ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
4407MartinsburgPike Phone:5406623811
ClearBrook,VA22624 Fax:5406658101
USA email:[email protected]
web:www.reimersinc.com
_______
MODEL:
________
SERIAL#:
ARSteamBoilerModels
InstructionsManual
PAGE2
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
LimitedWarrantyInformation........................................4
ImportantSafetyInformation.........................................5
Installation.....................................................................7
Location.........................................................................7
WaterSupply.................................................................8
SteamOutlet.................................................................8
SafetyReliefValve........................................................8
Electrical........................................................................8
BlowdownValve............................................................9
Operation......................................................................10
BoilerStartup................................................................10
ControlFunctions..........................................................10
PressureAdjustment.....................................................10
BoilerMaintenance.......................................................11
BoilerBlowoff................................................................11
SafetyValveTest...........................................................11
ElementReplacementandElementCleaning..............11
WaterLevelProbeandProbeBaffleBoxCleaning......11
GaugeGlassReplacement...........................................12
Troubleshooting............................................................13
PartsLists.....................................................................14
PartsList(Continued)...................................................15
TABLEOFCONTENTS
PAGE3
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
AR4‐8STEAMBOILERS
4407MartinsburgPike Phone:5406623811
ClearBrook,VA22624 Fax:5406658101
USA  email:[email protected]
web:www.reimersinc.com
• Miniatureboilermax.vesselvolume0.29
3
• Maximumsafetyvalveseng100psi
• Allboilersaremanufacturedinaccordancewiththerequirementsofthe
A.S.M.E.BoilerandPressureVesselCodeandA.S.M.E.CSD‐1.Eachboiler
bearstheNaonalBoardStamp“M”.
• Highqualitysaturatedsteam,operangpressurerange0–85psig
• Heavydutycarbonsteelpressurevessel.Vesseljacketandelectrical
enclosure304stainlesssteel
• Largeseleconofoponalequipment
Features
StandardEquipmentofEachBoilerIncludes:
• A.S.M.E.pressurereliefvalve
• One(1)quickopeningboomblowoffvalveasperA.S.M.E.CodeB31.1
• Bronzesteamoutletballvalve
• HighpressurefeedpumponARH‐models
• Lowwatercutoffcontrolwithmanualreset
• One(1)highpressurecutoffcontrolwithmanualreset
• One(1)operangpressurecontrol
• Magneccontactor
• IndicatorlightsforPOWER,REFILLING,HEATINGandALARMS
Applications
•ProcessSteam
•DryCleaning •FoodService(*)
•Laboratories
(*)DIRECTSTEAMAPPLICATIONSTOFOODPRODUCTS:Reimersoffersstainlesssteelboilersor#OPT1030Brass/Bronzefreeboilertrimopon(seePage5).This
alonedoesnotguaranteetheproduconofculinarygradesteam.Applicablesafetystandards(i.e.3‐AT609)mustbeconsidered.
ModelNumberKey
FeedWaterOptions:
Blank=SolenoidValve
H=SolenoidValve+Pump
BoilerPowerinkW
3=3kW
4=4kW
8=8kW SafetyRelief
ValveSetting:
A=15psi(1.03bar)
F=100psi(6.9bars)
Blank=120VACpowersupplyrequired
atboilerinstallationsitefor
hookupasboilercontrolvoltage
X= Boilerisequippedwith
transformertoprovide120VAC
asboilercontrolvoltage.(Applies
to380&415Vvoltagesonly)
Example:ARH8E1F=AR‐Seriesboilerwithfeedwater
