GSL GSL-H-12KLV-US User manual

POWER Inverters
GSL-H-12KLV-US
PV Energy
Import
Today:
Total:
Today:
Total:
Discharge Energy
Today:
Total:
Today:
Total:
Consumption
Hybrid 5.0 inch Big Touchscreen LCD Display
Normal
0.1V 0W
10240W
Battery
PV
Backup Loading
Home Loading
Grid
75%
51.9V
237.4V
49.99Hz
4936W
2W
0W
237.6V
49.99Hz
0.1V 0W
0.1V 0W

1
About This Manual
CONTENTS
Safety
Brief Introduction
2
Safety Instruction
1.1
System Solution
2.1
Installation
3
Packaging List
3.1
Location Selection and Installation
3.2
Connection Overview
3.3
PV Connection
3.4
System connection
3.
AC Coupling Installation Connection
3.8
01
01
01
03
03
04
04
07
04
07
08
Battery p
Battery
ower cable connection
3. 10
Battery communication cable connection
3.5.2 10
Grid&EPS load Connection
3.6 12
Grid type selection
3.6.1 12
AC cable connection
3.6.3 13
Parallel System Connection
3.9
3.9.1 Connection for paralleling system
18
20
20
Grid and EPS load connection for split-phase service
3.6.2 12
Requirements for installation location
3.2.1 04
Installing the inverter
3.2.2 05
Connection
3.5 10
CT/Meter connection
3.6.4 13
Working with Generator
3.7 15
Generator system connection
3.7.1 15
Generator Startup and stop settings
3.7.2 17

24
24
26
Operation Guide
4
4.1
31
31
31
31
35
Troubleshooting & Maintenance
Regular Maintenance
5.1
LED Displays
5.2
Troubleshooting Based On LCD Displays
5.3
Fan replacement
5.4
5
Operation Mode
Rapid Shutdown
4.2
Monitor System Setup
3.10 21
3.10.1
3.10.2
Wifi/GPRS/4G/WLAN dongle connection 21
22
Setup the Monitor system
3.10.3
3.10.4
Set homewifi password to dongle 23
23
Third party RS485 communication
4.1.1
4.1.2
Self-usage mode (Default) 24
25
Charge first mode
4.1.3 AC charge mode 26
27
LCD Display
4.3
4.3.1
4.3.2
Viewing information and alarm/fault record 27
28
Setting parameters
30
Start-up and shut down the inverter
4.4
4.4.1
4.4.2
Start up the inverter 30
30
Shut down the inverter

Dangers of High Voltages and Large Current
Beware of high PV voltage. Please turn-off the DC switch of PV Panel output before and during
the installation to avoid electric shock.
Beware of high grid voltage. Please turn-off the AC switch of grid connection before and during
the installation to avoid electric shock.
Do not operate the inverter when it's working, only the LCD and buttons can be touched in
limited cases by qualified personnel, other parts of the inverter can be touched when the
inverter is under a safe state (e.g. fully shut-down).
Inspect the connections are good between inverter and PV, battery and grid during installation
to prevent damages or injuries caused by bad connections.
Inspect relevant existed wiring on-site of the installation is under good condition before
installation, operation or maintenance.
Make sure the inverter is well grounding, an operator should make sure himself is good
protected by reasonable and professional insulation measurements (e.g. personal protective
equipment (PPE)).
Do not connect or disconnect any connections (PV, battery, grid, communication etc.) of the
inverter when it's working.
Beware of large current of the battery output. Please turn-off the battery module before and
during the installation to avoid electric shock.
Do not open the inverter when it's working to avoid electric shock and damages from live
voltage and current from the system.
1. Safety
1.1 Safety Instruction
General Safety Instructions
The inverter has been designed and tested strictly according to international safety regulations. Read all safety
instructions carefully prior to any work and observe them at all times when working on or with the inverter. The
operator must be qualified personnel and the installation must be capable with relevant national or international
standards or regulations.
Incorrect operation or work may cause:
- injury or death to the operator or a third party
- damage to the inverter and other properties belonging to the operator or a third party.
There are many safety issues need to be carefully notified before, during and after the installation, and also in
future operation and maintenance, following is important safety notifications to operator, owner and user of
this product in appropriate usage.
Important Safety Notifications
01

