Running the program
After the off temperature has been entered the display will show ‘run’.
Pushing the RUN button starts the program.
When the program is started the load will rise uncontrolled to the start
temperature. The up ramp will not start until the load temperature gets
within 15oC of the start temperature. During this phase the up LED will
be on and the display will flash between ‘Hold’ and the load
temperature. When the load gets within 15oC of the start temperature it
will ramp up at the set rate. The ‘Hold’ feature also applies during the up
ramp, so that if the setpoint exceeds the load temperature by 15oC or
more the up ramp will hold.
When the soak temperature is reached it will remain there for the set
time. During the soak time the display will flash between the load
temperature and the elapsed time. When the elapsed time is shown a
decimal point separates the hours and minutes. It will then ramp down
at the set rate until the off temperature setting is reached when it
switches off, which is shown by all LEDS being off.
Showing the setpoint value
During the temperature cycle, pushing the SP button displays the
setpoint temperature instead of the load temperature. Also the UP,
SOAK or DOWN LEDS will show which segment of the cycle is being
done. If it is required to terminate the program at any time, pushing the
RESET button shows ‘rst’ in the display and the RESET button must be
pushed again while this is being shown. The display will then show the
load temperature and all LEDS will be off.