solenoidandpump,8kWheangpower,heangpower
supply240V,1ph,controlvoltagepowersupply120V1ph,
safetyvalvesetto100psi.
(1) Each boiler model requires two (2)
powersupplies:Primaryheangpower
andsecondarycontrolvoltage.Nominal
controlvoltageis120V,50/60Hz.Boiler
modelswiththe–Xopon(thisapplies
to foreign voltages only, see Model
Number Key below) require only the
heang power supply of 240V 1PH,
50/60Hz.
(2)TheSTEAMCAPACITYlistedaboveis
basedontheevaporaonratefromand
at 212°F, at 0 psig. If the boiler feed
water temperature is 50°F, then the
STEAMCAPACITYforeachmodellisted
aboveisapproximately15%lower.
Pleasenotethatallinformationprovidedwithinthisbrochureisapproximateandsubjecttochangewithoutnotice.
PleasecontactReimersElectraSteam,Inc.withanyquestionsregardingthespecificationsordimensionsdetailedwithin.
•AirHumidificaon
A R 1
Voltage:
A=120V
E=240V
PAGE4
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
LIMITEDWARRANTY–STEAMGENERATORS
Reimers Electra Steam, Inc. warrants the following products of its own manufacture against defects in
materialsandworkmanshipundernormaluseandservice.Thiswarrantyisinlieuandexcludesallother
expressedorimpliedwarrantiesormerchantabilityoffitnessforanyparticularuse.Nopersonisauthorizedto
extendthetermsofthiswarrantyorassumeanyotherliabilityexceptbywrittenstatementsignedbyanofficer
ofReimersElectraSteam,Inc.ClearBrook,Virginia22624.
WARRANTYPERIOD
The pressure vessel and electrical & mechanical components are warranted for one year from date of
shipmentfromReimersElectraSteam,Inc.inClearBrook,VA22624.
LIMITATIONS
Productsmustbeinstalled,usedandmaintainedinaccordancewithourinstructions,includingreasonable&
necessary maintenance by the user.  Users are responsible for the suitability of the products to their
application.Thereisnowarrantyfordamageresultingfromimproperinstallation,abuse,powerfailure,fire,
flood,lightening,improperwater,misuse,improperspecification,misapplicationorotheroperatingconditions
beyondourcontrolorpartsthatarenormallyexpendableinusualcourseofoperation.
Claimsagainstcarriersfordamageintransitmustbefiledbythebuyer.Reimersliability,ifany,willnot
exceedthepriceofReimersproductsclaimedtobedefective.
ComponentsmanufacturedbyanysupplierotherthanReimersshallbearonlythatwarrantymadebythe
manufacturerofthatproductandserviceforthatwarrantyshallbetheresponsibilityofthatmanufacturerand
notReimers.
REMEDY
ClaimsunderthisLimitedWarrantymustbemadebyobtainingaReturnAuthorizationNumberfromouroffice
(PHONE: 5406623811, FAX: 5406658101) & returning the defective part, freight prepaid to: Reimers
ElectraSteam,Inc.,4407MartinsburgPike,ClearBrook,Virginia22624
Defectiveitemswillberepairedorreplacedasnecessarywithinareasonabletimewithoutcharge,otherthan
incidentalchargessuchasfreightprepayment.Suchrepairorreplacementwithinareasonabletimeisthe
exclusiveremedyavailablefromReimersElectraSteam,Inc.,underthisLimitedWarranty.
CONSEQUENTIALDAMAGES
ReimersElectraSteam,Inc.,isnotliableforlaborcostsincurredintheremoval,reinstallation,orunauthorized
repairofproduct,orfordamagesofanytypewhatsoever,includingincidentaland/orconsequentialdamages.
THISWARRANTYSUPERSEDESALLPREVIOUSWARRANTIES.
PAGE5
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
YouhavejustpurchasedaqualitysteamboilerdesignedtotheASMEBoilerCodeandregisteredwiththeNationalBoard
ofBoilerInspectors.Treatthisindustrialequipmentwithcareandrespect.Itissafewheninstalled,maintained,andused
properly.Readtheinstructioncarefullyandcontactthefactoryifyouhaveanyquestions.
Readthismanualbeforeinstallingandusingthisproduct.
Failuretodosocanresultinseriousinjuryordeath.
YourboilershouldbemarkedwithacompletesetofWARNING/CAUTIONlabelsshownbelow.Ifoneoftheselabelsis
