PAGE1
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
4407MartinsburgPike Phone:5406623811
ClearBrook,VA22624 Fax:5406658101
USA email:[email protected]
web:www.reimersinc.com
_______
MODEL:
________
SERIAL#:
ARSteamBoilerModels
InstructionsManual
PAGE2
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
LimitedWarrantyInformation........................................4
ImportantSafetyInformation.........................................5
Installation.....................................................................7
Location.........................................................................7
WaterSupply.................................................................8
SteamOutlet.................................................................8
SafetyReliefValve........................................................8
Electrical........................................................................8
BlowdownValve............................................................9
Operation......................................................................10
BoilerStartup................................................................10
ControlFunctions..........................................................10
PressureAdjustment.....................................................10
BoilerMaintenance.......................................................11
BoilerBlowoff................................................................11
SafetyValveTest...........................................................11
ElementReplacementandElementCleaning..............11
WaterLevelProbeandProbeBaffleBoxCleaning......11
GaugeGlassReplacement...........................................12
Troubleshooting............................................................13
PartsLists.....................................................................14
PartsList(Continued)...................................................15
TABLEOFCONTENTS
PAGE3
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
AR4‐8STEAMBOILERS
4407MartinsburgPike Phone:5406623811
ClearBrook,VA22624 Fax:5406658101
USA  email:[email protected]
web:www.reimersinc.com
• Miniatureboilermax.vesselvolume0.29
3
• Maximumsafetyvalveseng100psi
• Allboilersaremanufacturedinaccordancewiththerequirementsofthe
A.S.M.E.BoilerandPressureVesselCodeandA.S.M.E.CSD‐1.Eachboiler
bearstheNaonalBoardStamp“M”.
• Highqualitysaturatedsteam,operangpressurerange0–85psig
• Heavydutycarbonsteelpressurevessel.Vesseljacketandelectrical
enclosure304stainlesssteel
• Largeseleconofoponalequipment
Features
StandardEquipmentofEachBoilerIncludes:
• A.S.M.E.pressurereliefvalve
• One(1)quickopeningboomblowoffvalveasperA.S.M.E.CodeB31.1
• Bronzesteamoutletballvalve
• HighpressurefeedpumponARH‐models
• Lowwatercutoffcontrolwithmanualreset
• One(1)highpressurecutoffcontrolwithmanualreset
• One(1)operangpressurecontrol
• Magneccontactor
• IndicatorlightsforPOWER,REFILLING,HEATINGandALARMS
Applications
•ProcessSteam
•DryCleaning •FoodService(*)
•Laboratories
(*)DIRECTSTEAMAPPLICATIONSTOFOODPRODUCTS:Reimersoffersstainlesssteelboilersor#OPT1030Brass/Bronzefreeboilertrimopon(seePage5).This
alonedoesnotguaranteetheproduconofculinarygradesteam.Applicablesafetystandards(i.e.3‐AT609)mustbeconsidered.
ModelNumberKey
FeedWaterOptions:
Blank=SolenoidValve
H=SolenoidValve+Pump
BoilerPowerinkW
3=3kW
4=4kW
8=8kW SafetyRelief
ValveSetting:
A=15psi(1.03bar)
F=100psi(6.9bars)
Blank=120VACpowersupplyrequired
atboilerinstallationsitefor
hookupasboilercontrolvoltage
X= Boilerisequippedwith
transformertoprovide120VAC
asboilercontrolvoltage.(Applies
to380&415Vvoltagesonly)
Example:ARH8E1F=AR‐Seriesboilerwithfeedwater
