For All DC Inverter Heat Recovery A/C
1. PRECAUTIONS
• Ensure before installing this equipment, you conform to national
regulations.
• Read “PRECAUTIONS” carefully before installation.
• The following precautions include important safety items. Take the time to
observe them to avoid injury.
• After installation, store this manual and the owners manual in a safe place,
for future reference.
• The model names in the manual are using acronyms, for example, SBOX02
is short for SBOX02-1.
• The A-weighted sound pressure level is below 70 dB.
The safety precautions listed here are divided into two categories. Ensure you
read all safety device to prevent injury or damage.
WARNING
Failure to observe can result in serious injury or damage.
CAUTION
Failure to observe a caution may result in injury or damage to the
equipment.
After completing the installation, make sure that the unit operates properly
during the start-up operation. Please instruct the customer on how to operate
the unit and keep it maintained.Also, inform customers that they should store
this installation manual along with the owner’s manual for future reference.
WARNING
• Ensure only qualified personnel carry out works on this equipment.
• Only install manufactured products by Bosch. Do not use other products
unless suggested by Bosch.
• When installing in a small room, take steps to ensure if a leak happens, the
room is well ventilated. Check the safety limits required for the room your
are installing in.
• Contact the distributor for specific measures.
• Ensure a qualified electrician is used to install all electrical equipment. Make
sure you comply with national wiring regulations.
• Failure to repair the equipment properly, may result in injury or damage to
the property.
• If the supply cable is damaged, contact a qualified electrician to get this
replaced. Make sure you turn the power off until this has been fixed.
•
CAUTION
• Do not install the SBOX near strong electromagnetic interference. This may
cause communication errors and noise problems.
• When installing the SBOX, choose a suitable location. The SBOX can
produce noise from the valves. We recommend installing away from rooms
which require quiet.
• You must install drain pipe for condensate waste.
• Improper drain piping may result in water leakage.
• Be sure to install an earth leakage breaker. Failure to install an earth leakage
breaker may result in electric shocks.
• Do not install the SBOX at any place where flammable gas may leak out.
• Make sure you install in a good string location. If there is no solid
foundation, consult a structural engineer for advice.
• Ensure electrical cabling has been connected correctly in the correct
terminals. If wire connections are wrong, this will cause damage and
serious injury.
• Install in a dry location. Exposure to water may result in damage.
• After installation work is complete, pressure test to ensure no leaks are on
the system. For pressure testing, see outdoor installation manual.
2. INSTALLATION INFORMATION
2.1. SBOX installation location
1. Ensure when installing the SBOX, that sufficient access is available for
maintenance and fault finding.
2. Make sure the SBOX is installed level.
3. Make sure there is sufficient space to connect pipe work, drains and cabling.
4. Ensure the SBOX is installed within the pipe limitations.
CAUTION
• Location in the following places may cause malfunction of the machine.
1. A place where is full of mineral oil like cutting oil etc.
2. A place where salty air surrounding such as near the coast etc.
3. A place where is full of caustic gas such as the sulfide.
4. A place with serious mains voltage fluctuation.
5. A place where high-frequency electromagnetic waves are generated.
6. A place with flammable gas or material.
7. A place with acidic or alkaline gas.
• This series air-conditioner is comfort type air-conditioner, do not use for
the machine room, precise machine, food, plants, animals, art-work etc.
rooms.
2 | PRECAUTIONS
6720862460 (16/04) CLIMATE 5000 VRF

2.2. SBOX Installation and maintenance needed space
Ceiling concrete
0.3m or more
1.5m or less 1.5m or less
Ceiling tex
Pipe
hanger
Refrigerant
pipe
Do not install the SBOX to close to the ceiling Tex(minimum 50mm)
400mm or more
400mm
or more
500mm
or more
400mm or more
Fig.2-1
Fig.2-2
CLIMATE 5000 VRF 6720862460 (16/04)
INSTALLATION INFORMATION |3