missing,pleasecontactourfactoryimmediately.
USandAllOtherNonFrancophoneCountriesCanadaandAllOtherFrancophoneCountries
Locatedonelectricalenclosuredoor
Locatedonendcapsofcylindricalboilerpressurevesseljacket
Locatedonendcapsofcylindricalboilerpressurevesseljacket
Thismanualcontainssafetymessages.Eachofthesafetymessagesareprecededbyoneofthefollowingsignalword
panels:
Safetymessagesprecededbythislabelcontaininformation,thatifnotfollowedwillresultindeathorseriousinjury.
Safetymessagesprecededbythislabelcontaininformation,thatifnotfollowedcouldresultindeathor
seriousinjury.
Safetymessagesprecededbythislabelcontaininformation,thatifnotfollowedcouldresultinminoror
moderateinjury.
Messagesprecededbythislabelcontainimportantinformation,butarenothazardrelated.
Ensurethatthismanualisavailabletotheboileroperatoratanytime.
Readcarefullyallsafetylabelsattachedtotheboiler.Ifanysafetylabelwasdamagedduringshipment,contactthe
factoryimmediately:
Ph.5406623811;email:sales@reimersinc.com
Readthismanualbeforeinstallingandusingthisproduct.
Failuretodosocanresultinseriousinjuryordeath.
NOTICE
CAUTION
WARNING
DANGER
WARNING
PAGE6
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
ImportantSafetyInformation
1.BLOWDOWNVALVE:Thisvalveisutilizedtoblowimpuritiesfromtheboilerchamber.Whenopened,alargevolume
ofhotwaterandsteamisdischarged.Ensurethatthisvalveisproperlypipedforsuchdischarge.Stateandlocalcodes
mustbemetasapplicable.
2.ELECTRICAL:AllfieldwiringtotheboilermustbeinaccordancewiththeNationalElectricCodeandanylocalcodes
thatmayapply.Wiringmustbemadebyacompetentcertifiedelectrician.Usecopperwireonly.
Ensure that all electrical components are in a dry location, free from any possibility of water soaking. Electric foot
switcheswhensuppliedmustnotbeplacedonawetfloor.Theymustbeplacedondrysurface,notsubjecttosteamor
water.
3.GAUGEGLASS:Thegaugeglassprotectorguardsmustbeonatalltimes.Whenreplacingtheglass,besurethatthe
unitisnotunderpressureandiscooltotouch.Thegaugeglassshouldbereplacedonceperyear.Ifcracksorwearis
evident,replacethegaugeglassimmediately.
4.MODIFICATION/MISUSE:ThisboilerhasbeendesignedandconstructedinaccordancewiththeASMEBoilerand
PressureVesselCode.Anymodificationormisusecanresultinadangeroussituation.ReimersElectraSteam,Inc.is
notliableforanyproductthathasbeenmodifiedorimproperlyused.
5.PRESSUREGAUGE:Thepressuregaugeindicatestheinternalpressureoftheboiler.Itcanfail.Periodicallyhave
yourboilerinspectorcomparethegaugewithaknowngaugeutilizingthetestvalvearrangementprovided
6. REGISTRATION: Most states and cities require boiler registration and inspection. Check with your government
authorities.
7.INSTALLATIONANDREPAIR:
Installationandrepairworkofthisunitmustbeperformedonlybyexperiencedpersonnel.Beforecommencingarepair,
ensurethattheboileriscold,notpressurizedandelectricallydisconnected.Allstandardelectricalandsteamsafety
precautionsmustbetakenduringtesting.
8.SAFETYVALVE:Thesafetyvalveisdesignedtodischargehotsteamwhenthesetpressureisexceeded.Ensure
thatthedischargeportispointingtowardthebackoftheunitawayfromtheoperatororanyaisles.Testthesafetyvalve
periodicallytoensurethatitisoperatingproperly.Testcarefullyatfullpressurebyliftingleverusingpliersandletit
“slapping”shut.Steamdischargecanscald.Ensurenooneisexposed.
9.STEAMINSTALLATION:
Steampipingmustbeofblackpipe,notgalvanized.Workmustbedonebyanexperiencedsteamfitter.Allstateand
localcodesmustbemetasapplicable.
10.WATER:Ensurethatallelectricalcomponentsareinadrylocation,freefromanypossibilityofwatersoaking.
Electricfootswitcheswhensuppliedmustnotbeplacedonawetfloor.Theymustbeplacedondrysurfacenotsubject
tosteamorwater.
WARNING
PAGE7
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