solenoidandpump,8kWheangpower,heangpower
supply240V,1ph,controlvoltagepowersupply120V1ph,
safetyvalvesetto100psi.
(1) Each boiler model requires two (2)
powersupplies:Primaryheangpower
andsecondarycontrolvoltage.Nominal
controlvoltageis120V,50/60Hz.Boiler
modelswiththe–Xopon(thisapplies
to foreign voltages only, see Model
Number Key below) require only the
heang power supply of 240V 1PH,
50/60Hz.
(2)TheSTEAMCAPACITYlistedaboveis
basedontheevaporaonratefromand
at 212°F, at 0 psig. If the boiler feed
water temperature is 50°F, then the
STEAMCAPACITYforeachmodellisted
aboveisapproximately15%lower.
Pleasenotethatallinformationprovidedwithinthisbrochureisapproximateandsubjecttochangewithoutnotice.
PleasecontactReimersElectraSteam,Inc.withanyquestionsregardingthespecificationsordimensionsdetailedwithin.
•AirHumidificaon
A R 1
Voltage:
A=120V
E=240V
PAGE4
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
LIMITEDWARRANTY–STEAMGENERATORS
Reimers Electra Steam, Inc. warrants the following products of its own manufacture against defects in
materialsandworkmanshipundernormaluseandservice.Thiswarrantyisinlieuandexcludesallother
expressedorimpliedwarrantiesormerchantabilityoffitnessforanyparticularuse.Nopersonisauthorizedto
extendthetermsofthiswarrantyorassumeanyotherliabilityexceptbywrittenstatementsignedbyanofficer
ofReimersElectraSteam,Inc.ClearBrook,Virginia22624.
WARRANTYPERIOD
The pressure vessel and electrical & mechanical components are warranted for one year from date of
shipmentfromReimersElectraSteam,Inc.inClearBrook,VA22624.
LIMITATIONS
Productsmustbeinstalled,usedandmaintainedinaccordancewithourinstructions,includingreasonable&
necessary maintenance by the user.  Users are responsible for the suitability of the products to their
application.Thereisnowarrantyfordamageresultingfromimproperinstallation,abuse,powerfailure,fire,
flood,lightening,improperwater,misuse,improperspecification,misapplicationorotheroperatingconditions
beyondourcontrolorpartsthatarenormallyexpendableinusualcourseofoperation.
Claimsagainstcarriersfordamageintransitmustbefiledbythebuyer.Reimersliability,ifany,willnot
exceedthepriceofReimersproductsclaimedtobedefective.
ComponentsmanufacturedbyanysupplierotherthanReimersshallbearonlythatwarrantymadebythe
manufacturerofthatproductandserviceforthatwarrantyshallbetheresponsibilityofthatmanufacturerand
notReimers.
REMEDY
ClaimsunderthisLimitedWarrantymustbemadebyobtainingaReturnAuthorizationNumberfromouroffice
(PHONE: 5406623811, FAX: 5406658101) & returning the defective part, freight prepaid to: Reimers
ElectraSteam,Inc.,4407MartinsburgPike,ClearBrook,Virginia22624
Defectiveitemswillberepairedorreplacedasnecessarywithinareasonabletimewithoutcharge,otherthan
incidentalchargessuchasfreightprepayment.Suchrepairorreplacementwithinareasonabletimeisthe
exclusiveremedyavailablefromReimersElectraSteam,Inc.,underthisLimitedWarranty.
CONSEQUENTIALDAMAGES
ReimersElectraSteam,Inc.,isnotliableforlaborcostsincurredintheremoval,reinstallation,orunauthorized
repairofproduct,orfordamagesofanytypewhatsoever,includingincidentaland/orconsequentialdamages.
THISWARRANTYSUPERSEDESALLPREVIOUSWARRANTIES.
PAGE5
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
YouhavejustpurchasedaqualitysteamboilerdesignedtotheASMEBoilerCodeandregisteredwiththeNationalBoard
ofBoilerInspectors.Treatthisindustrialequipmentwithcareandrespect.Itissafewheninstalled,maintained,andused
properly.Readtheinstructioncarefullyandcontactthefactoryifyouhaveanyquestions.
Readthismanualbeforeinstallingandusingthisproduct.
Failuretodosocanresultinseriousinjuryordeath.
YourboilershouldbemarkedwithacompletesetofWARNING/CAUTIONlabelsshownbelow.Ifoneoftheselabelsis