3. SYSTEM WIRING SPECIFICATION
Please check the following contents were supplied within the box. If any equipment is missing, ring you local distributor for replacement.
ACCESSORIES
NAME QTY. SHAPE USE
Installation & operation
manual 1For the SBOX installation and
operation instructions
Heat-insulated pipe 2-12
(Follow the SBOX model)
For heat insulation of pipe
connectors
Flexible drainage pipe 1Connect the drainage port of SBOX
and the PVC water pipe.
Clamp 1
Fasten the connector between
flexible drainage pipe and SBOX
drainage port.
Three-way connector 1 pair
(for SBOX02E)
Parallel connect the two groups
of pipes, to enlarge the capacity
output
Five-way connector 1 pair
(for SBOX04E)
Adapter pipe
1 pair (for SBOX01)
2 pairs(for SBOX02)
4 pairs(for SBOX04)
6 pairs(for SBOX06)
Use for the indoor unit capacity is
2.2~4.5kW
Copper nut 1-11
(Follow the SBOX model)
Use for connecting the pipes of the
indoor unit
Adapter pipe 1
(for SBOX01)
Use for connecting the liquid side of
the outdoor unit
LOCAL PURCHASED COMPONENTS
Copper Pipes
(Drawn copper pipes
GB1527-1987)
Indoor unit capacity 2.2~4.5kW 5.6~16.0kW Note
Liquid side pipe Φ6.4×0.8 Φ9.5×0.8 Use for the connection of SBOX and
indoor unit refrigerant system (TP2M).
The length selection is according to
actual needs.
Gas side pipe Φ12.7×0.8 Φ15.9×1.0
PVC drainage pipe For drainage pipe of SBOX, according to the actual needs for the length.
Heat-insulated pipe The inner diameter should be same with the relative copper pipes and PVC pipes, the thickness should be (more than)
10mm, especially thicker for the closed wet area.
Table:3-1
Table:3-2
4 | SYSTEM WIRING SPECIFICATION
6720862460 (16/04) CLIMATE 5000 VRF

4. SBOX INSTALLATION
WARNING
4.1. Install the main body
4.1.1 Install appropriate fixings. Check the weight of the SBOX.
1. Select a suitable location for the SBOX to be installed.
4.1.2 Hoisting install the SBOX
1. Ensure you use appropriate lifting equipment when installing the SBOX.
2. Make sure you use a level when installing the SBOX. Failure to do so, will
cause water leaks and damage.
4.2. The installation of hanging screw bolts
The installation situations of hanging screw bolts refer to the following (Table
4-1 and 4-2)
CAUTION
• You must use fixings that are appropriate for the installation. Make sure the
fixings have been treated for rust.
• Prior to lifting the SBOX in place, pull on the frame to ensure the frame is
secure.
• Suspending bolts must be fixed, the fixing method as per guidelines
suggested by the manufacture.
4.3. Dimension Figure
Model A B C D E
SBOX01 630 600 225 490 310
SBOX02 & SBOX02E 630 600 225 490 310
SBOX04 & SBOX04E 960 600 225 820 310
SBOX06 960 600 225 820 310
Model F G H I
SBOX01 Φ19.1 Φ16 Φ9.52 Φ24.5
SBOX02 & SBOX02E Φ25.4 Φ19.1 Φ12.7 Φ24.5
SBOX04 & SBOX04E Φ32 Φ22 Φ16 Φ24.5
SBOX06 Φ32 Φ22 Φ16 Φ24.5
Model J K
SBOX01 7/8”14UNF-2A 5/8”18UNF-3A
SBOX02 & SBOX02E 7/8”14UNF-2A 5/8”18UNF-3A
SBOX04 & SBOX04E 7/8”14UNF-2A 5/8”18UNF-3A
SBOX06 7/8”14UNF-2A 5/8”18UNF-3A
H
G F
I
C
E
J
K
D
A
B
Fig.4-1
Table:4-3
CLIMATE 5000 VRF 6720862460 (16/04)
SBOX INSTALLATION |5