1.Installation
REIMERSELECTRASTEAM,INC.boilersareheatedbyoneormoreimmersiontypeheatingelements.Automatic
controlsareprovidedtomaintainpresetoperatingpressureandproperwatersupply.Safetyfeaturesincludeautomaticlow
watercutoff,automaticpressurecontrol,safetyvalveandvisiblewaterlevelgauge.Eachboilerismanufacturedinaccordance
withtheASME PowerBoiler CodeStandards andis individuallyinspectedand stampedby anauthorized NationalBoard
InsuranceInspector.AllboilersareregisteredwiththeNationalBoardofBoilerandPressureVesselInspectors.Whenboileris
received,makesureithasnotbeendamagedinshipment.
NOTE:
ASMEDATAPLATEISLOCATEDONENDOFPRESSUREVESSELBEHINDLABELSTAMPEDWITHNATIONALBOARD
NUMBEROFUNIT.
Whenboilerisreceived,makesureithasnotbeendamagedinshipment.
Placetheboilerinalevelposition,closetotheequipmentwhichitistosupply.Thiswillinsureminimumheatlossesandallow
moreeconomicalpipingarrangements.Allsteamlinesshouldbeinsulated.Reviewtheoveralldimensionsofyourboilermodel
onpage7toselectproperboilerlocation.
RegardlessoftheNFPA70workingspacerequirementsshownbelow,provideaminimumof3ftclearanceonbothsidesofthe
boilerforelementservicing,3ftofclearancetothefrontoftheboilerand1.5fttotherearoftheboiler.
a.)Workingspace:
ElectricboilerspacingisdictatedbyNFPA70,Table110.26asfollows:
Note:Wheretheconditionsareasfollows:
Condition1—Exposedlivepartsononesideoftheworkingspaceandnoliveorgroundedpartsontheothersideoftheworkingspace,orexposed
livepartsonbothsidesoftheworkingspacethatareeffectivelyguardedbyinsulatingmaterials.
Condition2—Exposedlivepartsononesideoftheworkingspaceandgroundedpartsontheothersideoftheworkingspace.Concrete,brick,ortile
wallsshallbeconsideredasgrounded.
Condition3—Exposedlivepartsonbothsidesoftheworkingspace.
(a)DeadFrontAssemblies.Workingspaceshallnotberequiredinthebackorsidesofassemblies,suchasdeadfrontswitchboardsormotorcontrol
centers,whereallconnectionsandallrenewableoradjustableparts,suchasfusesorswitches,areaccessiblefrom
locationsotherthanthebackorsides.Whererearaccessisrequiredtoworkonnonelectricalpartsonthebackofenclosedequipment,aminimum
horizontalworkingspaceof762mm(30in.)shallbeprovided.
b.)AlcoveorclosetinstallationperUL834:Properlocationofthisboilermodelwithregardtocombustibleandnoncombustiblesurfacesandmaterialsis
codedontheboilernameplate.Thefollowingdecodingsketchanddescriptionisprovidedfortheuserinformation:
Descriptionofdimensionsandsymbols
A–Clearanceabovetopofboiler
B–Clearancefromfrontofboiler
PrefixCtonumeralindicatessuitabilityforclosetoralcoveinstallation
PrefixAindicatessuitabilityforalcovebutnotforclosetinstallation
D–Clearancefrombackofboiler
EL–Clearancefromleftsideofboiler
ER–Clearancefromrightsideofboiler
F–Indicatestypeofflooring:"NC"fornoncombustiblefloor/"C"forcombustiblefloor.Numeralindicatesminimumclearancebelowsuspendedunitsto
combustiblefloor
1.1Location
PAGE8
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
Onmodelswithpumpand/orsolenoidvalve,connect
incomingwatersupplytointakesideofsolenoidvalve.
AR&ARHsteamboilermodelsrequirefour(4)gallonsof
feedwaterperhourforeach10kWofelectricheating
capacityoftheboiler.Linesshouldbeofadequatesizeand
meetlocalplumbingcodes.
Inordertoensurelongtermtroublefreeboileroperation,
werecommendthatthewaterusedasboilerfeedwaterto
betestedforhardness.Ifthewaterinyourareaisharder
than1grain(17mg/L),useawatersoftener.Themain
causeforprematureheatingelementfailureinelectric
steamboilersiswaterhardness.Ifseverecorrosionduring
inspectionofthepressurevesselasindicatedinchapter
3.4ofthismanualbecomesevident,additionaltestsof
yourboilerfeedwatermustbeperformed.Awateranalysis
shouldbeperformedbyaqualifiedandrecognizedwater
treatmentcompanylocatedinyourarea.
