4.3 Filling
1. Unscrew the reservoir cover lock nut (1) and remove the reservoir cover (2).
2. Using clean, recommended fluid fill the reservoir to approximately 2/3 full.
3. Refit the reservoir cover and re-tighten the reservoir cover lock nut (1).
4. Connect the required pipes and equipment to the outlet ports.
4.4 Priming the System
There are two methods: vacuum priming to extract the air or pre-filling the system.
Note: If air remains in the system, full pressure cannot be achieved as the air in the fluid
compresses. Air must be removed from the system fluid.
Both priming methods require the pump to be held in the vertical position to keep the
reservoir bleed hole (4) in fluid. Do not allow air to enter the system through this bleed hole
(4).
4.4.1 Vacuum Priming (Figure A2)
1. Connect the equipment as detailed in “Operation” on page 4.
2. Air can be removed using the vacuum facility on the pump.
Note: This method should not be used with vacuum-sensitive equipment.
3. Turn selector valve fully out, counterclockwise (vacuum) position.
4. Turn the volume adjuster valve fully counterclockwise (out) position.
5. Pump until bubbles stop appearing in the reservoir, (this generates a vacuum in the
system).
6. Turn the selector valve fully in, (this action releases the vacuum and rapidly fills the
system with fluid from the reservoir). It is advisable to generate a small hydraulic
pressure, then release this pressure and repeat the vacuum priming sequence above
a second time, to verify that any air in the system has been removed.
7. The pump and connected system is ready for use.
4.4.2 Pre-filling
1. Connect the equipment as detailed “Operation” on page 4.
2. Turn the selector valve fully clockwise (in) position.
3. Loosen the reservoir cover lock nut (1) to open the reservoir cover (2) and let
atmospheric pressure into the top of the reservoir.
4. Open the bleed valve on the UUT.
5. Carefully operate the scissor-action handles to fill the system. Stop pumping when
fluid comes out of the bleed valve.
6. Close the bleed valve on the UUT.
7. If necessary, top-up the reservoir to the 2/3 level with clean fluid.
8. Secure the reservoir cover by tightening the reservoir cover lock nut (1).