6
STP-SCIIIC: For 240 Volt hook signal; 380-415 Volt, 3 phase, 50Hz ¾ , 1 ½ , 3 and 5 Horsepower pumps.
Installation Instructions
1. Install STP per applicable Installaon and Owner’s Manual.
2. Remove cover of STP-SCIIIC and mount base to wall or other surface.
3. Connect input power of 380-415V for STP-SCIIIC to L1, L2, L3 and Ground wire to terminals.
(See Figure 2.) On High Capacity Pumps (3HP & 5HP) there is no need to connect the Thermal Overload
wires (blue) coming from the pump as long as an STP-SCIIIC is being used and is calibrated properly.
4. Connect dispenser hook signal or other equipment to terminals, 240V supply and return for STP-SCIIIC.
5. Using an ohmmeter, conrm M1, M2 & M3 have connuity to pump. Also, make sure M1 to Ground, M2 to
Ground, and M3 to Ground are not shorted.
6. Connect motor leads to M1, M2 and M3, and Ground wire to terminals.
7. Set SW1 Poles 4 and 5 for the motor Horsepower rang (see Table 3).
8. For Stand Alone installaon, set (SW1) poles 1-3 per Table 2 (Factory Set). If installed as Master-Slave and/
or Alternang Circuit go to “Master-Slave/Alternang Circuit” secon.
9. Aach cover of controller to base. Then go to “Calibraon” secon to complete installaon.
WARNING Always replace the cover of the STP-SCIIIC before applying power. Failure to do so could
result in severe injury or death.
Calibration
Note: It is recommended to calibrate all manifolded Master and Slave controllers at the same me.
1. Turn on power supply to the STP-SCIIIC. The green light indicator will come on steady, the red light
indicator will ash 8 mes and an audible alarm will sound, thus indicang the controller is Uncalibrated.
Note: The audible alarm will sound each me the red light indicator ashes. During the calibraon process,
do not silence the alarm. Once the calibraon process has been completed, an alarm can be silenced when an
abnormal condion is present by briey depressing the push buon. See “Troubleshoong Guide” for details.
2. Press and hold the push buon on the boom of the box unl all three light indicators blink alternately.
This will take approximately 10 seconds. At this point the push-buon should be released.
3. The handle on the dispenser should then be lied to turn the pump on (for more than 16 seconds). Aer
16 seconds the controller will take a “snapshot” of the voltage, current and power. The three lights will
quit alternang and only the green light should remain ashing. This will indicate the calibraon has been
completed and the dispenser handle can then be turned o. If the controller(s) will not calibrate, see the
“Troubleshoong Guide” secon.
Calibration Tips
The “snapshot” values will be used as the nominal values. The calibraon process will be aborted if not
completed within 10 minutes or if the push buon is depressed during calibraon. The calibraon must be
done at zero ow. If an electronic line leak detector is being used, it is important that the STP-SCIIIC be in the
calibraon mode (all three lights ashing alternately) before the dispenser handle is turned on. Otherwise, the
STP-SCIIIC will not turn on and the line leak detector will likely detect a fault. If the line leak detector shows a
fault, it will not provide a dispenser hook signal to the STP-SCIIIC and it will not be possible to calibrate the STP-
SCIIIC unl the line leak detector is reset.
Note: All STP-SCIIICs must be calibrated prior to operaon.
Note: All three indicator lights will ash alternately in calibraon mode.
Note: When calibrang system and dispensers that are blenders, both STP-SCIIICs must be calibrated
simultaneously by selecng the mid-grade at the dispenser.
Note: The calibraon data is retained in non-volale memory (i.e. it is saved in the event of power loss to the
controller).