Luffing Jib Raising Procedure
Luffing Jib No. 135 on Boom No. 76
Manitowoc Cranes, Inc.
8799-A, 2016-06-03
Manitowoc, Wisconsin 54220 U.S.A.
1/6
Recommended boom and luffing jib raising and lowering procedure:
14000 SERIES 1 must be equipped with 127,000 lb (57 610 kg) crane counterweight and 0 lb (0 kg) carbody
counterweight. 14000 SERIES 2 must be equipped with 168,000 lb (76 200 kg) crane counterweight and
53,000 lb (24 040 kg) carbody counterweight. 14000 SERIES 3 must be equipped with 178,000 lb (80 740 kg)
crane counterweight and 70,500 lb (31 980 kg) carbody counterweight. Refer to luffing jib rigging assembly
No. A18387 for boom and luffing jib make-up of inserts, pendants, struts, strut raising and lowering procedure,
jib stop setup and operation and miscellaneous parts, etc. Refer to Operator’s Manual for setup and installation.
Three methods may be used to raise and lower boom and luffing jib combinations, depending on length:
A. Layout In-Line Method
Boom and luffing jib are assembled in layout, end-to-end, position. Slowly raise boom until luffing jib stop strut
is just clear of ground. Attach luffing jib stop pendants and unpin luffing jib stop inner strut from retracted
position. Slowly raise boom until luffing jib stop strut is fully extended and pins engaged (approximately 168
degree boom-to-luffing jib angle). Tighten luffing jib suspension with luffing jib hoist. Boom and luffing jib can
then be raised simultaneously using only the boom hoist. Reverse this procedure when lowering boom and
luffing jib.
Boom and luffing jib combinations in following tables may be raised and lowered using layout in-line method.
WITH OR WITHOUT BOOM CATWALKS
14000 SERIES 1
Maximum Boom and Luffing Jib Lengths Lifted Unassisted
Using In-Line Method
Boom
Length
Over End of
Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 135 Luffing Jib No. 135
Feet Meters Feet Meters Feet Meters
65.6 20,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
75.5 23,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
85.3 26,0 70.0 - 170.0 21,3 - 51,8 70.0 - 150.0 21,3 - 45,7
95.1 29,0 70.0 - 170.0 21,3 - 51,8 70.0 - 130.0 21,3 - 39,6
105.0 32,0 70.0 - 150.0 21,3 - 45,7 70.0 - 110.0 21,3 - 33,5
114.8 35,0 70.0 - 120.0 21,3 - 36,6 70.0 - 80.0 21,3 - 24,4
124.7 38,0 70.0 - 90.0 21,3 - 27,4 — —
134.5 41,0 70.0 21,3 — —
Load blocks, hook and weight ball on ground until boom and luffing jib are erected.
REFERENCE ONLY!
8799-A, 2016-06-03
Manitowoc Cranes, Inc.
2/6
Manitowoc, Wisconsin 54220 U.S.A.
14000
Luffing Jib Raising Procedure
Luffing Jib No. 135 on Boom No. 76
WITH OR WITHOUT BOOM CATWALKS
14000 SERIES 2 and SERIES 3
Maximum Boom and Luffing Jib Lengths Lifted Unassisted
Using In-Line Method
Boom
Length
Over End of
Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 135 Luffing Jib No. 135
Feet Meters Feet Meters Feet Meters
65.6 20,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
75.5 23,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
85.3 26,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
