MONTAGEANLEITUNG VARIO-SLACK © Slackline-Tools 03.2017 MONTAGEANLEITUNG VARIO-SLACK © Slackline-Tools 03.2017 7
Requirements for assembly
• Level concrete surface, non-cracked, of concrete
compressive strength class C 20/25 to C 50/60.
• Concrete thickness of at least 150 mm.
• Space requirement: 740 mm wide, 645 mm high and
548 mm deep, as well as at least 100 mm of additional
free space around the anchor.
• Recommended mounting distance: 4–6 m, max. 10 m.
• Make sure that both ground anchors are aligned opposite
to each other. The slackline must not be pull diagonally.
Assembly
Assembly of Vario-Slack WALL and oor rack
•Proceed as shown in the drawing above ( g. 7).
• Insert one of the supplied hexagon head screws with
applied large washer through the centre hole (14 mm)
of the upper row on the Vario-Slack WALL.
•Hold the Vario-Slack WALL against the oor rack so that it
is possible to insert the hexagon head screw into the
provided borehole in the oor rack.
• Screw down the supplied hexagon nut and the small
washer at the rear side of the oor rack onto the hexagon
head screw and hand-tighten the hexagon nut.
• Repeat the procedure with the other screws (total amount
of screws: 6).
• Now tighten all screws to a maximum tightening torque
of 60 Nm.
Securing the Vario-Slack GROUND to the concrete oor
Secure the Vario-Slack GROUND according to the above
drawing ( g. 8) and handle the Vario-Slack GROUND
(weight: 36 kg) with care.
• Place the Vario-Slack GROUND at the desired position.
• Mark the position of the boreholes (d) and (dl) through the
holes in the rear transverse pipe of the Vario-Slack GROUND
on the oor. Mark the centre of the long hole (dl) (to allow
for additional correction).
•Drill through the top layer of the oor (max. 4 mm).
• Drill a borehole with a diameter of 20 mm and a depth of
130 mm so that the inserted female thread anchors are
ush with the concrete oor.
• Clean the boreholes.
•Observe the speci ed processing and hardening time for
the mortar.
• Inject the injection mortar beginning at the bottom of the
borehole making sure that there are no bubbles.
Tip: Screw the complete knurled screw into the female thread
anchor to allow for easier screwing in and for the vertical
alignment of the female thread anchor.
•Screw the female thread anchors into the boreholes by
hand without a setting tool rotating them slightly until their
upper edge is ush with the concrete oor.
•Make sure that the female thread anchors are vertically
aligned.
•Allow the mortar to harden completely.
•Remove the knurled screws in case you have inserted them
for screwing in and alignment.
• Position the Vario-Slack GROUND above the female thread
anchors on the oor.
•Insert the knurled screws ( rst (d), then (dl)); then tighten
them by hand.
Fig. 7:
Washer, large
M12x160 hexagon head screw
Plastic cap
Washer, small
Plastic cap
M12 hexagon nut
Fig. 8:
(d)
(dl)
600 mm
M12 RG 18x125 female thread anchor
M12x60 knurled screw
Montageanweisung_DE_EN_Vario-Slack_02.2017_eingebettet.indd 7 17.05.17 13:55