4.4. Hanging the SBOX
1. Adjust the nuts, to ensure the SBOX is level. Make sure a foam gasket us
used when tightening the nuts. This will stop vibration noise. See Fig.4-2
2. Make sure the nut sits in the bracket of the SBOX with a washer either side.
Then tighten the nut to the bracket to secure the SBOX.
3. Note: Make sure before fastening the nuts, the SBOX is level. See Fig. 4-3.
5. ARRANGEMENTS FOR DRAINAGE PIPE
5.1. SBOX drain pipes installation
1. Please use the flexible drainage pipe to connect the SBOX drainage
port and the PVC pipes, and use the snap ring for fastening.
2. Then connect PVC with solvent weld to complete the drainage.
3. To avoid water flowing back into the SBOX, ensure the drain has a
fall of 1/100 away from the SBOX.
4. While connecting drains, make sure the gravity drain doesn’t exceed
20m. If drain termination cannot be done within 20m, install an
external pump. Make sure the drain is supported every 800mm
(dependant on quality of drain pipe). Ensure no dips are in the drain.
5. Follow fig 5-2 for connecting multiple units on one drain.
6. The termination of the drain pipe should be terminated 50mm
above the ground. When installing make sure a dry trap or U bend
is installed. This will prevent smells and water returning back up the
drain.
CAUTION
Make sure every joint in the drain is sealed using solvent weld.
5.2. Drainage test
5.2.1 Before carrying out drainage test, make sure you have checked
to make sure there are no dips in the drain. Make sure all drain
have been sealed.
1. Use a water main to fill the water tank with 500~1000ml water.
2. Check to see if the water has drained away. If not repeat the process or
re-install.
Fig.4-2
Hanging Bolt
Nut (top side)
Gasket (top side)
Installing lug
Gasket (bottom side)
Nut (bottom side)
Underneath of the ceiling
Fig.4-3
Ensure the nuts are
fastened.
Level gauge
Water container Snap
ring
Flexible drainage
pipe PVC water
pipe(Φ25)
Outlet Hard PVC binder
0.8~1.0 m Gradient:
higher than 1/100
a
>1.0 m
b
Fig.5-3
As long as possible (about 10cm)
Downside gradient
over 1/100
VP30
Fig.5-2
Fig.5-1
6 | ARRANGEMENTS FOR DRAINAGE PIPE
6720862460 (16/04) CLIMATE 5000 VRF

6. INSTALL THE CONNECTING PIPE
6.1. Range of SBOX application
SBOX outside
drawing Model Max. connecting
indoor unit quantity
Max. total indoor
unit capacity
SBOX01 4×1=4 16kW
SBOX02 4×2=8 28kW
SBOX04 4×4=16 45kW
SBOX06 4×6=24 45kW
SBOX02E 1 28kW
SBOX04E 1 56kW
6.2. Connecting diagram of SBOX and indoor unit
Connecting diagram 1
Suitable model SBOX01 SBOX02 SBOX04 SBOX06
Note
1. Capacity matching with each indoor unit group is lower
than16kW.
2. If auto mode function has been disabled, you may con-
nect up to four indoor units on one port. If auto mode has
been selected, only one indoor unit per port is allowed.
Connecting diagram 2
Suitable model SBOX02E
Note Match with large capacity duct type unit
(20.0kW~28.0kW)
Connecting diagram 3
Suitable model SBOX04E
Note Match with large capacity duct type unit
(40.0kW~56.0kW)
Note: for pipe sizing guidelines and connections to SBOX, refer to
outdoor unit installation manual.
CAUTION
• Do not let air, dust, or other impurities fall in the pipe system during instal-
lation.
• Keep the connecting pipe dry, and do not let moisture in during installation.
• Ensure you insulate copper pipes with a minimum of 10mm thick. For high
humidity and warm locations, use thicker insulation.
max:4 units, max capacity:16kW
max:4 units, max capacity:16kW
max:4 units, max capacity:16kW
max:4 units, max capacity:16kW
max:4 units, max capacity:16kW
max:4 units, max capacity:16kW
total max capacity:
16kW(for SBOX01)
28kW(for SBOX02)
45kW(for SBOX04/06)
indoor unit
indoor unit
indoor unit
indoor unit
indoor unit
indoor unit
indoor unit max: 1 unit, max capacity: 28kW
indoor unit max: 1 unit, max capacity:56kW
Table: 6-1
Table: 6-2
CLIMATE 5000 VRF 6720862460 (16/04)
INSTALL THE CONNECTING PIPE |7