95.1 29,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
105.1 32,0 70.0 - 170.0 21,3 - 51,8 70.0 - 170.0 21,3 - 51,8
114.8 35,0 70.0 - 170.0 21,3 - 51,8 70.0 - 160.0 21,3 - 48,8
124.7 38,0 70.0 - 170.0 21,3 - 51,8 70.0 - 130.0 21,3 - 39,6
134.5 41,0 70.0 - 150.0 21,3 - 45,7 70.0 - 110.0 21,3 - 33,5
144.4 44,0 70.0 - 140.0 (a) 21,3 - 42,7 70.0 - 90.0 21,3 - 27,4
154.2 47,0 70.0 - 110.0 21,3 - 33,5 — —
164.0 50,0 70.0 - 90.0 21,3 - 27,4 — —
Load blocks, hook and weight ball on ground until boom and luffing jib are erected.
(a) When equipped with boom catwalks, this combination of boom and luffing jib
length cannot be raised using In-Line method.
REFERENCE ONLY!
14000
Luffing Jib Raising Procedure
Luffing Jib No. 135 on Boom No. 76
Manitowoc Cranes, Inc.
8799-A, 2016-06-03
Manitowoc, Wisconsin 54220 U.S.A.
3/6
B. Layout Jack-Knife Method:
(Longer boom and luffing jib combinations must be raised and lowered using this method)
Caution: Anytime luffing jib point rollers are in contact with ground during raising or lowering procedure,
disengage swing lock and release swing brake.
Raising:
Boom and luffing jib are assembled in layout, end-to-end, position. Slowly raise boom until luffing jib stop strut
is just clear of ground. Attach luffing jib stop pendants and unpin luffing jib stop inner strut from retracted
position. Slowly raise boom until luffing jib stop strut is fully extended and pins engaged (approximately 168
degree boom-to-luffing jib angle). Boom is then raised while luffing jib point wheels are allowed to roll on
ground. Tension should be applied to luffing jib hoist to keep luffing jib strut off luffing jib during boom raising.
Boom up until boom-to-luffing jib angle reaches value specified in table below or vertical, whichever occurs first.
Tighten luffing jib suspension with luffing jib hoist. Boom and luffing jib are then raised together using boom
hoist until boom reaches desired boom operating angle. Luffing jib radius must be within capacity chart before
swinging over side of machine when raising over end of blocked crawlers.
Lowering:
Position boom at 85 degrees prior to lowering luffing jib. Lower luffing jib until boom-to-luffing jib angle reaches
value specified in table below. Lower boom until luffing jib point wheels contact ground. If luffing jib is hanging
vertical, raise luffing jib a few degrees forward of vertical. Continue to lower boom while luffing jib wheels roll
along ground. Keep enough tension on luffing jib hoist to keep luffing jib strut off luffing jib. Stop lowering boom
when luffing jib stop pendants start to go into tension (approximately 168 degree boom-to-luffing jib angle).
Disengage luffing jib stop strut pins and lower boom to retract luffing jib stop inner strut. Pin strut in retracted
position.
REFERENCE ONLY!
8799-A, 2016-06-03
Manitowoc Cranes, Inc.
4/6
Manitowoc, Wisconsin 54220 U.S.A.
14000
Luffing Jib Raising Procedure
Luffing Jib No. 135 on Boom No. 76
Boom and luffing jib combinations in following tables require layout jack-knifing to a specified boom-to-luffing jib
