7:
Using the built in aiming sight at the top edge of the luminaire and the degree indicators
shown as a guide, rotate vertically the luminaire to the desired position and retighten the
bolts loosened in Step 6 to 45 ft.-lbs.
DuraForm Installaon Instrucons