Beware of burning hurt, the inverter and some parts of the system could be hot when working,
please do not touch the inverter surface or most of the parts when they are working. During
inverter working states, only the LCD and buttons could be touched.
All connections must be in accordance with local and national regulations and standards.
Only when permitted by utility grid, the inverter and system can interconnected with the utility
grid.
Avoid misoperation and Inappropriate Usage
All the work of this product (system design, installation, operation, setting , configuration
and maintenance must be carried out by qualified personnel as required.
All the warning lable or nameplate on the inverter must be clearly visible and must not be
removed, covered or pasted.
The installation should choose a right position and location as required in this manual with
consideration to safety of users' in future operation.
Please keep the children away from touching or misoperation the inverter and relevant system.
The qualified personnel should have had training in the installation and commissioning of
the electrical system as well as dealing with hazards, also they should have the knowledge
of the manual and other related documents. As the installer or operator they are required
to be familiar with local regulations and directives.
Please carefully read this manual before any work carried out on this inverter, after the
installation, please keep this manual carefully stored and easy to access at any time.
02

2. Brief Introduction
2.1 System Solution
This product and relevant system is suitable for following system applications (system diagram):
1 . Solar and battery storage system 2. AC Coupling with existed solar system
3. On-grid solar system without battery
(Support EPS even without battery)
4 . Off-grid and back-up applications
5. Single and three phase paralleling system 6. Energy storage system with peak shaving Function
03
Existed On-grid Solar System
Reserved Battery & UPS Interfaces
Router Viewer
Grid

3. Installation
3.1 Packaging List & Storing
Packaging List
When the packaging is unpacked, the inner components should be the same as described in
below packaging list.
Hybrid Inverter X1
User Manual X1
Communication
Port Cover X6
Wi-Fi dongle X1
Optional
1.3" CT x2
Expansion Screw
and Tube X4
Cross Head
Screw X17
Battery communication
cable Length 2mx1(Grey)
Bracket: wall-mounted×1
3.2 Location Selection and Installation
3.2.1 Requirements for installation location
a. The wall for mounting should be strong enough to bear the weight of inverter .
b. Please maintain the minimum clearances below for adequate heat dissipation.
400mm
400mm 400mm
400mm
04
Parallel communication
cable L=2m×1(Grey)

c. Never install the inverter in a place with direct sunlight, rain or snow. Please refer to below figure and select a well
shaded place or install a shed to protect the inverter from direct sunlight, rain and snow etc. PROTECT the LCD screen
from excessive UV exposure
d. The inverter should be installed upright on a vertical surface.
3.2.2 Installing the inverter
The inverter is wall-mounted type, should be installed on a vertical, solid mounting surface, such as wood studs,
brick or concrete wall. Two or more persons may be needed to install the inverter due to its weight. The slots on
mounting bracket can accommodate various stud spacing from 12inch to 16inch.
>75 90 >90 90
05
The mounting steps are as below: (Use brick wall as example)
2 in
4 in
16 in
18 in

Step1. Mark the positions of drill holes with the mounting bracket, then drill 4 holes of 8mm(5/16inch) diameter
and make sure the depth of the holes is deeper than 50mm(2inch).
Step3. Hang the inverter onto the wall-mounting bracket and lock the inverter on the wall using 2 self-tapping
screws on the top of the inverter.
Step2. Install the expansion bolts into the holes and tighten them, then use the corresponding nuts and
washers (packaged together with the expansion bolts) to install and fix the wall-mounting bracket on the wall.
06
For installation on wood studs
Fasten the mounting bracket on the studs with 4 wood screws, then hang the inverter onto the bracket and lock
the inverter on the wall with 2 self-tapping screws.
Please note that the wood screws and self-tapping screws are not provided with the inverter. Installers need to
prepare the screws before installation.

3.3 Connection Overview
3.3.1 System Connection
The system connection diagram is as below( for US version):
Please prepare the breakers before connetion, breakers selection recommendation for both DC and AC
Overview of Connection Ports
UPS Load
Inverter model
PV Breakers(2Px4)
Main Breaker(2P)
Geneartor breaker
MPPT1 string 1 : 600V/20A
200A/240Vac when ups is used for whole home backup
200A/240Vac when ups is used for whole home backup
12K
100A/240Vac when ups is used for partial load backup
MPPT2: 600V/20A
Load Breaker(2P)
Battery Breaker(2P) 100V/300A
MPP
7777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777.09in)
95 mm(3.74in)
77777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777
777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777777