angle for raising and lowering.
WITH OR WITHOUT BOOM CATWALKS
14000 SERIES 1
Maximum Boom and Luffing Jib Lengths Lifted Unassisted Using Jack-Knife Method
Boom
Length
Over End of Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 135
Boom to
Luffing Jib
Angle Luffing Jib No. 135
Boom to
Luffing Jib
Angle
Feet Meters Feet Meters Degrees Feet Meters Degrees
85.3 26,0 —— — 160.0 - 170.0 48,8 - 51,8 90
95.1 29,0 — — — 140.0 - 170.0 42,7 - 51,8 90
105.0 32,0 160.0 - 170.0 48,8 - 51,8 90 120.0 - 170.0 36,6 - 51,8 90
114.8 35,0 130.0 - 170.0 39,6 - 51,8 90 90.0 - 170.0 27,4 - 51,8 90
124.7 38,0 100.0 - 170.0 30,5 - 51,8 90 70.0 - 170.0 21,3 - 51,8 90
134.5 41,0 80.0 - 170.0 24,4 - 51,8 90 70.0 - 150.0 (c) 21,3 - 45,7 60
144.4 44,0 70.0 - 150.0 21,3 - 45,7 90 — — —
160.0 - 170.0 48,8 - 51,8 60 — — —
(a) 154.2 47,0 70.0 - 170.0 21,3 - 51,8 60 — — —
(b)(c) 164.0 50,0 70.0 - 110.0 21,3 - 33,5 60 — — —
Load blocks, hook and weight ball on ground until boom and luffing jib are erected.
(a) Requires lower boom point to be removed.
(b) Requires lower boom point and wire rope guide assembly No. 177364 to be removed.
(c) When equipped with boom catwalks, lowerworks jacking cylinders must be attached to 164.0 ft boom or
150.0 ft luffing jib on 134.5 ft boom over side of crawlers.
WITH OR WITHOUT BOOM CATWALKS
14000 SERIES 2 and SERIES 3
Maximum Boom and Luffing Jib Lengths Lifted Unassisted Using Jack-Knife Method
Boom
Length
Over End of Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 135
Boom to
Luffing Jib
Angle Luffing Jib No. 135
Boom to
Luffing Jib
Angle
Feet Meters Feet Meters Degrees Feet Meters Degrees
114.8 35,0 — — — 170.0 51,8 90
124.7 38,0 — — — 140.0 - 170.0 42,7 - 51,8 90
134.5 41,0 160.0 - 170.0 48,8 - 51,8 90 120.0 - 170.0 36,6 - 51,8 90
144.4 44,0 150.0 - 170.0 45,7 - 51,8 90 100.0 - 170.0 30,5 - 51,8 90
154.2 47,0 120.0 - 170.0 36,6 - 51,8 90 70.0 - 170.0 21,3 - 51,8 90
164.0 50,0 100.0 - 170.0 30,0 - 51,8 90 70.0 - 170.0 21,3 - 51,8 60
173.9 53,0 70.0 - 170.0 21,3 - 51,8 90 — ——
183.7 56,0 70.0 - 170.0 21,3 - 51,8 60 — ——
(a)(b) 193.6 59,0 70.0 - 170.0 21,3 - 51,8 60 — ——
Load blocks, hook and weight ball on ground until boom and luffing jib are erected.
(a) Requires lower boom point to be removed.
(b) When equipped with boom catwalks, this boom length requires wire rope guide assembly No. 177364 to be
removed and lowerworks jacking cylinders must be attached.
REFERENCE ONLY!
14000
Luffing Jib Raising Procedure
Luffing Jib No. 135 on Boom No. 76
Manitowoc Cranes, Inc.
8799-A, 2016-06-03
Manitowoc, Wisconsin 54220 U.S.A.
5/6
C. Fold Under Jack-Knife Method:
Raising:
Boom and luffing jib are assembled in fold under position. Slowly raise boom; luffing jib point wheels will roll along
ground. When luffing jib hinge pin is 30 Ft. (9.1m) off ground, connect luffing jib pendants. Move luffing jib top wire rope
guide to working position. Tighten luffing jib suspension with luffing jib hoist. Slowly raise boom until luffing jib is vertical