6.3. Pipe size (Unit: mm)
6.4.1 SBOX pipe size
Model SBOX01 SBOX2 &
SBOX02E
SBOX04 &
SBOX04E
SBOX06
SBOX
main con-
nection
pipes
Liquid
pipe
Φ9.5 Φ12.7 Φ15.9 Φ15.9
High
pressure
gas pipe
Φ15.9 Φ19.1 Φ22.2 Φ22.2
Low
pressure
gas pipe
Φ19.1 Φ25.4 Φ31.8 Φ31.8
SBOX to
indoor
unit con-
nection
pipe
Liquid
pipe
Φ9.5 Φ9.5 Φ9.5 Φ9.5
Low
pressure
gas pipe
Φ15.9 Φ15.9 Φ15.9 Φ15.9
6.4.2 Indoor unit pipe size
Lower side
indoor unit
capacity A
(×100W)
Branch pipe side (mm) Suitable
branch pipe
Gas pipe Liquid side
22≤A≤45 Φ12.7 Φ6.4 IDU-BJ01
45<A≤160 Φ15.9 Φ9.5 IDU-BJ01
6.4. The Procedure of Connecting Pipes
1) Connect the indoor unit first, and then connect the outdoor unit.
a. The pipe bend should be handled carefully, without damaging the pipe and
insulation layer. Ensure once you have installed the indoor unit, cover with
plastic to stop dirt and dust collecting inside the unit. Failure to do so will
cause damage to the unit.
b. Before tightening up the flare nut, apply refrigerant oil at the outer surface of
the pipe. Screw up the nut for 3~4 circles beforehand (see Fig.6-1).
c. Ensure when connecting and disconnecting pipe work, use two spanners
simultaneously.
d. Ensure that you don’t over tighten the flare nut. This will deform the
connection pipe on the indoor unit and cause leaks.
2) Ensure when making flare you tape/cover the inlet of the indoor unit, to
ensure no impurities go inside the unit.
3) After connecting all the pipe work, ensure you flush the system through with
nitrogen and pressure test according to outdoor installation manual.
i.The bend angle shall not exceed 90°. (See Fig.6-2)
ii. Where possible use long radius bends to help flow of refrigerant.
iii. Do not bend the pipe more than three times.
i. When bending the pipe, measure the pipe length required, mark bend
position and bend with benders.
ii. Longer radius elbows are recommended to help flow of refrigerant.
iii. Always use pipe benders when bending pipe.
2. Fixing pipe work
1) Ensure you use appropriate brackets for supporting pipe work.
2) Ensure the liquid pipe and the suction pipe feeding one unit are bound
together, with the correct cable.
3) When installing pipe work through walls, you need to protect pipe work with
large plastic pipe work.
Table: 6-4
Apply refrigerant oil
Table: 6-3
Fig.6-1
Use a thumb to bend the pipe
Minimum radius 100mm
When rolling out copper pipe, ensure
there are no kinks or imperfections in
the pipe work.
Fig.6-2
Fig.6-3
8 | INSTALL THE CONNECTING PIPE
6720862460 (16/04) CLIMATE 5000 VRF

6.5. Pipeline connection
1. Flare
1) Use a pipe cutter to cut off the pipe (See Fig.6-4)
2) Pull the pipe into the rear flare of the connective nut. (Refer to Table: 6-5)
Table: 6-5
Outer
diameter
(mm)
A (mm)
Max. Min.
Φ6.4 8.7 8.3
Φ9.5 12.4 12.0
Φ12.7 15.8 15.4
Φ15.9 19.0 18.6
Φ19.1 23.3 22.9
2. Tighten the nut
Align with the connective pipe, screw up the connection pipe nut manually, and
use a spanner to tighten it as shown in Fig.6-5.
CAUTION
Make sure you use the correct torque when tightening the flare nut. Use the
table below for guidance on tightening.
Table: 6-6
Pipe size Tightening torque N.m
Φ6.4 14.2~17.2
Φ9.5 32.7~39.9
Φ12.7 49.5~60.3
Φ15.9 61.8~75.4
Φ19.1 97.2~118.6
CAUTION
6.6. Welding the copper pipe
Use braze-welding for the low pressure gas pipe, high pressure gas pipe, liquid
pipe which connected with SBOX and the outdoor unit.
CAUTION
During brazing, ensure you use cool gel on brass connections. If not used,
the brass will deform and leak.
● During welding, use nitrogen gas to protect welding.
6.7. Airtight test
CAUTION
Don’t use the refrigerant of the outdoor unit to do the vacuum.
Slant Coarse Burr
90
90°±4
45°±2
R0.4~0.8
A
Gas pipe(Flare) Liquid pipe(Flare)
Protect with wet
towel when brazing
Pipe connection from outdoor unit
Low pressure gas pipe
connection(Brazing)
High pressure gas pipe
connection(Brazing)
Liquid pipe connection(Brazing)
Pipe connection to intdoor unit
Fig.6-4
Fig.6-5
Fig.6-6
CLIMATE 5000 VRF 6720862460 (16/04)
INSTALL THE CONNECTING PIPE |9