Recommendedlevelsforboilerfeedwater:
Recommendedlevelsforboilerwater(waterinside
pressurevesselwhenboilerisoperating)
Allpipingfromandtotheboilermustcomplywiththe
A.S.M.E.B31.1PowerPipingCode.AllStateandlocal
codesmustbemet.Allpipingmustbedonebyaqualified
steamfitter.
Connectsteamlineofsufficientsizefromsteamlinevalve
totheequipment.Steampipingmustbeblacksteelpipe,
notgalvanized.Workmustbedonebyanexperienced
steamfitter.Allstateandlocalcodesmustbemet.
Thesafetyvalveisdesignedtodischargehotsteamwhen
thesetpressureisexceeded.Ensurethatthedischarge
portispointingtowardthebackoftheunitawayfromthe
operatorandanyaisles.Ifitisrequiredthatdischarge
pipingbeinstalledfromthesafetyvalve,thepipeshould
notbesmallerthanthevalveoutletandshouldberigidly
supportedsoasnottoplaceweightonthevalveitself.
Important:Novalveinthisline!
NOTICE Donotaddanychemicalsto
theboilerfeedwaterunless
specificallyrecommendedbya
qualifiedandrecognizedwater
treatmentcompany.
BoilerFeed
WaterSupply
SafetyRelief
Valve
1.2WaterSupply 1.3SteamOutlet
1.5SafetyReliefValve
SteamOutlet
FIGURE03
FIGURE05
FIGURE04
PAGE9
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
Tohookuppowerandcontrolvoltagetotheboiler,please
proceedasfollows.Toensureproperconnection,please
referalsototheattachedwiringdiagramandlabelsnextto
thefieldwiringterminalsforproperconductorsizeand
maximumtorquesthatcanbeappliedtotheterminal
contacts.Allwiringmustbeinstalledinaccordancewiththe
NationalElectricCodeandanylocalcodesthatmayapply.
Wiringmustbedonebyacompetent,certifiedelectrician.
Forthisservice,theN.E.C.requiressupplywiresratedat
125%offullload.Useonlycopperwire.Installafused
disconnectswitchwithinsightoftheboiler.Connectpower
supplytotheterminalsincontrolpanel.
1.6.2240VBoilerModelswithVoltageTransformer
ConnectpowersupplyasindicatedinFIGURE07.Use
AWG#8copperwire,ratedfor75°Cminimum.
1.6.3BoilerModelswithoutPreInstalledPowerCord
andControlVoltageTransformer
ConnectpowersupplyasindicatedinFIGURE08.Use
AWG#8copperwire,ratedfor75°Cminimum.
EnsurethatthevoltagebetweentheconductorsL1andL2
toNEUTRALis120VAC
Ifno240Vpowersourceisavailablethatmeasures120V
ACfromtheconductorsL1andL2toNEUTRAL,then
hookuptwoseparatepowersupplies,seeFIGURE09:
Powerhookup,AWG#8copperconductors,rated
75°Cminimum
Controlvoltagehookup,AWG#14copper
conductors,rated75°Cminimum
1.6.4120VBoilerModelswithoutPreInstalledPower
CordandControlVoltageTransformer
Connectpowersupplyasindicated.UseAWG#10copper
wireratedfor75°Cminimum
Whentheblowdownvalveisutilized,a
largevolumeofhotwaterandsteamis
discharged.Ensurethatthisvalveis
properlypipedforthisdischarge.Stateandlocalcodes
mustbemetasapplicable.
1.6Electrical
1.7BlowdownValve
CAUTION
GND
L2
L1
GND
L2
L1
NEUTRAL
INSTALL#14
AWGCONTROL
VOLTAGEWIRE
JUMPER
GND
L2
L1
NEUTRAL
FIGURE07
FIGURE08
FIGURE09
GND
L
Power
Control
Voltage
GND
L1
NEUTRAL
FIGURE10
Power
BLOWDOWN
VALVE
PAGE10
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
a.Opensteamlinevalveslightly.Thiswillallowtheboiler
tobefilledwithoutproducingbackpressure.
b.Openupperandlowergaugeglassfixturevalve
c.EnsurethatthefeedwatershutoffvalveisintheOPEN
position
d.Closetheboilerblowdownvalve
e.Throwthefuseddisconnectswitch(notprovidedby
factory)totheONpositionandturnontheboilercontrol
voltage
f.Afterapproximately2seconds,theWATERFEEDlight
turnsonandwaterenterstheboiler.Assoonasthewater
levelreachesapproximatelyhalfheightinthegaugeglass,
theautomaticwaterfeedturnsoff.
g.Iftheboilercontrollerindicatesanyalarms,thenpress
thecorrespondingRESETbutton(s).
Assoonasnoboileralarmsareindicated,theHEATING
lightturnsonandtheboilerstartstobuilduppressure.
Observethepressuregaugewhilepressurebuildsup,until
workingpressureisreached.Theworkingpressureshould
