5.2.3 Connection with LISN
1. Connect an earth bonding wire from the earth stud on the CG100/500 to a
reliable earth point, ensuring a good connection.
2. Connect the supplied Power cord from the AC socket on the CG100/500 to
the mains EUT outlet on the LISN.
Ensure the connections to the receiver/analyzer are as used for measuring the
EUT, with any pre-amplifiers and/or transient limiters switched on.
5.2.4 Connection with ISN
1. Connect an earth bonding wire from the earth stud on the CG100/500 to a
reliable earth point, ensuring a good connection.
2. Connect the RJ-11 or RJ-45 cable from the RJ11/RJ45 connector on
CG100/500 to the RJ11/RJ45 connector on EUT port of ISN.
5.2.5 Recommends of site validation
The CG100/500 Comb generator can be used to validate test site or used to daily
check. In order to minimize the measure deviation, the same setup installation at
each test is in need, and the follow items have to be considered.
1. The same position and orientation of CG100/500.
2. The same cable placement, include Power cord, ground wire, RJ11 and RJ45
cables.
3. The same cable length, it would be best to use the same cable for each test.
4. Ground connection point must be connect to the same point for each test and
has good connection.