6.8. Check the Leakage
Check all the joints with the leak detector or soap water.
6.9. Thermal insulation
Use appropriate thermal insulation for pipe insulation. Use thicker insulation
when installing in hot or humid conditions.
1. Use the thermal insulation with properties that can withstand 120 C.
7. WIRING
7.1. Electrical wiring
CAUTION
1. Ensure all power cable installation works are carried out by a qualified
electrician.
2. All equipment must be grounded and have a local isolation point.
3. Ensure when installing power cables they are installed in different
containment to communication cables.
4. If you have to extend the cable, make sure you use connective blocks or
connecting terminals.
5. Before turning on the power, ensure all terminals are connected securely.
7.2. Power specification
Use the table below for power cable selection.
Table 7-1
Item
Model
SBOX Power
Power supply Power switch
Capacity Safety fuse
SBOX01/
SBOX02
220-240V~
50Hz 5A 5A
SBOX04 220-240V~
50Hz 5A 5A
SBOX06 220-240V~
50Hz 5A 5A
SBOX02E 220-240V~
50Hz 5A 5A
SBOX04E 220-240V~
50Hz 5A 5A
Table 7-2
Item
Model
SBOX Power Wires
Power cable Signal wire
Power
wire
Grounding
wire
Wire diameter
SBOX01/
SBOX02 2mm 2mm 3-core shielded
wire 0.75mm
SBOX04 2mm 2mm 3-core shielded
wire 0.75mm
SBOX06 2mm 2mm 3-core shielded
wire 0.75mm
SBOX02E 2mm 2mm 3-core shielded
wire 0.75mm
SBOX04E 2mm 2mm 3-core shielded
wire 0.75mm
NOTE
The above parameters are only for guidance, ensure you adhere to
national wiring regulations.
7.3. Wiring for the SBOX power wire and signal wire
1. You must use a different power supply to the outdoor power supply.
2. For power terminal connection, use connections labelled L,N and E. For
communication wiring use terminals P,Q and E.
Cut it from up to down
Field piping side
Unit body
Subsidiary belt of thermal
insulation pump
Fig.6-7
10 | WIRING
6720862460 (16/04) CLIMATE 5000 VRF

7.4. Wiring figure of piping lines and signal wires
1.For SBOX01, SBOX02, SBOX04, SBOX06
2.For SBOX02E, SBOX04E
Fig.7-1
2# SBOX UNIT
1# SBOX UNIT
OUTDOOR
UNIT
(P Q E)
(P Q E)
(P Q E)
(P Q E)
(P Q E)
(P Q E)
(P Q E)
INDOOR UNIT
INDOOR UNIT
INDOOR UNIT
INDOOR UNIT
INDOOR UNIT
INDOOR UNIT
PIPING LINE
SIGNAL WIRE NOTICE: Indoor signal wires must match piping lines.
1# SBOX UNIT
For SBOX0E
For SBOX02
For SBOX01
1 2 3 4 5 6
1 2 3 4 5 6
SBOX-INDOOR
NO.6 NO.5 NO.4 NO.3 NO.2 NO.1 SBOX-OUTDOOR
2# SBOX UNIT
1# SBOX UNIT
For SBOX02E
INDOOR UNIT
(P Q E)
(P Q E)
1# SBOX UNIT
OUTDOOR
UNIT
NOTICE: Indoor signal wires must match piping lines.
PIPING LINE
SIGNAL WIRE
SBOX–INDOOR
NO.1 SBOX–OUTDOOR
CLIMATE 5000 VRF 6720862460 (16/04)
WIRING |11