havebeenfactorysettoyourspecification.However,ifyou
wishtochangetheworkingpressuresetting,proceedas
follows.
Allpressurecontrolsarefactorypresetandrequireno
adjustment.However,ifachangeoftheoperatingsteam
pressureisrequired,thenproceedas
follows:
• Disconnectallpowersuppliesfromtheboiler.
• Closethesteamoutletvalve
• Removethelowerfrontcover.
• Turntheblackknoboftheoperatingpressureswitch
clockwisetoincreasethepressureandcounterclockwise
todecreasethepressure.
• Connectallpowersuppliestotheboiler,openthesteam
outletvalve,andinstallthelowerfrontcover.
h.Toshutofftheboiler,turnthePOWERswitchonthe
boilercontrollerOFF.
Standclearofscaldingwaterorsteam.
Disconnect the boiler from all power
supplies.
2.Operation
2.1BoilerStartup
GAUGE
GLASS
VALVES
BLOWDOWN
VALVE FEEDWATER
SHUTOFFVALVE
TurntheBLOWDOWNENABLE
switchOFFifinstalled
TurnthePOWER
switchON
NOTICE
WARNING
HighPressure
SafetyLimit
PressureSwitch.
DONOTADJUST!
Operating
PressureSwitch
OptionalBoiler
BlowoffPressure
Switch.OPT1016
STEAMOUTLET
VALVE
Donotletthepumptorundryforan
extended time as this will cause
damagetothepump.
FIGURE11
FIGURE12
FIGURE13
FIGURE14
2.2PressureAdjustment
PAGE11
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
Boilerrepairsmustbeperformedby
experiencedpersonnelonly.Ensureboiler
wateriscoldanddrainedandthatthereisnopressureand
allelectricitytotheboilerisshutoff.
Allboilersmustbeblownoffperiodicallytoremove
minerals,scaleandotherforeignmatter,whichaccumulate
insidethepressurevessel.Theconcentrationofthis
depositdependsinpartupontheconditionofthewaterin
thearea.Whenwaterisnaturallysoft,orhasbeen
softenedchemically,boilerblowoffsarerequiredlessoften
thaninareaswherehardwaterisfound.Watersofteners
aresuggestedinhardwaterareastominimizethe
formationofhardscaleonheatingelements.Anotherfactor
affectingwaterconditionistheamountofcondensate,if
any,thatisbeingreturnedtotheboiler.Sincecondensate
isessentiallycleandistilledwater,itcontainsveryfew
impurities.Ifalargepartofthecondensateisbeing
returnedandlittlemakeupwaterisused,theboilerneed
notbeblowndownasoftenaswhenlittleornocondensate
isreturnedtotheboiler.Werecommendblowoffofnewly
installedsteamboilersonceperdayuntilthefirstheating
elementandpressurevesselinspectionisperformed(refer
tochapter3.4).Ifnosignificantamountofsedimentis
foundonthebottomofthepressurevesselandonthe
heatingelementsheaths,thentheboilerblowofffrequency
canbereducedaccordingly.Thesafestmethodtoblowoff
RseriessteamboilersistoinstallaReimersElectra
Steam,Inc.properlysizedandfullytrimmedblowdown
tank,modelBTANK10.Reimersblowdowntanksare
designedandconstructedtoSectionVIIIoftheA.S.M.E.
CodeandinspectedbyacommissionedNationalBoard
Boilerinspector.
3.1.1BoilerBlowoffFrequency
Inareaswherewaterissoftorhasbeensoftened
chemically:
• Whenlittlecondensateisreturnedblowdownonceevery
secondday
• Whenalargepartofthecondensateisreturnedandlittle
makeupwaterisused,blowdownonceeveryweek.
Inareaswherehardwaterexists:
• Whenlittleornocondensateisreturned,blowdown
once
• Whenalargepartofthecondensateisreturnedandlittle
makeupwaterisused,blowdownonceeverysecond
day
Standclearofscaldingwaterorsteam.
EnsurethattheBoilerBottomBlowoff
Valveisproperlypiped.
Thistestshouldbeperformedoncepermonth.Proceedas
follows:
• Increasethesteampressureas
showninchapter2.2to
maximumoperatingpressure.
• Keepthesteamoutletvalve
closed
• Pullthetripleverandholdopen
forfive(5)secondsinorderto
flushoffthevalveseat.
• Permitthevalveto“slap”shut.If
aleakoccurs,repeatthistest
andifnecessary,replacethe
valve.
Ensurethattheboileriscold,drained
andallpowersuppliesare
disconnected
Cleantheelementrodseverysix(6)months.Tocleanthe
elementrods,orifanelementmustbereplaced,proceed