and luffing jib point wheels are clear of ground. Tighten luffing jib suspension with luffing jib hoist. Boom and luffing jib
are then raised together using boom hoist until boom reaches desired boom operating range. Luffing jib radius must be
within capacity chart before swinging over side of machine, when raising over end of blocked crawlers.
Lowering:
Position boom at 75 degrees prior to lowering luffing jib. Slowly lower luffing jib to vertical. Lower boom until luffing jib
point wheels are just clear of ground. Slowly boom down and assist luffing jib point wheels in fold under direction. Boom
down until luffing jib hinge pin is 30 Ft. (9.1m) off ground. Disconnect luffing jib pendants. Move luffing jib top wire rope
guide to stowed position. Raise luffing jib strut with luffing jib hoist until luffing jib strut is in line with luffing jib. Lower
boom and luffing jib to ground.
Boom and luffing jib combinations in following tables may be raised and lowered using fold under jack-knife method.
WITH OR WITHOUT BOOM CATWALKS
14000 SERIES 1
Maximum Boom and Luffing Jib Lengths Lifted Unassisted
Using Fold Under Jack-Knife Method
Boom
Length
Over End of Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 135 Luffing Jib No. 135
Feet Meters Feet Meters Feet Meters
95.1 29,0 70.0 21,3 70.0 21,3
105.0 32,0 70.0 - 80.0 21,3 - 24,4 70.0 - 80.0 21,3 - 24,4
114.8 35,0 70.0 - 90.0 21,3 - 27,4 70.0 - 90.0 21,3 - 27,4
124.7 38,0 70.0 - 100.0 21,3 - 30,5 70.0 - 100.0 21,3 - 30,5
134.5 41,0 70.0 - 110.0 21,3 - 33,5 70.0 - 110.0 21,3 - 33,5
144.4
(a) 154.2 44,0 70.0 - 120.0 21,3 - 36,6 — —
47,0 70.0 - 130.0 21,3 - 39,6 — —
Load blocks, hook and weight ball on ground until boom and luffing jib are erected.
(a) Requires lower boom point to be removed.
REFERENCE ONLY!
8799-A, 2016-06-03
Manitowoc Cranes, Inc.
6/6
Manitowoc, Wisconsin 54220 U.S.A.
14000
Luffing Jib Raising Procedure
Luffing Jib No. 135 on Boom No. 76
WITH OR WITHOUT BOOM CATWALKS
14000 SERIES 2 and SERIES 3
Maximum Boom and Luffing Jib Lengths Lifted Unassisted
Using Fold Under Jack-Knife Method
Boom
Length
Over End of Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 135 Luffing Jib No. 135
Feet Meters Feet Meters Feet Meters
95.1 29,0 70.0 21,3 70.0 21,3
105.0 32,0 70.0 - 80.0 21,3 - 24,4 70.0 - 80.0 21,3 - 24,4
114.8 35,0 70.0 - 90.0 21,3 - 27,4 70.0 - 90.0 21,3 - 27,4
124.7 38,0 70.0 - 100.0 21,3 - 30,5 70.0 - 100.0 21,3 - 30,5
134.5 41,0 70.0 - 110.0 21,3 - 33,5 70.0 - 110.0 21,3 - 33,5
144.4
154.2 44,0 70.0 - 120.0 21,3 - 36,6 70.0 - 120.0 21,3 - 36,6
47,0 70.0 - 130.0 21,3 - 39,6 70.0 - 130.0 21,3 - 39,6
164.0 50,0 70.0 - 140.0 21,3 - 42,7 70.0 - 140.0 21,3 - 42,7
173.9 53,0 70.0 - 150.0 21,3 - 45,7 ——
183.7 56,0 70.0 - 160.0 21,3 - 48,8 ——
(a)(b)193.6 59,0 70.0 - 170.0 21,3 - 51,8 — —
Load blocks, hook and weight ball on ground until boom and luffing jib are erected.
(a) Requires lower boom point to be removed.
(b) When equipped with boom catwalks this boom length cannot be raised using
Fold Under Jack-Knife method.
REFERENCE ONLY!