missing,pleasecontactourfactoryimmediately.
USandAllOtherNonFrancophoneCountriesCanadaandAllOtherFrancophoneCountries
Locatedonelectricalenclosuredoor
Locatedonendcapsofcylindricalboilerpressurevesseljacket
Locatedonendcapsofcylindricalboilerpressurevesseljacket
Thismanualcontainssafetymessages.Eachofthesafetymessagesareprecededbyoneofthefollowingsignalword
panels:
Safetymessagesprecededbythislabelcontaininformation,thatifnotfollowedwillresultindeathorseriousinjury.
Safetymessagesprecededbythislabelcontaininformation,thatifnotfollowedcouldresultindeathor
seriousinjury.
Safetymessagesprecededbythislabelcontaininformation,thatifnotfollowedcouldresultinminoror
moderateinjury.
Messagesprecededbythislabelcontainimportantinformation,butarenothazardrelated.
Ensurethatthismanualisavailabletotheboileroperatoratanytime.
Readcarefullyallsafetylabelsattachedtotheboiler.Ifanysafetylabelwasdamagedduringshipment,contactthe
factoryimmediately:
Ph.5406623811;email:sales@reimersinc.com
Readthismanualbeforeinstallingandusingthisproduct.
Failuretodosocanresultinseriousinjuryordeath.
NOTICE
CAUTION
WARNING
DANGER
WARNING
PAGE6
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
ImportantSafetyInformation
1.BLOWDOWNVALVE:Thisvalveisutilizedtoblowimpuritiesfromtheboilerchamber.Whenopened,alargevolume
ofhotwaterandsteamisdischarged.Ensurethatthisvalveisproperlypipedforsuchdischarge.Stateandlocalcodes
mustbemetasapplicable.
2.ELECTRICAL:AllfieldwiringtotheboilermustbeinaccordancewiththeNationalElectricCodeandanylocalcodes
thatmayapply.Wiringmustbemadebyacompetentcertifiedelectrician.Usecopperwireonly.
Ensure that all electrical components are in a dry location, free from any possibility of water soaking. Electric foot
switcheswhensuppliedmustnotbeplacedonawetfloor.Theymustbeplacedondrysurface,notsubjecttosteamor
water.
3.GAUGEGLASS:Thegaugeglassprotectorguardsmustbeonatalltimes.Whenreplacingtheglass,besurethatthe
unitisnotunderpressureandiscooltotouch.Thegaugeglassshouldbereplacedonceperyear.Ifcracksorwearis
evident,replacethegaugeglassimmediately.
4.MODIFICATION/MISUSE:ThisboilerhasbeendesignedandconstructedinaccordancewiththeASMEBoilerand
PressureVesselCode.Anymodificationormisusecanresultinadangeroussituation.ReimersElectraSteam,Inc.is
notliableforanyproductthathasbeenmodifiedorimproperlyused.
5.PRESSUREGAUGE:Thepressuregaugeindicatestheinternalpressureoftheboiler.Itcanfail.Periodicallyhave
yourboilerinspectorcomparethegaugewithaknowngaugeutilizingthetestvalvearrangementprovided
6. REGISTRATION: Most states and cities require boiler registration and inspection. Check with your government
authorities.
7.INSTALLATIONANDREPAIR:
Installationandrepairworkofthisunitmustbeperformedonlybyexperiencedpersonnel.Beforecommencingarepair,
ensurethattheboileriscold,notpressurizedandelectricallydisconnected.Allstandardelectricalandsteamsafety
precautionsmustbetakenduringtesting.
8.SAFETYVALVE:Thesafetyvalveisdesignedtodischargehotsteamwhenthesetpressureisexceeded.Ensure
thatthedischargeportispointingtowardthebackoftheunitawayfromtheoperatororanyaisles.Testthesafetyvalve
periodicallytoensurethatitisoperatingproperly.Testcarefullyatfullpressurebyliftingleverusingpliersandletit
“slapping”shut.Steamdischargecanscald.Ensurenooneisexposed.
9.STEAMINSTALLATION:
Steampipingmustbeofblackpipe,notgalvanized.Workmustbedonebyanexperiencedsteamfitter.Allstateand
localcodesmustbemetasapplicable.
10.WATER:Ensurethatallelectricalcomponentsareinadrylocation,freefromanypossibilityofwatersoaking.
Electricfootswitcheswhensuppliedmustnotbeplacedonawetfloor.Theymustbeplacedondrysurfacenotsubject
tosteamorwater.
WARNING
PAGE7
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
