Installation Guide
Solar PULSA 4x4
SAFETY FIRST
INSTALLATION
Ensure that the site is surveyed for buried services and that
Ensure that the site is surveyed for buried services and that
any electrical supply is isolated before commencing work.
any electrical supply is isolated before commencing work.
All materials to be handled using suitable mechanical equip-
All materials to be handled using suitable mechanical equip-
ment or suffi cient manpower for the weight of the item being
ment or suffi cient manpower for the weight of the item being
handled.
TOOLS & MATERIALS REQUIRED
Tri-head Key.
5mm Allen key.
Electrical Screwdriver.
PACKING LIST
Box 1 - Solar panel
Box 2 - Solar PULSA 4x4
Box 3 - Solar Panel support, channel clips , battery and regulator.
Side Cutters
13mm spanner
Ø14mm drill
The Solar PULSA 4x4 is
supplied as a kit designed
to fi t onto a pre-installed
89/168 column. The col-
umn manufacturer should
be consulted to provide
a column and foundation
plan suitable for the equip-
ment to be mounted and
environmental conditions
peculiar to the site. The
solar panel includes an
89mm socket which should
be accommodated in the
design.
Weights and dimensions
of the Solar PULSA 4x4
equipment are shown over-
leaf to help with calculating
loads.
3Consider how the
PULSA 4x4 power
cable will be routed
to the column base
housing. Drill the
post to suit the
route.
Surface protect
any bare metal and
ensure any holes
are free from burrs
and sharp edges.
Assemble the solar panel support by
uncoiling the solar panel output lead
and feeding it through the panel support
bracket as shown.
Place the bracket over the aperture in
the panel back moulding and secure
with the 4 Tri-head screws supplied.
2
Solar panel
output lead
Panel back
moulding
Panel support
bracket (89mm)
45
Doc Ref : IG198
Issue Date: September 2019
Issue Number : 1
Take the solar panel assembly
and feed the solar panel output
lead down the post from the top
so that it emerges in the column
base housing.
Place the solar panel assembly
on the top of the post and align it
to point directly South.
Ensure that nothing impedes the
solar panels view of the sun all
year round.
Tighten the grub screws to lock
the solar panels assembly onto
the post.
Fix the PULSA 4x4 to
the post using slide in
channel clips.
Route the PULSA supply
cable down into the
large base compartment,
protecting any exposed
cable with suitable
conduit.
1
6
Moving to the column base remove the existing
wooden board and replace with the regulator
board assembly supplied
Connect the Solar panel output lead to the PV
terminals and the PULSA supply cable to the
Load terminals as shown.
On/Off Switch
Hook
PV
Solar
Load
Fixing screw