User Instructions
Modulift UK Ltd tel: 011 44 1202 621511 email: [email protected] www.modulift.com
The CMOD Spreader Frame is modular in span and every frame consists of 4 Corner Units,
with intermediate Struts that can be bolted into the assembly to achieve dierent spans.
 Personnel using this system should be suitably trained, competent and have a clear
understanding of Safe Slinging procedures.
 The use of Modulift equipment must be in accordance with the procedures laid down in‘ASME B30.20 - 2013’.
 Never exceed stated SWL – Adhere to SWL in Table 2 for particular sling angle used.
 The top sling length is critical to the safe use of the spreader – Ensure you refer to the correct table.
WARNING!
Assembled
Frame
α
Table 1 – Component List
CMOD 24 Spreader Frame
CMOD 24 Frame Specication
 Rated at a maximum of 30 tonnes SWL.
Please see Table 2 for SWL at specic spans.
 ‘Base to Sling’ angle, α, no less than 45 degrees.
 Corner Units are rated at 7.5 tonnes each
(30 tonnes combined capacity).
 Bolt tightening torque: 110 Pound-Foot. Spanner size required: 30mm.
 Recommended additional equipment: Torque Wrench, Podger Spanner and Ring Spanner.
CMOD 24 has an assembled span ranging from 4ft by 4ft to 20ft by 20ft in 1ft increments.
P7P2–P5
Span
P6
P1 P8
Strut Corner Unit
Part Ref. Description Weight/item
P1 Corner Unit(length 2ft each) 130 lbs
P2 6ft Strut 80 lbs
P3 4ft Strut 56 lbs
P4 2ft Strut 37 lbs
P5 1ft Strut 26 lbs
P6 17t Shackle 18 lbs
P7 12t Shackle 11 lbs
P8 M20 x 50, Grade 8.8, HT Bolts, Nuts & Washers
α= Base to sling angle (BSA)
Fig. 1 – Typical CMOD Spreader Frame Assembly
User Instructions
Should you nd your equipment is no longer of use,
please dispose of in a responsible manner. Please
contact Modulift if you need further guidance
Table 2 – Load v Span
© Copyright 2016 Modulift.
All rights reserved.
Modulift UK Ltd tel: 011 44 1202 621511 email: [email protected] www.modulift.com
User Instructions
WARNING!
Assembly Procedure
 Check the ID plates on each Modulift component to ensure the
correct size is used.
 Lay out the Struts and Corner Units in the correct conguration.
 Check all anges are clear from debris, sand etc. before connection.
 Bolt the components together* using bolts, nuts & washers
provided. Tighten the bolts to torque as shown overleaf.
 Loop the top Shackles through the bows of the Corner Units so
they contact‘bow-to-bow’. The eye of the top slings can then be
passed through the jaws of the Shackles and the pins replaced.
 Loop the bottom Shackles through the eyes of the drop slings and
connect to the bottom of the Corner Unit with the Shackle pin.
 Attach the lower slings to the load to be lifted.
 The assembled Spreader Frame and lifting rig must be
thoroughly checked by a competent person prior to lifting.
*The use of a Podger Spanner will aid in assembly by helping to align the bolt
holes by forcing it through.
Do’s & Don’ts
 Do ensure that the frame is only loaded at the Corner Units
and they are all equally loaded.
 Do ensure enough clearance between frame and the load to
prevent the load hitting the frame. Any collision could cause
failure of the frame.
 Do not undertake a lift without the correct use of
appropriate top slings.
 Do not hang any loads from the Strut tube or anges.
 Do not exceed the stated SWL for your span.
 Do not rig the lower slings more than 6° from vertical.
 Do not under any circumstances hang load(s) from the tube
or anges – the Spreader Frame is designed for compression
– not bending.
 Ensure that the top Shackle contacts the bow of the corner
plate ‘bow-to-bow’.
 The components in the frame will be marked as ASME‘Category
B’, however the frame is modular and some arrangements may
be‘Category A’due to this please contact Modulift prior to any
‘Category B’application (e.g. Oshore).
 Max number of Struts allowed in assembly: 5 per side
 Assemble longer Struts in the centre of the conguration
 Sling angle is crucial to safe use of frame.
 The top sling must be positioned centrally in the Shackle
pin to ensure even loading. Contact your Modulift supplier
for supply of loose spacers where required.
First pick the span required for your frame (e.g. 10ft
x 16ft) and the Sling Angle (we recommend 60°
BSA where possible), then check the SWL via the
appropriate table. Read the table by locating the
lower span on the y axis of the chart and the larger
on the x. The cell which you are referred to, will
indicate the SWL for your chosen span. If your exact
span is not noted in the table, then please round up
or down to the values that will give you the lowest
SWL (to ensure no overloads are applied). Please
contact Modulift for conrmation on your SWL if
required. SWL given in Metric Tons (Tonnes).
CMOD 24 US MAY 2016
CMOD 24 Spreader Frame
20 23
18 24 21
16 30 24 20
14 30 30 24 19
12 30 30 24 23 18
10 30 30 30 24 22 17
830 30 30 30 24 20 17
630 30 30 30 28 24 19 16
430 30 30 30 30 27 23 19 16
Span
(ft) 4 6 8 10 12 14 16 18 20
CMOD 24: SWL / tonnes @ 60° BSA
20 13
18 14 12
16 17 14 11
14 17 17 14 11
12 17 17 14 13 10
10 17 17 17 14 12 9
817 17 17 17 14 11 9
617 17 17 17 16 14 11 9
417 17 17 17 17 15 13 11 9
Span
(ft) 4 6 8 10 12 14 16 18 20
CMOD 24: SWL / tonnes @ 45° BSA