1.Installation
REIMERSELECTRASTEAM,INC.boilersareheatedbyoneormoreimmersiontypeheatingelements.Automatic
controlsareprovidedtomaintainpresetoperatingpressureandproperwatersupply.Safetyfeaturesincludeautomaticlow
watercutoff,automaticpressurecontrol,safetyvalveandvisiblewaterlevelgauge.Eachboilerismanufacturedinaccordance
withtheASME PowerBoiler CodeStandards andis individuallyinspectedand stampedby anauthorized NationalBoard
InsuranceInspector.AllboilersareregisteredwiththeNationalBoardofBoilerandPressureVesselInspectors.Whenboileris
received,makesureithasnotbeendamagedinshipment.
NOTE:
ASMEDATAPLATEISLOCATEDONENDOFPRESSUREVESSELBEHINDLABELSTAMPEDWITHNATIONALBOARD
NUMBEROFUNIT.
Whenboilerisreceived,makesureithasnotbeendamagedinshipment.
Placetheboilerinalevelposition,closetotheequipmentwhichitistosupply.Thiswillinsureminimumheatlossesandallow
moreeconomicalpipingarrangements.Allsteamlinesshouldbeinsulated.Reviewtheoveralldimensionsofyourboilermodel
onpage7toselectproperboilerlocation.
RegardlessoftheNFPA70workingspacerequirementsshownbelow,provideaminimumof3ftclearanceonbothsidesofthe
boilerforelementservicing,3ftofclearancetothefrontoftheboilerand1.5fttotherearoftheboiler.
a.)Workingspace:
ElectricboilerspacingisdictatedbyNFPA70,Table110.26asfollows:
Note:Wheretheconditionsareasfollows:
Condition1—Exposedlivepartsononesideoftheworkingspaceandnoliveorgroundedpartsontheothersideoftheworkingspace,orexposed
livepartsonbothsidesoftheworkingspacethatareeffectivelyguardedbyinsulatingmaterials.
Condition2—Exposedlivepartsononesideoftheworkingspaceandgroundedpartsontheothersideoftheworkingspace.Concrete,brick,ortile
wallsshallbeconsideredasgrounded.
Condition3—Exposedlivepartsonbothsidesoftheworkingspace.
(a)DeadFrontAssemblies.Workingspaceshallnotberequiredinthebackorsidesofassemblies,suchasdeadfrontswitchboardsormotorcontrol
centers,whereallconnectionsandallrenewableoradjustableparts,suchasfusesorswitches,areaccessiblefrom
locationsotherthanthebackorsides.Whererearaccessisrequiredtoworkonnonelectricalpartsonthebackofenclosedequipment,aminimum
horizontalworkingspaceof762mm(30in.)shallbeprovided.
b.)AlcoveorclosetinstallationperUL834:Properlocationofthisboilermodelwithregardtocombustibleandnoncombustiblesurfacesandmaterialsis
codedontheboilernameplate.Thefollowingdecodingsketchanddescriptionisprovidedfortheuserinformation:
Descriptionofdimensionsandsymbols
A–Clearanceabovetopofboiler
B–Clearancefromfrontofboiler
PrefixCtonumeralindicatessuitabilityforclosetoralcoveinstallation
PrefixAindicatessuitabilityforalcovebutnotforclosetinstallation
D–Clearancefrombackofboiler
EL–Clearancefromleftsideofboiler
ER–Clearancefromrightsideofboiler
F–Indicatestypeofflooring:"NC"fornoncombustiblefloor/"C"forcombustiblefloor.Numeralindicatesminimumclearancebelowsuspendedunitsto
combustiblefloor
1.1Location
PAGE8
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
Onmodelswithpumpand/orsolenoidvalve,connect
incomingwatersupplytointakesideofsolenoidvalve.
AR&ARHsteamboilermodelsrequirefour(4)gallonsof
feedwaterperhourforeach10kWofelectricheating
capacityoftheboiler.Linesshouldbeofadequatesizeand
meetlocalplumbingcodes.
Inordertoensurelongtermtroublefreeboileroperation,
werecommendthatthewaterusedasboilerfeedwaterto
betestedforhardness.Ifthewaterinyourareaisharder
than1grain(17mg/L),useawatersoftener.Themain
causeforprematureheatingelementfailureinelectric
steamboilersiswaterhardness.Ifseverecorrosionduring
inspectionofthepressurevesselasindicatedinchapter
3.4ofthismanualbecomesevident,additionaltestsof
yourboilerfeedwatermustbeperformed.Awateranalysis
shouldbeperformedbyaqualifiedandrecognizedwater
treatmentcompanylocatedinyourarea.
