Installing the automated system
Preliminary checks
For the safety and correct operation of the automated system, ensure that the following conditions are met:
• e gate structure must be designed to be automated. In particular, the diameter of the wheels must conform to the weight of
the gate being automated, there must be a guide on top and mechanical limit switches sized to suit the weight and speed of the
movable leaf, to avoid derailment of the gate;
• Initially, leave at least 10 cm of clearance between the movable leaf stopping points (open and close) and the mechanical
stops of the gate. e nal adjustment is made once the inverter programming precedure is completed.
Minimum distance 3 cm.
• e gate sliding rail must be linear and horizontal.
• Manual movement of the gate must be smooth along the entire stroke.
• e characteristics of the ground must guarantee sucient solidity of the foundation plinth.
• No tubes or electrical cables should be present in the plinth digging area.
• If the gearmotor is exposed to vehicle transite, provide for adequate protection against accidental impact, when possible.
• Ensure that there is an ecient earth plate for connecting the gearmotor.
Should various elements not need the above-mentioned conditions, adjust them so they do.