Other manuals for 14000

6

This manual suits for next models

1

Other Manitowoc Construction Equipment manuals

Manitowoc Grove TMS500-2 User manual

Manitowoc

Manitowoc Grove TMS500-2 User manual

Manitowoc GROVE GMK7450 User manual

Manitowoc

Manitowoc GROVE GMK7450 User manual

Manitowoc Grove GMK 5250L User manual

Manitowoc

Manitowoc Grove GMK 5250L User manual

Manitowoc National Crane NBT40 Series User manual

Manitowoc

Manitowoc National Crane NBT40 Series User manual

Manitowoc Grove RT9130E User manual

Manitowoc

Manitowoc Grove RT9130E User manual

Manitowoc 14000 User manual

Manitowoc

Manitowoc 14000 User manual

Manitowoc MLC300 User manual

Manitowoc

Manitowoc MLC300 User manual

Manitowoc GROVE GMK 6400 User manual

Manitowoc

Manitowoc GROVE GMK 6400 User manual

Manitowoc NTC55 User manual

Manitowoc

Manitowoc NTC55 User manual

Manitowoc Grove TMS500-2 User manual

Manitowoc

Manitowoc Grove TMS500-2 User manual

Manitowoc GROVE RT650E User manual

Manitowoc

Manitowoc GROVE RT650E User manual

Manitowoc Grove GMK 4100L-1 User manual

Manitowoc

Manitowoc Grove GMK 4100L-1 User manual

Manitowoc GHC 75 Technical specifications

Manitowoc

Manitowoc GHC 75 Technical specifications

Manitowoc Grove TMS9000-2 Series User manual

Manitowoc

Manitowoc Grove TMS9000-2 Series User manual

Manitowoc MLC300 User manual

Manitowoc

Manitowoc MLC300 User manual

Manitowoc National Crane NBT30H-2 User manual

Manitowoc

Manitowoc National Crane NBT30H-2 User manual

Manitowoc National Crane 600H User manual

Manitowoc

Manitowoc National Crane 600H User manual

Manitowoc 14000 2 Series User manual

Manitowoc

Manitowoc 14000 2 Series User manual

Manitowoc MLC165 User manual

Manitowoc

Manitowoc MLC165 User manual

Manitowoc MLC300 User manual

Manitowoc

Manitowoc MLC300 User manual

Manitowoc 14000 User manual

Manitowoc

Manitowoc 14000 User manual

Manitowoc GROVE GMK3060 User manual

Manitowoc

Manitowoc GROVE GMK3060 User manual

Manitowoc National Crane NBT30H-2 User manual

Manitowoc

Manitowoc National Crane NBT30H-2 User manual

Manitowoc 2250 User manual

Manitowoc

Manitowoc 2250 User manual

Popular Construction Equipment manuals by other brands

Sonic Equipment 4822331 instruction manual

Sonic Equipment

Sonic Equipment 4822331 instruction manual

Sealey PH20.V4 instructions

Sealey

Sealey PH20.V4 instructions

Volvo DD24 Operator's manual

Volvo

Volvo DD24 Operator's manual

TYROLIT Hydrostress WCE30 operating instructions

TYROLIT Hydrostress

TYROLIT Hydrostress WCE30 operating instructions

Masalta MSR58 SERIES instruction manual

Masalta

Masalta MSR58 SERIES instruction manual

Festool CT-VA Original operating instructions

Festool

Festool CT-VA Original operating instructions

SET MAKINA TIGERFILL Maintenance and Instruction Manual

SET MAKINA

SET MAKINA TIGERFILL Maintenance and Instruction Manual

Krendl 450A owner's manual

Krendl

Krendl 450A owner's manual

ShelterLogic 10075 instructions

ShelterLogic

ShelterLogic 10075 instructions

Tadano GR-300EX-3 Service manual

Tadano

Tadano GR-300EX-3 Service manual

HULTDINS SuperGrip SG installation manual

HULTDINS

HULTDINS SuperGrip SG installation manual

Atlas Copco Dynapac F2500W manual

Atlas Copco

Atlas Copco Dynapac F2500W manual

Renova moviroll MRE 100 L operating instructions

Renova

Renova moviroll MRE 100 L operating instructions

ASE SM 5 Operation manual

ASE

ASE SM 5 Operation manual

Schletter FIXGRID PRO-100 Assembly instructions

Schletter

Schletter FIXGRID PRO-100 Assembly instructions

Hercules HA31 owner's manual

Hercules

Hercules HA31 owner's manual

hymer 6371 Instructions for use

hymer

hymer 6371 Instructions for use

MBW ScreeDemon Operator's safety and service manual

MBW

MBW ScreeDemon Operator's safety and service manual

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.