Recommendedlevelsforboilerfeedwater:
Recommendedlevelsforboilerwater(waterinside
pressurevesselwhenboilerisoperating)
Allpipingfromandtotheboilermustcomplywiththe
A.S.M.E.B31.1PowerPipingCode.AllStateandlocal
codesmustbemet.Allpipingmustbedonebyaqualified
steamfitter.
Connectsteamlineofsufficientsizefromsteamlinevalve
totheequipment.Steampipingmustbeblacksteelpipe,
notgalvanized.Workmustbedonebyanexperienced
steamfitter.Allstateandlocalcodesmustbemet.
Thesafetyvalveisdesignedtodischargehotsteamwhen
thesetpressureisexceeded.Ensurethatthedischarge
portispointingtowardthebackoftheunitawayfromthe
operatorandanyaisles.Ifitisrequiredthatdischarge
pipingbeinstalledfromthesafetyvalve,thepipeshould
notbesmallerthanthevalveoutletandshouldberigidly
supportedsoasnottoplaceweightonthevalveitself.
Important:Novalveinthisline!
NOTICE Donotaddanychemicalsto
theboilerfeedwaterunless
specificallyrecommendedbya
qualifiedandrecognizedwater
treatmentcompany.
BoilerFeed
WaterSupply
SafetyRelief
Valve
1.2WaterSupply 1.3SteamOutlet
1.5SafetyReliefValve
SteamOutlet
FIGURE03
FIGURE05
FIGURE04
PAGE9
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
Tohookuppowerandcontrolvoltagetotheboiler,please
proceedasfollows.Toensureproperconnection,please
referalsototheattachedwiringdiagramandlabelsnextto
thefieldwiringterminalsforproperconductorsizeand
maximumtorquesthatcanbeappliedtotheterminal
contacts.Allwiringmustbeinstalledinaccordancewiththe
NationalElectricCodeandanylocalcodesthatmayapply.
Wiringmustbedonebyacompetent,certifiedelectrician.
Forthisservice,theN.E.C.requiressupplywiresratedat
125%offullload.Useonlycopperwire.Installafused
disconnectswitchwithinsightoftheboiler.Connectpower
supplytotheterminalsincontrolpanel.
1.6.2240VBoilerModelswithVoltageTransformer
ConnectpowersupplyasindicatedinFIGURE07.Use
AWG#8copperwire,ratedfor75°Cminimum.
1.6.3BoilerModelswithoutPreInstalledPowerCord
andControlVoltageTransformer
ConnectpowersupplyasindicatedinFIGURE08.Use
AWG#8copperwire,ratedfor75°Cminimum.
EnsurethatthevoltagebetweentheconductorsL1andL2
toNEUTRALis120VAC
Ifno240Vpowersourceisavailablethatmeasures120V
ACfromtheconductorsL1andL2toNEUTRAL,then
hookuptwoseparatepowersupplies,seeFIGURE09:
Powerhookup,AWG#8copperconductors,rated
75°Cminimum
Controlvoltagehookup,AWG#14copper
conductors,rated75°Cminimum
1.6.4120VBoilerModelswithoutPreInstalledPower
CordandControlVoltageTransformer
Connectpowersupplyasindicated.UseAWG#10copper
wireratedfor75°Cminimum
Whentheblowdownvalveisutilized,a
largevolumeofhotwaterandsteamis
discharged.Ensurethatthisvalveis
properlypipedforthisdischarge.Stateandlocalcodes
mustbemetasapplicable.
1.6Electrical
1.7BlowdownValve
CAUTION
GND
L2
L1
GND
L2
L1
NEUTRAL
INSTALL#14
AWGCONTROL
VOLTAGEWIRE
JUMPER
GND
L2
L1
NEUTRAL
FIGURE07
FIGURE08
FIGURE09
GND
L
Power
Control
Voltage
GND
L1
NEUTRAL
FIGURE10
Power
BLOWDOWN
VALVE
PAGE10
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
a.Opensteamlinevalveslightly.Thiswillallowtheboiler
tobefilledwithoutproducingbackpressure.
b.Openupperandlowergaugeglassfixturevalve
c.EnsurethatthefeedwatershutoffvalveisintheOPEN
position
d.Closetheboilerblowdownvalve
e.Throwthefuseddisconnectswitch(notprovidedby
factory)totheONpositionandturnontheboilercontrol
voltage
f.Afterapproximately2seconds,theWATERFEEDlight
turnsonandwaterenterstheboiler.Assoonasthewater
levelreachesapproximatelyhalfheightinthegaugeglass,
theautomaticwaterfeedturnsoff.
g.Iftheboilercontrollerindicatesanyalarms,thenpress
thecorrespondingRESETbutton(s).
Assoonasnoboileralarmsareindicated,theHEATING
lightturnsonandtheboilerstartstobuilduppressure.
Observethepressuregaugewhilepressurebuildsup,until
workingpressureisreached.Theworkingpressureshould