asfollows:
• Removethelowerfrontcover
• Removetheelementterminalcoverfromthefrontofthe
boiler.
• Disconnectandlabeltheterminalwires
• Removeallfour(4)nutsfromeachelementflangeand
pullouttheheatingelement
• Useastiffwirebrushtoremoveallscaleandforeign
matterfromtheelementrods.
• Cleantheelementflangesurfacesbeforeinstallingnew
elementsandgaskets
Ensurethattheboileriscold,
drainedandallpowersuppliesare
disconnected.
Inordertoprovidereliableautomaticwaterlevelcontrol,
thewaterlevelprobesarelocatedinsideafunnelshaped
probebaffle,weldedtotheinnerwallofthepressure
vessel.Theprobebafflehasdirectconnectiontothetop
andbottomofthepressurevesselsothattheprobescan
readthewaterlevel,protectedfromfoamandbursting
steambubblesthatformonthesurfaceoftheboiler
water.
Theprobebafflemustbecleanedeverysix(6)monthsof
sedimentsandotherdebristhataccumulatesatthebottom
ofthebaffle.Toaccomplishthis,proceedasfollows:
Step1:
Removethewater
levelprobecover,
disconnectfromeach
probethewireand
labelit.
RemovefirsttheShort
Probeandinspectthe
proberod.Ifsediment
hasaccumulated,use
astiffwirebrushto
removeit.Installthe
probeinitsplacein
theshell.
Repeattheabove
cleaningprocedurefor
theotherprobe(if
applicable).
Don’tinstalltheprobe(s)yet.
Step2:
Removethepipeplugfromtheboilerblowofflineas
showninFIGURE17.
Step3:
Inserttwo(2)1/4inODcoppertubesoranyothersoftrods
throughtheprobeopeningandthroughtheboilerblowoff
openingintothepressurevesseltoremovesedimentsfrom
3.BoilerMaintenance
3.1BoilerBlowoff
3.2SafetyValveTest
3.3ElementReplacementandElementCleaning
WARNING
ElementRods
WARNING
3.4WaterLevelProbeandProbeBaffleBoxCleaning
Long
Probe Short
Probe
(IfInstalled)
WARNING
WARNING
FIGURE15
FIGURE16
FIGURE17
PAGE12
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
thebottomofthe
probebaffle.
Step4:
Putaflashlightabove
theprobeopeningand
observewhetherlight
isvisiblethroughthe
boilerblowoffopening.
Ifnolightisvisible,
thenrepeatinserting
thecoppertube
throughtheLong
Probeopeningand
pushingtowardsthe
bottomtoremove
furthersedimentfrom
theprobebaffle.
Ifthereisasignificantamountofsedimentvisibleatthe
bottomofthepressurevessel,thentheheatingelements
mustberemovedasshowninchapter3.3andthe
sedimentsscoopedoutthroughtheelementopenings.
Step5:
Installtheprobe(s)intotheshellandconnectallprobe
wires.
Frequency:Minimumonceperyear.
Ensurethattheboileriscold,
drainedandallpowersuppliesare
disconnected.
3.5GaugeGlassReplacement
Closegauge
glassvalves
(TopandBottom)
Opendrainvalve
onbottomfixture
todrainglass
Removegauge
glassprotector&
rods
Loosennutsat
topandbottomof
glass.
Slideglassup
Rotatetopgauge
fixture,pullout
onbottomof
glassand
remove
Installnewglassby
performingthe
aboveprocedurein
reverseorder.
Alwaysinstallnew
rubberwashers.
Step1 Step2
Step3 Step4
Step5 Step6
Rod
Rod
WARNING
FIGURE18
PAGE13
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
4.Troubleshooting
WARNING
Ensurethattheboileriscoldandhasnopressure.
Electricaltroubleshootingmustbeperformedbyaqualifiedelectrician.
Iftroubleshootingdidnotresolveproblem,pleasecontactourservicetechniciansat:
Phone:5406623811
Email:techsup[email protected]
PAGE14
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
5.PartslistforAR,ARHModels
WARNING
UseReimersreplacementparts.Allcomponentsaredesignedandapprovedto
beusedinthisUnderwritersLaboratorieslistedandASMENationalBoard
Stampedboiler.Failuretodosomaycauseseriousinjuryordeath.
4
31
25
15
13
9
28
21
LowWaterCutOffProbe(E3):
Connectthisprobetowiremarked“3”
*IFINSTALLED*AutomaticRefillProbe(E1):
Connectthisprobetowiremarked“1”
22
19
14
8
27
29
11
20
2
5
1
4
6 6
8
30
26
18
5
2
3
2
23 24
PAGE15
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2