08
Overview of the cable box
Mains model
j. CAN Matching resistance
FAN1
f. FAN2
g. TEMP
FAN3
485B
485A
GND
RSD
+VIN
+12V
NO
GEN
NC
NO
DRY
NC
b. Battery Communication Interface
c. CT Interface
e. Parallel cable
communication Interface
a. DRM Interface
h. Meter
d. INV485
a). DRM port(Applied only in AU)
c). CT Interface: please check Chapter 3.6.4 for CT connection
d). INV 485: Debugging port
b). Battery communication port(CAN&RS485)
please check Chapter 3.5.2 for Pin definition
please check Chapter 3.9 for Parallel connection
e). Parallel communication port
f). FAN1/2/3
g). TEMP: Connection for temperature sensor of lead-acid battery
h). Meter 485B&485A: For Meter communication
i). VIN/+12V: Connect a outside emergency switch on these 2 terminals
j). CAN Matching resistance: Set DIP switch when use inverters in parallel
k). GEN(NO, NC): Connection for generator auto-start function
l). DRY(NO,NC): reserved
3.4 PV Connection
* Please check the lowest ambient temperature of the location of the installation. The rated
Voc on solar panel nameplate is obtained at 25 temperature. Solar panel Voc will increase
with the decreasing of ambient temperature. Please ensure the Max.solar string voltage
corrected at the lowest temperature not exceed the inverter max input voltage 550V for safe.
PV connection of this hybrid inverter is same as traditional on-grid solar inverter (string inverter).
M i n i m u m V o l t a g eCable Size
2
4 - 6 mm 600V
Cable Requirement:
i.
k.
l.

1. The inverters has triple MPPTs. For MPPT1, users can connect two strings. For MPPT2 and
MPPT3, users can connect one string.
2. When users connect 2 strings to MPPT1, make sure the two strings has same quantity of
solar panels. The inverter will limit the total MPPT1/MPPT2/MPPT3 input current to
25A/15A/15A automatically.
3. The inverter will limit the max solar input power to 18kW totally.
09
face the same direction
Steps for PV connection
d. Route the PV conductors through the
conduit and conduit fitting into the inverter.
a. Strip off 1/4-5/16inch(6~8mm) insulation
on the PV string positive and negative
conductors.
b. Use wire ferrules for PV string conductors
if they are stranded wire type.
c. Insert the conduit fitting to the opening
for PV connection and tighten it from inside
using the counter nut.
e. Secure the cable gland in place.
f. Ensure that the cables are connected
correctly and securely. Then take appropriate
measures to ensure that the conduit and conduit
fittings are fastened reliably, and seal the cable
entry holes.

Step 1: Strip 1/4-5/16inch(6-8mm) insulation from the cable end and crimp OT rings for the cable ends.
Step 3: Secure the conduit fitting to the enclosure using the counter nut.
10
3.5 Battery Connection
3.5.1 Battery power cable connection
2
3/0-4/0 AWG(85-100 mm ) 600V
Cable Requirement:
12K
Step 2: Route the battery power cable through the cable gland, connect positive to BAT+,negative to BAT-.
Step 5: Fix the cable gland in place.
Step 4: Fasten the OT rings of battery positive and negative cables to the lugs according to the marking.
Polarity reverse will damage the inverter!
Install a DC isolator between battery and
inverter can avoid potential damages
caused by electric arc.
3.5.2 Battery communication cable connection
A correct battery communication cable must be used to connect the battery to the inverter when users
choose lithium-ion battery type. Please select ‘Lead-acid ‘ type if the lithium battery can not communicate
with inverter. The battery communication port on inverter is a RJ45 socket, Pin for the RJ45 plug of the
communication cable is as below. Make the communication cable according to the below inverter Pin and
the correct pinout of communication port on battery. The inverter supports both CAN and
RS485 communication.
Pin
1
Description
2
3
4
NC
GND
NC
BAT CAN H
5
6
7
8
BAT RS485 A
NC
BAT RS485 B
Pin 1 2 3456 7 8
BAT CAN L
Battery CAN&RS485
20(N.M)
Minimum Voltage
Model Cable Size Torque for cable connection OT ring
RNB100-10

