8 May 2020
3.1. CHECK THE ARRAY LOOP FOR LEAKS
1. Before the system has been charged, open
all shut-off valves on the collector loop.
2. Apply 20 psi less than the pressure relief
valve rating of pressure for 15 minutes.
Any drop in pressure during that time
indicates a leak.
3. Find the source of the leak and repair it.
Repeat this procedure until the loop holds
pressure.
3.2. FLUSHING THE SYSTEM
After installing the SolarStation XL the system
should be flushed. Piping in new solar
installations can be covered with dirt, grease,
solder flux or other impurities that over time
affect the quality of the propylene glycol HTF.
A thorough cleaning is required before
charging the system with propylene glycol
water mixture.
Step 1 – Fill solar tank with water and ensure
there are no leaks on the potable side of the
system. Open the nearest hot water fixture
and run to flush out any flux from the
installation.
Step 2 -Keeping the two potable isolation/flush
valves closed during potable circuit flush.
Open a flush/drain port allowing water to flush
circuit to this point then close flush/drain port.
Open other flush/drain port allowing water to
flush circuit to this point then close flush drain
port.
Alternate flush/drain sequence stated above
until all air is removed from the potable circuit.
Step 3—Keeping the two solar isolation/flush
valves closed. Flush array loop with water to
clean out any debris or sediment from the
pipes and collectors.
3.3. CHARGING THE SOLAR CIRCUIT
Once the system is flushed you are ready to fill
the solar storage tank with water and to
charge the collector loop with a mixture of heat
transfer fluid (HTF) and water. Due to
variations in municipal water quality
throughout the country, distilled or deionized
water shall be used to mix with the propylene
glycol HTF. Refer to Table 3.3.1 for percent
concentrations.
1. Connect the outlet of a transfer pump via a
hose to the fill valve.
2. Open the fill valve.
3. Open the drain valve. Connect the drain
valve to a bucket.
4. Fill the bucket with the appropriate mixture
of propylene glycol and water.
5. Run the pump. Continue running the pump
until you do not see air bubbles in the
coolant.
6. Turn off the pump. Let the system sit for
ten minutes.
7. Repeat previous steps until no air is
discharged.
8. Close drain valve.
9. Continue charging until it reaches the
necessary pressure for the system’s
configuration.
10.Close the fill valve.
11. Turn off and disconnect charging pump.
Note: It is recommended to install commissioning
automac air vents as provided in SunEarth Add-a-
row and systems kits on each collector bank. Two
weeks following system commissioning the solar
circuit pressure should be veried and increased if
needed with the automac air vent isolaon valves
being closed and plugged with the commissioning air
vents being removed .
3. SYSTEM COMMISIONING
Percent By Volume - Dow Frost HD
Temperature (°F) Freeze Protection
20 18%
10 29%
036%
-142%
-20 46%
-30 50%
-40 54%
-50 57%
-60 60%
Table 3.3.1: HTF Concentration