Qwik Install
STEP 0: Install mounting pole per separate instructions.
STEP 1: Prepare the enclosure: Install DIN rail (if required) to door
using two phillips head screws. Install just the top mounting bracket to
the enclosure using two 8mm bolts.
NOTE: It takes two people to mount the
enclosure to a pole. The standard U-Bolt
mounting accommodates a pole up to 4”
diameter. Multiple pole straps can be
used for extra strength. Pole straps are
available for poles up to 11” diameter or
larger.
STEP 2: Install the bottom bracket and
stabilizer bracket to the pole using U-Bolt
and Pole Straps. The stabilizer bracket is
used as an aid to mounting and addition-
al support when mounted.
STEP 3: Lift the enclosure and place it
on the stabilizer bracket. Connect the top
bracket to the pole using U-Bolt and/or
Pole Straps.
STEP 4: Attach the two 8mm bolts that
hold the bottom bracket to the enclosure.
Make sure all bolts are tight. (8-15 ft lbs)
STEP 5: Install the three wire feedthru
cable glands in the holes in the bottom of
the enclosure. If one or more of the cable
glands will not be used, just cut a short
piece of cable and tighten in the cable
gland to seal it.
NOTE: The bottom plate can be removed
from the enclosure if you need to add
some additional feedthru. (ex; conduit
connection)
STEP 6: Install the batteries in the enclosure. For 12VDC the batteries
are connected in parallel, for 24VDC the batteries are con-
nected in series pairs and for 48VDC the batteries are con-
nected in series. (See wiring diagrams later in this guide).
NOTE: The enclosure has slot features that can be used
to strap the batteries if desired. Tycon has velcro straps
(#5700030) available. It takes two straps per battery.