havebeenfactorysettoyourspecification.However,ifyou
wishtochangetheworkingpressuresetting,proceedas
follows.
Allpressurecontrolsarefactorypresetandrequireno
adjustment.However,ifachangeoftheoperatingsteam
pressureisrequired,thenproceedas
follows:
• Disconnectallpowersuppliesfromtheboiler.
• Closethesteamoutletvalve
• Removethelowerfrontcover.
• Turntheblackknoboftheoperatingpressureswitch
clockwisetoincreasethepressureandcounterclockwise
todecreasethepressure.
• Connectallpowersuppliestotheboiler,openthesteam
outletvalve,andinstallthelowerfrontcover.
h.Toshutofftheboiler,turnthePOWERswitchonthe
boilercontrollerOFF.
Standclearofscaldingwaterorsteam.
Disconnect the boiler from all power
supplies.
2.Operation
2.1BoilerStartup
GAUGE
GLASS
VALVES
BLOWDOWN
VALVE FEEDWATER
SHUTOFFVALVE
TurntheBLOWDOWNENABLE
switchOFFifinstalled
TurnthePOWER
switchON
NOTICE
WARNING
HighPressure
SafetyLimit
PressureSwitch.
DONOTADJUST!
Operating
PressureSwitch
OptionalBoiler
BlowoffPressure
Switch.OPT1016
STEAMOUTLET
VALVE
Donotletthepumptorundryforan
extended time as this will cause
damagetothepump.
FIGURE11
FIGURE12
FIGURE13
FIGURE14
2.2PressureAdjustment
PAGE11
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
Boilerrepairsmustbeperformedby
experiencedpersonnelonly.Ensureboiler
wateriscoldanddrainedandthatthereisnopressureand
allelectricitytotheboilerisshutoff.
Allboilersmustbeblownoffperiodicallytoremove
minerals,scaleandotherforeignmatter,whichaccumulate
insidethepressurevessel.Theconcentrationofthis
depositdependsinpartupontheconditionofthewaterin
thearea.Whenwaterisnaturallysoft,orhasbeen
softenedchemically,boilerblowoffsarerequiredlessoften
thaninareaswherehardwaterisfound.Watersofteners
aresuggestedinhardwaterareastominimizethe
formationofhardscaleonheatingelements.Anotherfactor
affectingwaterconditionistheamountofcondensate,if
any,thatisbeingreturnedtotheboiler.Sincecondensate
isessentiallycleandistilledwater,itcontainsveryfew
impurities.Ifalargepartofthecondensateisbeing
returnedandlittlemakeupwaterisused,theboilerneed
notbeblowndownasoftenaswhenlittleornocondensate
isreturnedtotheboiler.Werecommendblowoffofnewly
installedsteamboilersonceperdayuntilthefirstheating
elementandpressurevesselinspectionisperformed(refer
tochapter3.4).Ifnosignificantamountofsedimentis
foundonthebottomofthepressurevesselandonthe
heatingelementsheaths,thentheboilerblowofffrequency
canbereducedaccordingly.Thesafestmethodtoblowoff
RseriessteamboilersistoinstallaReimersElectra
Steam,Inc.properlysizedandfullytrimmedblowdown
tank,modelBTANK10.Reimersblowdowntanksare
designedandconstructedtoSectionVIIIoftheA.S.M.E.
CodeandinspectedbyacommissionedNationalBoard
Boilerinspector.
3.1.1BoilerBlowoffFrequency
Inareaswherewaterissoftorhasbeensoftened
chemically:
• Whenlittlecondensateisreturnedblowdownonceevery
secondday
• Whenalargepartofthecondensateisreturnedandlittle
makeupwaterisused,blowdownonceeveryweek.
Inareaswherehardwaterexists:
• Whenlittleornocondensateisreturned,blowdown
once
• Whenalargepartofthecondensateisreturnedandlittle
makeupwaterisused,blowdownonceeverysecond
day
Standclearofscaldingwaterorsteam.
EnsurethattheBoilerBottomBlowoff
Valveisproperlypiped.
Thistestshouldbeperformedoncepermonth.Proceedas
follows:
• Increasethesteampressureas
showninchapter2.2to
maximumoperatingpressure.
• Keepthesteamoutletvalve
closed
• Pullthetripleverandholdopen
forfive(5)secondsinorderto
flushoffthevalveseat.
• Permitthevalveto“slap”shut.If
aleakoccurs,repeatthistest
andifnecessary,replacethe
valve.
Ensurethattheboileriscold,drained
andallpowersuppliesare
disconnected
Cleantheelementrodseverysix(6)months.Tocleanthe
elementrods,orifanelementmustbereplaced,proceed