Other manuals for AR Series

1

This manual suits for next models

3

Other Reimers Boiler manuals

Reimers AR Series User manual

Reimers

Reimers AR Series User manual

Reimers RB Series Assembly instructions

Reimers

Reimers RB Series Assembly instructions

Reimers RHP-120 User manual

Reimers

Reimers RHP-120 User manual

Reimers JR Series User manual

Reimers

Reimers JR Series User manual

Reimers HLR120 User manual

Reimers

Reimers HLR120 User manual

Reimers RE Series User manual

Reimers

Reimers RE Series User manual

Reimers RHPHC-330 User manual

Reimers

Reimers RHPHC-330 User manual

Reimers HLR15 User manual

Reimers

Reimers HLR15 User manual

Reimers RB Series User manual

Reimers

Reimers RB Series User manual

Popular Boiler manuals by other brands

Beretta CIAO AT 29 C.S.I. installer and user manual

Beretta

Beretta CIAO AT 29 C.S.I. installer and user manual

Strebel Ca 7s Installation and operating instructions

Strebel

Strebel Ca 7s Installation and operating instructions

Weil-McLain PFG 7 Series Installation & operation

Weil-McLain

Weil-McLain PFG 7 Series Installation & operation

Hoval TopGas 80 installation instructions

Hoval

Hoval TopGas 80 installation instructions

REMEHA Gas 210 ECO Installation, user and service manual

REMEHA

REMEHA Gas 210 ECO Installation, user and service manual

Vaillant TURBOmax Pro 28 Instructions for installation and servicing

Vaillant

Vaillant TURBOmax Pro 28 Instructions for installation and servicing

Electric Heating Company Fusion Comet Installation and technical manual

Electric Heating Company

Electric Heating Company Fusion Comet Installation and technical manual

IBC EX 850 User's information manual

IBC

IBC EX 850 User's information manual

Viessmann VITORADIAL 300-T Service instructions

Viessmann

Viessmann VITORADIAL 300-T Service instructions

Thermal Solutions EVS SERIES Installation, operating and service instructions

Thermal Solutions

Thermal Solutions EVS SERIES Installation, operating and service instructions

Curtis WB5GT Service manual

Curtis

Curtis WB5GT Service manual

Cecilware ME10E-N Operator's manual

Cecilware

Cecilware ME10E-N Operator's manual

Argo AT Series Installation manual and operating instructions

Argo

Argo AT Series Installation manual and operating instructions

Viessmann VITOLADENS333-F Service instructions

Viessmann

Viessmann VITOLADENS333-F Service instructions

Slant/Fin LX-90 User's information manual

Slant/Fin

Slant/Fin LX-90 User's information manual

Potterton Performa 30 HE user guide

Potterton

Potterton Performa 30 HE user guide

Weil-McLain HE II Boiler manual

Weil-McLain

Weil-McLain HE II Boiler manual

Red Heating PERFORMA 15 EasyClean Plus installation guide

Red Heating

Red Heating PERFORMA 15 EasyClean Plus installation guide

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.