7.5. Wiring requirements for signal wire
1. You must use shielded wire for communication signal cables.
2. All the shielding wires network should be interconnected, and finally
connected together to the metal plate grounding.
3. Ensure when installing power cables and communication wires there is a
distance of at least 300mm.
4. The control wire can not be a close loop.
5. The control wire has polarity, be careful during wiring.
6. All communication wires should be 0.75mm.
7.6. SBOX spot check function checks signal between indoor
unit and outdoor unit
Enter spot check:
1. Only power on the indoor units and the SBOX in the same system;
2. Long press the SBOX spot check key on the first SBOX. Then the other
SBOX’s connected to the system will enter spot check mode (SBOX01,
SBOX02, SBOX04, SBOX06 separately has 1,2, 4, 6 spot check keys);
3. After enter spot check mode, the display panel will display “CH”, when
No.ofsystem of SBOX detects the indoor unit communication signal, the
No. of system will immediately operate the solenoid valve under this system
as the following sequence: “SV(n)” ON 10s →“SV(n)-B” ON 10s → repeat the
above steps for 3times → “SV(n)” and “SV(n)-B” OFF;
4. If the valve didn’t follow step 3 operation then means the No. of system
communication has error, please check the signal wire connection between
No.of system and indoor unit, and then repeat the step 1~3 to check the
No.ofsystem; if the valve followed step 3 operation then means the No.of
system communication is normal, and then can repeat the step 1~3 to check
other systems;
Exit spot check:
1. No indoor unit signal is detected in 10 minutes;
2. SBOX power off;
3. Finish spot check operation.
8. APPLICATION CONTROL
8.1. Spot check instruction of main control panel
SBOX Spot check keys SW1-SW6 are separately corresponded to No.1-6 system
Table: 8-1
No. Display
1Connected indoor unit quantity under this SBOX
2This SBOX operation mode
3Subcooling inlet temp. T1C2
4Subcooling outlet temp. T1C1
5Total T2(B) average value back from outdoor unit
6Indoor unit T2(B) value under this SBOX
7Total ON status intdoor unit quantity
8Outdoor unit operation mode
9Subcooling PMV opening
10 ON status indoor unit quantity under this SBOX
11 Chip version number
12 — —
Operation mode:
0-Off
2-Cooling
3-Heating
4-Forceing cooling
5-Mixed cooling
6-Mixed Heating
8.2. LED indication lamp instruction
Table: 8-2
Normally ON Slow flash Flash
LED1 lamp Outdoor unit ON Outdoor unit
standby
Outdoor unit
communication error
LED2 lamp Indoor unit ON
under this SBOX
Indoor unit OFF
under this SBOX
Indoor unit
communication error
12 | APPLICATION CONTROL
6720862460 (16/04) CLIMATE 5000 VRF

9. TEST RUNNING
9.1. Confirm the following before operation
1. Whether the SBOX, indoor unit and outdoor unit are installed correctly;
2. Whether the tubing and wiring are correctly completed;
3. Whether check the leakage of refrigeration piping system;
4. Whether the drainage is unimpeded;
5. Whether the heating insulation works well;
6. Whether the ground wiring is connected correctly;
7. Whether recorded the pipe length and the refrigerant added amount;
8. Whether the power voltage fits the rated voltage of the unit;
9. Whether there is no obstacle at the air outlet and inlet;
10. Open the stop valves of low pressure gas pipe, high pressure gas pipe, and
liquid pipe, air balance pipe and oil balance pipe;
11. Power on, pre-heat the unit;
12. Whether the connected indoor unit quantity is the same with the actual
quantity under the spot check SBOX situation;
13. Whether the connected outdoor unit quantity is the same with the actual
quantity.
9.2. Test running
Use the wire controller (main unit matched) to control the operation of the unit,
check the following items according to the instruction. If there is error, check
the error according to the instruction and solve them.
9.2.1 Indoor unit
1. Check whether the switch of the wire/remote controller is normal;
2. Check whether the functional keys of the wire/remote controller are normal;
3. Check whether the indoor temperature adjusts normally;
4. Check whether the indication lamp is normal;
5. Check whether the manual operation button is normal.
6. Check whether water draining normally;
7. Check for excessive noise and vibration during operation.
9.2.2 SBOX
1. Check whether water draining is normally;
2. Check for excessive noise and vibration during operation and mode shifting;
9.2.3 Outdoor unit
1. Check for excessive noise and vibration during operation;
2. Check whether the produced wind, noise and condensed water affect
neighbors;
3. Check whether refrigerant leakage.
CAUTION
Once power is supplied, the unit should start instantly, but the condenser will
start 12 minutes later.
CLIMATE 5000 VRF 6720862460 (16/04)
TEST RUNNING |13

14 | NOTES
6720862460 (16/04) CLIMATE 5000 VRF
10. NOTES

CLIMATE 5000 VRF 6720862460 (16/04)
NOTES |15

Bosch Thermotechnology Ltd.
CotswoldWay, Warndon, Worcester WR4 9SW
All Enquiries: 0330 123 3004
www.bosch-industrial.co.uk
Other manuals for CLIMATE 5000 VRF RDCI Series
11
This manual suits for next models
6
Table of contents
Other Bosch Switch manuals

Bosch
Bosch VSS7390/01T User manual

Bosch
Bosch NPD-6001A User manual

Bosch
Bosch LTC 5104 Series User manual

Bosch
Bosch Universal switch II Operator's manual

Bosch
Bosch ICP-EZTS User manual

Bosch
Bosch LTC 8500 User manual

Bosch
Bosch Universal Switch Flex User manual

Bosch
Bosch Rexroth HED 8 Series User manual

Bosch
Bosch LTC 5141 Series User manual