Other Modulift Construction Equipment manuals

Modulift CMOD 70 User manual

Modulift

Modulift CMOD 70 User manual

Modulift CMOD 12 User manual

Modulift

Modulift CMOD 12 User manual

Popular Construction Equipment manuals by other brands

Malta Dynamics X Series instruction manual

Malta Dynamics

Malta Dynamics X Series instruction manual

Winget 2 Series Operators Handbook & Parts

Winget

Winget 2 Series Operators Handbook & Parts

ELEC-MECH SAFE-AID TS7000 Operator's manual

ELEC-MECH

ELEC-MECH SAFE-AID TS7000 Operator's manual

Fayat Group BOMAG BM 500/15 Service manual

Fayat Group

Fayat Group BOMAG BM 500/15 Service manual

Trejon MULTIFOREST V Series Instruction Manual and Maintenance Directions

Trejon

Trejon MULTIFOREST V Series Instruction Manual and Maintenance Directions

Neuson 3001 Operator's manual

Neuson

Neuson 3001 Operator's manual

Dynapac CA270 instruction manual

Dynapac

Dynapac CA270 instruction manual

Sima SPIRAL-26 Original user guide

Sima

Sima SPIRAL-26 Original user guide

SPIERINGS SK597-AT4 manual

SPIERINGS

SPIERINGS SK597-AT4 manual

Wassermann WGS-25 T Service manual

Wassermann

Wassermann WGS-25 T Service manual

ABS ABS-Lock X-PMT-4 quick start guide

ABS

ABS ABS-Lock X-PMT-4 quick start guide

Manitowoc Grove GMK 5200-1 Maintenance manual

Manitowoc

Manitowoc Grove GMK 5200-1 Maintenance manual

Fayat DYNAPAC DRP15D Operating	 instruction

Fayat

Fayat DYNAPAC DRP15D Operating instruction

Atlas Copco CA3600 instruction manual

Atlas Copco

Atlas Copco CA3600 instruction manual

MULTIQUIP MC94SH Operation and parts manual

MULTIQUIP

MULTIQUIP MC94SH Operation and parts manual

Hailo 1-2-3 500 Assembly instructions

Hailo

Hailo 1-2-3 500 Assembly instructions

Toro MMXD-958H-S Operator's manual

Toro

Toro MMXD-958H-S Operator's manual

TYROLIT Hydrostress FGE515 operating instructions

TYROLIT Hydrostress

TYROLIT Hydrostress FGE515 operating instructions

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.