asfollows:
• Removethelowerfrontcover
• Removetheelementterminalcoverfromthefrontofthe
boiler.
• Disconnectandlabeltheterminalwires
• Removeallfour(4)nutsfromeachelementflangeand
pullouttheheatingelement
• Useastiffwirebrushtoremoveallscaleandforeign
matterfromtheelementrods.
• Cleantheelementflangesurfacesbeforeinstallingnew
elementsandgaskets
Ensurethattheboileriscold,
drainedandallpowersuppliesare
disconnected.
Inordertoprovidereliableautomaticwaterlevelcontrol,
thewaterlevelprobesarelocatedinsideafunnelshaped
probebaffle,weldedtotheinnerwallofthepressure
vessel.Theprobebafflehasdirectconnectiontothetop
andbottomofthepressurevesselsothattheprobescan
readthewaterlevel,protectedfromfoamandbursting
steambubblesthatformonthesurfaceoftheboiler
water.
Theprobebafflemustbecleanedeverysix(6)monthsof
sedimentsandotherdebristhataccumulatesatthebottom
ofthebaffle.Toaccomplishthis,proceedasfollows:
Step1:
Removethewater
levelprobecover,
disconnectfromeach
probethewireand
labelit.
RemovefirsttheShort
Probeandinspectthe
proberod.Ifsediment
hasaccumulated,use
astiffwirebrushto
removeit.Installthe
probeinitsplacein
theshell.
Repeattheabove
cleaningprocedurefor
theotherprobe(if
applicable).
Don’tinstalltheprobe(s)yet.
Step2:
Removethepipeplugfromtheboilerblowofflineas
showninFIGURE17.
Step3:
Inserttwo(2)1/4inODcoppertubesoranyothersoftrods
throughtheprobeopeningandthroughtheboilerblowoff
openingintothepressurevesseltoremovesedimentsfrom
3.BoilerMaintenance
3.1BoilerBlowoff
3.2SafetyValveTest
3.3ElementReplacementandElementCleaning
WARNING
ElementRods
WARNING
3.4WaterLevelProbeandProbeBaffleBoxCleaning
Long
Probe Short
Probe
(IfInstalled)
WARNING
WARNING
FIGURE15
FIGURE16
FIGURE17
PAGE12
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
thebottomofthe
probebaffle.
Step4:
Putaflashlightabove
theprobeopeningand
observewhetherlight
isvisiblethroughthe
boilerblowoffopening.
Ifnolightisvisible,
thenrepeatinserting
thecoppertube
throughtheLong
Probeopeningand
pushingtowardsthe
bottomtoremove
furthersedimentfrom
theprobebaffle.
Ifthereisasignificantamountofsedimentvisibleatthe
bottomofthepressurevessel,thentheheatingelements
mustberemovedasshowninchapter3.3andthe
sedimentsscoopedoutthroughtheelementopenings.
Step5:
Installtheprobe(s)intotheshellandconnectallprobe
wires.
Frequency:Minimumonceperyear.
Ensurethattheboileriscold,
drainedandallpowersuppliesare
disconnected.
3.5GaugeGlassReplacement
Closegauge
glassvalves
(TopandBottom)
Opendrainvalve
onbottomfixture
todrainglass
Removegauge
glassprotector&
rods
Loosennutsat
topandbottomof
glass.
Slideglassup
Rotatetopgauge
fixture,pullout
onbottomof
glassand
remove
Installnewglassby
performingthe
aboveprocedurein
reverseorder.
Alwaysinstallnew
rubberwashers.
Step1 Step2
Step3 Step4
Step5 Step6
Rod
Rod
WARNING
FIGURE18
PAGE13
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
4.Troubleshooting
WARNING
Ensurethattheboileriscoldandhasnopressure.
Electricaltroubleshootingmustbeperformedbyaqualifiedelectrician.
Iftroubleshootingdidnotresolveproblem,pleasecontactourservicetechniciansat:
Phone:5406623811
Email:techsup[email protected]
PAGE14
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2
5.PartslistforAR,ARHModels
WARNING
UseReimersreplacementparts.Allcomponentsaredesignedandapprovedto
beusedinthisUnderwritersLaboratorieslistedandASMENationalBoard
Stampedboiler.Failuretodosomaycauseseriousinjuryordeath.
4
31
25
15
13
9
28
21
LowWaterCutOffProbe(E3):
Connectthisprobetowiremarked“3”
*IFINSTALLED*AutomaticRefillProbe(E1):
Connectthisprobetowiremarked“1”
22
19
14
8
27
29
11
20
2
5
1
4
6 6
8
30
26
18
5
2
3
2
23 24
PAGE15
ReimersElectraSteam,Inc. 03/15/2022 AR812Manual REV2

