UfiSpace S9300-32D Manual

Hardware Installation Guide
S9300-32D
400GE Spine Switch
R1.0

S9300-32D Hardware Installation Guide | i
Table of Contents
1Overview.............................................................................................................................1
2Preparation.........................................................................................................................2
Installation Tools .....................................................................................................................2
Installation Environment Requirements .................................................................................3
Preparation Check List.............................................................................................................4
3Package Contents................................................................................................................5
Accessory List ..........................................................................................................................5
Component Physical Information............................................................................................5
4Identifying Your System.......................................................................................................7
S9300-32D DC Version Overview ............................................................................................7
S9300-32D AC Version Overview ............................................................................................9
DC Version PSU Overview .....................................................................................................10
AC Version PSU Overview......................................................................................................11
Fan Overview.........................................................................................................................12
Port Overview........................................................................................................................13
5Rack Mounting..................................................................................................................14
6Installing Fan Modules.......................................................................................................17
7Installing Power Supply Units ............................................................................................18
8Grounding the Router........................................................................................................20
9Connecting Power .............................................................................................................22
DC Version .............................................................................................................................22
AC Version .............................................................................................................................24
10 Verifying System Operation...............................................................................................26
Front Panel LED ...................................................................................................................26
PSU FRU LED........................................................................................................................27
Fan FRU LED.........................................................................................................................27
11 Initial System Setup...........................................................................................................28
12 Cable Connections.............................................................................................................29
Connecting the USB Cable...................................................................................................29
Connecting the OOB Management Cables..........................................................................29

S9300-32D Hardware Installation Guide | ii
Connecting the Management Cables..................................................................................30
Connecting the Transceivers ...............................................................................................30
13 Cautions............................................................................................................................31

S9300-32D Hardware Installation Guide | 1
1Overview
The UfiSpace S9300-32D is a high-performance, versatile open networking white box switch
that is designed to address the fast growing segment of the Ethernet switching market and
the needs to push capacity to the next level.
With 32 x 400GE QSFP-DD ports, the S9300-32D switch is where computer resources
(servers or blade chassis) are centralized and managed in a structured way utilizing high-
efficiency Ethernet connectivity.
With advanced capabilities, these switches deliver performance and intelligence to the
network edge in a flexible 1RU form factor that helps reduce infrastructure and
administrative costs.
The S9300-32D is the epitome of future networking with a powerful 8-core processor and 32
high-speed 400GE interfaces. It comes with redundant, hot swappable components for
convenience, increased availability, reliability and lower costs of maintenance.
This document describes the hardware installation process for S9300-32D.

S9300-32D Hardware Installation Guide | 2
2Preparation
Installation Tools
Phillips #2 Screwdriver
Crimping tool
8 AWG wire with ring terminal for
DC power supply
6-AWG wire for grounding
Wire-stripping tools for
stripping 6-AWG copper wire
Console cable
•PC with terminal emulation software. Refer to the "Initial System Setup" section for
details.
•Baud rate: 115200 bps
•Data bits: 8
•Parity: None
•Stop bits: 1
•Flow control: None

S9300-32D Hardware Installation Guide | 3
Installation Environment Requirements
•Power Reserve: The S9300-32D power supply is available with:
1. DC Version: 1+1 active-active -48 voltage DC power supply field replaceable unit or;
2. AC Version: 1+1 active-active universal 220V AC power supply field replaceable unit.
To ensure the active-active feed power design functions properly, a field with dual power
circuit is recommend with a reserve of at least 1300 watts on each power circuit.
•Space Clearance: The S9300-32D width is 17.17 inches (43.6cm) and shipped with a rack
mount brackets suitable for 19 inch (48.3cm) wide racks. The depth of the S9300-32D chassis
is 25.4 inches (64.5cm) without the field replaceable units (FRUs) and comes with adjustable
mounting rails suitable for rack depths of 26 inches (66cm) to 30 inches (76.2cm). The handle
for the fan units will extend outwards by 1 inch (2.5cm) and the handle for the power supplies
will extend outwards by 1.5 inches (3.8cm). Therefore, to accommodate the fan and power
supply handles, a minimum space clearance of 6 inches (15.24cm) is needed at the back of
the S9300-32D. A total minimum reserve depth of 31.4 inches (79.7cm) is required.
Figure 1.
Figure 2.

