1) Select the mounting location of the flow station.
The construction plans normally show the
mounting location. If no location is specified,
then typically the flow station is installed
upstream of the damper actuator.
WARNING: Figure 7 gives the minimum straight
length duct diameters required for the flow
station to operate correctly.
TSI recommends installing the flow station
upstream of the damper (before). TSI does not
recommend installing the flow station
downstream (after) the damper. If the flow
station must be placed downstream, a minimum
of 4 straight duct lengths between the damper
and flow station is required. In addition, the flow
station must be rotated 90o (perpendicular) from
the damper shaft position.
The minimum straight duct lengths shown are
the absolute minimum.
2) Drill a 1¼” hole in the side of the duct work. If
probe is longer than 18 inches, drill a 516" hole
directly across from the 1¼” hole (Figure 8).
3) Slide foam gasket onto flow station, and insert
into duct work. Insert the flow station through
the 1¼” hole, and into the 516" hole (if required).
On probes 18 inches or longer attach the nut to
the threaded end of the flow station (516”hole
end).
4) Rotate the flow station until the air flow
indicator arrow matches the correct direction of
air flow.
5) Screw the flow station into place with sheet
metal screws (screws not provided by TSI). On
18 inch and longer flow stations tighten the 516”
nut. The finished installation should look like
Figure 8.