Other manuals for AR Series

1

This manual suits for next models

3

Other Reimers Boiler manuals

Reimers RHPHC-330 User manual

Reimers

Reimers RHPHC-330 User manual

Reimers RB Series User manual

Reimers

Reimers RB Series User manual

Reimers JR Series User manual

Reimers

Reimers JR Series User manual

Reimers AR Series User manual

Reimers

Reimers AR Series User manual

Reimers HLR120 User manual

Reimers

Reimers HLR120 User manual

Reimers HLR15 User manual

Reimers

Reimers HLR15 User manual

Reimers RHP-120 User manual

Reimers

Reimers RHP-120 User manual

Reimers RE Series User manual

Reimers

Reimers RE Series User manual

Reimers RB Series Assembly instructions

Reimers

Reimers RB Series Assembly instructions

Popular Boiler manuals by other brands

Biasi Inovia 16S user manual

Biasi

Biasi Inovia 16S user manual

Unical IDEA AC 23 Installation and Servicing Manual

Unical

Unical IDEA AC 23 Installation and Servicing Manual

SOLARFOCUS octoplus installation manual

SOLARFOCUS

SOLARFOCUS octoplus installation manual

Ferroli ENERGY TOP W 60 Installation and maintenance manual

Ferroli

Ferroli ENERGY TOP W 60 Installation and maintenance manual

Rapido F 310 installation manual

Rapido

Rapido F 310 installation manual

Riello Family PRO 42 KIS User's information manual

Riello

Riello Family PRO 42 KIS User's information manual

ACV SMART Line 320 Installation, operation and maintenance instructions

ACV

ACV SMART Line 320 Installation, operation and maintenance instructions

Lennox OWB86-4D installation instructions

Lennox

Lennox OWB86-4D installation instructions

Reginox Amanzi user manual

Reginox

Reginox Amanzi user manual

Lamborghini Caloreclima ECO FVT 8 Operation and maintenance manual

Lamborghini Caloreclima

Lamborghini Caloreclima ECO FVT 8 Operation and maintenance manual

Viessmann Vitodens 200-W 19 WB2B Series installation instructions

Viessmann

Viessmann Vitodens 200-W 19 WB2B Series installation instructions

Varmebaronen Vedolux 37 Installation operation and care

Varmebaronen

Varmebaronen Vedolux 37 Installation operation and care

Metal-Fach GRAND PELLET 15 Technical and Operational Documentation

Metal-Fach

Metal-Fach GRAND PELLET 15 Technical and Operational Documentation

Proline CWB16 operating instructions

Proline

Proline CWB16 operating instructions

ROBUA AY00-120 Installation, use and maintenance manual

ROBUA

ROBUA AY00-120 Installation, use and maintenance manual

NISBETS ESSENTIALS CU759 instruction manual

NISBETS ESSENTIALS

NISBETS ESSENTIALS CU759 instruction manual

Well-mcLain SVF 725 user manual

Well-mcLain

Well-mcLain SVF 725 user manual

Riello TAU N Series Instructions For The System Manager, Installer And The Technical Assistance Service

Riello

Riello TAU N Series Instructions For The System Manager, Installer And The Technical Assistance Service

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.