Battery type
Lithium brand Bat capacity(Ah)
HV1
Reconnect time(S)
LV1
HF1
LF1
USA
Grid regulation
Debug
Charge
Discharge
Device info.
Basic
Advanced
Set
V
V
S
S
S
S
Hz
Hz
HV2
LV2
HF2
LF2
V
V
S
S
S
S
Hz
Hz
V
V
S
S
S
S
Hz
Hz
HV3
LV3
HF3
LF3
Grid type Gird Freq 60
1:Lead-acid
2:Lithium Battery
Set
240V/120V
Battery type
Lithium brand Bat capacity(Ah)
HV1
Reconnect time(S)
LV1
HF1
LF1
USA
Grid regulation
Debug
Charge
Discharge
Device info.
Basic
Advanced
Set
V
V
S
S
S
S
Hz
Hz
HV2
LV2
HF2
LF2
V
V
S
S
S
S
Hz
Hz
V
V
S
S
S
S
Hz
Hz
HV3
LV3
HF3
LF3
Grid type Gird Freq 60
1:Lead-acid
2:Lithium Battery
Set
240V/120V
After battery power cable and communication cable connection, users need to enter Advanced setting and
choose Battery type and brand on the inverter LCD
11
1.
Please make sure the lithium-ion
battery to be used is compatible with
inverters. Please contact
your
distributor for updated battery
compatible list.
2.
If you are using multiple battery
modules with the inverter, the inverter
communication cable must be
connected to the master battery. Please
check with your battery supplier for
battery master and slave settings.
1. The temperature sensor for lead
-acid battery is optional. If you need
it, please contact distributor for
purchasing.
For Li-ion battery
For Lead-acid battery
2. There are three stages for lead-acid
battery charging. For charging/discharge
related parameters, please check charge
/discharge setting page.
3.6 Grid&EPS load Connection
3.6.1 Grid type selection
The inverter can be used with 120/240V split-phase , 120/208V split-phase , and 240V single phase service.
You can choose the grid type on LCD. If you are going to use the inverter with 240V single phase supply, please
contact your supplier for the correct connection diagram.
The inverter has passed the main grid-connection regulations in the US(IEEE1547, CA Rule21, HECO Rule 14H,
etc.). Users can choose different Grid Type in Advanced program as below:
Charge first(PV)
Time 1
Time 2
Time 3
Charge first power(kW)
Stop charge first SOC(%)
::
::
:: Stop charge first Volt(V)
Debug
Charge
Discharge
Device info.
Basic
Advanced
Set
Absorb voltage(V)
Float voltage(V)
Equalization time(hour)
Equalization Volt(V)
Equalization peroid(day)
Lead-acid: Set
Start derate Volt(V)

12
3.6.2 Grid and EPS load connection for split-phase service
Connection diagram for 120/240V is as below. The connection diagram for 120/208V split phase service is
roughly the same except that generator is not supported.
The inverter can be connected to the load side of the service disconnecting means if the busbar rating in the
main panel can meet the NEC705.12(B)(3) requirements. Otherwise, a Line side connection can be made to
avoid an expensive main panel upgrade.
L1 L2 N
EPSGEN GRID
L1 L2 L1 L2
Utility Meter
Main Panel
Generator
Inverter Disconnect
Generator
Disconnect
Backup Panel
Grid and EPS Load Connection
CT
PE
NPE
L1 L2
NPE
L1 L2
PE
N
L2
L1
CT 2
CT 1
Kw. h
7 9 8 6 6
480r/kw. h 10A

a. Strip off 5/16-3/8inch(8~10mm) insulation sleeve on the cables.
3.6.4 CT/Meter Connection
2
3-2AWG(25-35mm ) 6-7mm 600V
Cable Requirement:
13
3.6.3 AC cable connection
b. Use wire ferrules if the cables are made of find stranded wires.
c. Secure the conduit fitting to the enclosure using the counter nut of the fitting.
d. Fasten the grid and EPS load cables to the terminal block in accordance with the markings.
e. Secure conduit to the conduit fitting.
f. Checks that the cables are connected correctly and securely, then take appropriate measures to ensure
that the conduit and conduit fitting are secured reliably, and seal the cable entry holes.
To measure the power import from and export to the grid, a pair of CTs or one triphase meter must be
installed at the service entry point in or near the main service panel. We standard supply 2 CT for one
inverter.
The CT interface for 2 CTs connection is a RJ45 port ,we have made a RJ45 plug on those 2 CTs in advance,
so you can connect it to port directly.
CT Port Pin definition
Pin
1-4
Description
reserve
CT2N
CT2P
CT1N
5
6
7
8
Pin 1 2 3456 7 8
CT1P
41(N.M)
Current Cross-section Cable Diameter Minimum Voltage Torque for cable connection OT ring
100A
200A 9-10mm 600V 41(N.M)
RNB38-10S
RNB100-10
2
2/0-3/0AWG(70-85mm )

