2. Installation
IMPORTANT: Read this before tting the WC valve.
Flushing directly from the mains water supply
When ushing WCs or urinals directly from the mains, the Water Regulations require that the water supply
be protected by a suitable category 5 protection method or device.
In the case of WCs, this can be achieved in three ways:
1 The use of a dedicated supply for ushing use only, supplied from a break tank that protects the mains
supply with a type AA, AB or AD air gap.
2 The use of a specic type of WC bowl which has been tested and shown to incorporate the equivalent
of a type AB air gap.
3 The use of a type DC pipe interrupter (supplied with all Cistermiser Direct Flushing products).
A note about type DC pipe interrupters
These devices have an integral air gap; it is therefore important that pipework design and WC bowl
selection are appropriate to ensure sucient ow to ush the WC while preventing water owing back up
and out of the air gap.
The DC pipe interrupter must be installed not less than 150mm above the spill over level of the WC pan.
Ensure you follow these key design & installation points
• Install the valve as high as possible above the WC bowl.
• Install a free-owing, low restriction connection from the valve to the WC bowl. Ensure the water system
can deliver min. 90 lpm.
• Use a large pipe size in the pipework between the DC pipe interrupter and the WC.
• The DC pipe interrupter is tted with a 100 lpm ow regulator to control the ow of water; if you still have
issues with the DC pipe interrupter overowing, it may be necessary to install a further ow restricting
device upstream of the valve.
NOTE:
For grey water/rain harvesting. Ensure
adequate ltering is tted, a 10μm lter is
recommended. NOTE:
For chemical water treatment. If the water
system had been treated with chemical dosing,
ensure the system is thoroughly ushed before
tting any Cistermiser products. Concentrated
chemicals in dead legs can damage the
product and result in failure. If the water is
treated with Chlorine Dioxide (ClO2), ensure
concentration levels are maintained below
5ppm.Ensure adequate ltering is tted, a
10μm lter is recommended.
NOTE:
As with all water containing products, limescale
in hard water areas can aect the products
performance. This can result in maintenance
to remove the limescale when required.Ensure
adequate ltering is tted, a 10μm lter is
recommended.