Please refer to the above connection diagram for the correct positions of CTs. Please clamp the 2 CTs
on the L1 and L2 wires at the service entry point in the main service panel. The arrows on the CTs must
point to inverter side.
14
Pin5
CT 2
CT 1
Pin6
Pin7
Pin8
TO Grid
TO PCS
TO Grid
TO PCS
L1
L2
PN
PN
5 6
NC
NO
NC
NO
+VIN
-12V
485B
485A
GND
RSD
DRY
GEN
GRID
The Luxpower inverters support two ratios of CT clamp- 1000:1 and 3000:1 . The CT ratio of the CTs in
the accessory bag is 3000:1. If you are using a 3rd party CT, please ensure the CT ratio is either 1000:1
or 3000:1, and then select the correct CT ratio setting in the inverter monitor page or on inverter LCD.
CT Clamp Ratio
The CT wires can be extended with a common ethernet cable if the length is not enough. A RJ45 adapter
is needed for the extending. The CT wires can be extended up to 300ft(around 100m).
Extend CT clamp cable

Meter or CT
Meter type
MODBUS addr
PV input
CT ratio
Debug
Charge
Discharge
Device info.
Basic
Advanced
Set
PV Arc
PV Arc fault clear
Vpv start (V)
Set
1/1000
1: CT
0: Default
PV1,PV2 independent
Set
AC couple on EPS side
Offgrid output EPS output
without Battery Micro-grid
Charge last
CT direction reversed
Seamless switch RSD disable
15
Meter Connection
Currently only EASTRON SDM630-Modbus meters can be used. If you
need to use meter for import/export detection instead of CTs, you need
to connect it to the Meter 485A and 485B terminals on the inverter,
please contact for detailed guideline.
FAN1
FAN2
TEMP
FAN3
485B
485A
GND
RSD
+VIN
+12V
NO
GEN
NC
NO
DRY
NC
Meter
3.7 Working with Generator
This hybrid inverter can work with generator. There are Gen ports on the inverter for generator connection.
3.7.1 Generator system connection
L1 L2 N
EPSGEN GRID
L1 L2 L1 L2
Utility Meter
Main Panel
Generator
Inverter Disconnect
Generator
Disconnect
Backup Panel
Generator Connection-Partial Backup
PE
NPE
L1 L2
NPE
L1 L2
PE
N
L2
L1 2-wire start
CT
CT 2
CT 1
Kw. h
7 9 8 6 6
480r/kw. h 10A

16
CT
L1 L2 N
EPSGEN GRID
L1 L2 L1 L2
Utility Meter
Service
Disconnect
Generator
Inverter Disconnect
Generator
Disconnect
Backup Panel
Generator Connection-Whole Home Backup
PE
NPE
L1 L2
PE
N
L2
L1
PE
N
L2 L1
2-wire start
CT 2
CT 1
When generator is started, all the loads connected to EPS will be supplied by the generator. Meanwhile battery
will be charged.
The pass-through relay on the generator port is 100A. When generator is on, please ensure the total load and
charge current will not exceed 100A.
The generator start signal shall connect to COM board GEN(NO,NC port) if users want to start generator remotely .
NC
NO
NC
NO
Generator
+VIN
-12V
485B
485A
GND
RSD
DRY
GEN
NO
NC
NO
GEN
Kw. h
7 9 8 6 6
480r/kw. h 10A

Debug
Charge
Discharge
Device info.
Basic
Advanced
Generator
Charge start Volt(V)
Charge end Volt(V)
Gen peak-shaving power(kW)
Gen peak-shaving
Bat charge current limit(A)
Charge start SOC(%)
Charge end SOC(%)
Set
Smart load
Smart load start SOC(%) Start PV power (kW)
Smart load end SOC(%)
Set
17
3.7.2 Generator Startup and Stop settings
Bat charge current limit(A)
AC charge
Time 1
Time 2
Time 3
::
::
::
Bat charge control
Debug
Charge
Discharge
Device info.
Basic
Advanced
Set
Use SOC %
Use Bat V
Set
Stop AC charge SOC(%)
Stop AC charge Volt (V)
AC charge power(kW)
Depends on the Bat charge control setting, system will use either battery SOC or battery voltage to judge
if system need to start or stop the generator.
-When battery is discharged to cut-off settings
or there is force charge request from battery.
or when the battery voltage or SOC lower than Generator Charge start Volt/SOC settings,
Generator Start Conditions
Generator Stop Conditions
when battery voltage or SOC higher than Charge end Volt/SOC settings value.
When utility fails and
Table of contents
Other GSL Inverter manuals
Popular Inverter manuals by other brands

Hyundai power products
Hyundai power products QL2000i instruction manual

Hitachi
Hitachi J100-E2 SERIES Service manual

Honeywell
Honeywell HW400PI owner's manual

Fulling
Fulling DZB200M user manual

WESTECH
WESTECH VS Series instruction manual

Champion Global Power Equipment
Champion Global Power Equipment 201057 quick start guide