S9300-32D Hardware Installation Guide | 4
•
Cooling: The S9300-32D has two options for airflow direction. There is a back-to-front
option (Figure 3. Left) and a front-to-back option (Figure 3. Right). Make sure the
equipment on the same rack have the same airflow direction.
(Back-to-Front Airflow)
(Front-to-Back Airflow)
Figure 3.
Figure 4.
Preparation Check List
Task
Check
Date
Power voltage and electric current requirement
DC version: -40 to -75V DC, 40Ax2 ampere maximum or;
AC version: 200 –240V, 7.5x2 ampere maximum
Installation spacing and weight load requirement:
S9300-32D is 1RU (1.75”/4.5cm) in height, 19” (48.3cm) in width,
and 31.4 inches (79.7cm) in depth without considering cable routing
Thermal requirement
S9300-32D working temperature is 0 to 40°C (32°F to 104°F),
airflow direction is front-to-back or back-to-front
Installation tools required
#2 Phillips Screwdriver, 6-AWG wire stripper, and crimping tool
Accessories required
PC with terminal emulation software

S9300-32D Hardware Installation Guide | 5
3Package Contents
Accessory List
Item
Description
Spec. & Dimensions
Qty.
Weight
1
Grounding Lug
1.54” x 1.47” x 0.49”
(#6 AWG)
(39 x 37.5 x 12.5mm)
1 pcs
0.14lbs (63.6g)/pcs
2
DC Input Lug
DC Version:
0.87’’ x 0.47’’ x 0.34 ‘’
(# 8 AWG)
(20 x 12 x 8.8mm)
4 pcs
(DC Only)
0.09lbs (40.8g)/1pcs
3
Screw Kit
(for Ground Lug)
2 x Screws M4*L8.0mm
1 set
0.01lbs (2.6g)/set
4
Adjustable Mounting
Rail (for 4 posts)
26.03” x 1.72” x 0.88”
(20” to 35” rack depth)
(661.3 x 43.8 x 22.4mm)
2 pcs
3.39lbs(1.54kg)/pcs
5
Screw Kit
(for Adjustable
Mounting Rail)
2 x Screws M4.0*L5.5mm
1 set
0.004lbs (1.9g)/set
6
RJ45 to DB9 Female
Cable
8”(2.4m)
1pcs
0.27lbs(123.9g)/pcs
7
USB3.0
7.8”(20cm)
1pcs
0.03lbs(16g)/pcs
Component Physical Information
Specification
Item
Description
Weight
Total package contents
45.56lbs (20.5kg)
Chassis without FRU
23.93lbs (10.77kg)
DC/AC PSU
DC PSU: 2.2lbs (1.0kg)
AC PSU: 2.6lbs (1.2kg)
Fan module
0.41lbs (185g)
Grounding lug kit
0.147lbs (66.2g)

S9300-32D Hardware Installation Guide | 6
Adjustable mounting rail
6.79lbs (3.08kg)
USB extension cord
0.03lbs (16g)
AC power cord (AC version only)
0.7lbs (318g)
RJ45 to DB9 female cable
0.27lbs (123.9g)
Dimension
S9300-32D (W x D x H)
17.17” x 25.4” x 1.72”
(436 x 645 x 43.8mm)
PSU (W x D x H)
1.99” x 12.64” x 1.57” (50.5 x 321 x 40mm)
Fan module(W x D x H)
1.98” x 5.64” x 1.57” (50.4 x 143.2 x 40mm)

S9300-32D Hardware Installation Guide | 7
4Identifying Your System
S9300-32D DC Version Overview
Figure 5.

S9300-32D Hardware Installation Guide | 8
Figure 6.

S9300-32D Hardware Installation Guide | 9
S9300-32D AC Version Overview
Figure 7.

S9300-32D Hardware Installation Guide | 10
Figure 8.
DC Version PSU Overview
1+1, hot swappable power supply unit (PSU) field replaceable unit (FRU). There are two types of DC
PSUs. The picture on the left is the DC PSU with back-to-front airflow and the picture on the right is
the DC PSU for front-to-back airflow.
(Back-to-Front Airflow PSU)
(Front-to-Back Airflow PSU)
Figure 9.

S9300-32D Hardware Installation Guide | 11
(Front-to-Back Airflow PSU)
Figure 10.
AC Version PSU Overview
1+1, hot swappable power supply unit (PSU) field replaceable unit (FRU). There are two types of AC
PSUs. In Figure 12 below, the left is the AC PSU with back-to-front airflow and the picture on the
right is the AC PSU for front-to-back airflow.
(Back-to-Front Airflow PSU)
(Front-to-Back Airflow PSU)
Figure 11.

S9300-32D Hardware Installation Guide | 12
(Front-to-Back Airflow PSU)
Figure 12.
Fan Overview
5+1, hot swappable fan field replaceable unit (FRU). There are two types of fans. In Figure 13, the
top picture is for fans with back-to-front airflow and the picture on the bottom is for the fans with
front-to-back airflow.
(Back-to-Front Airflow Fans)
(Front-to-Back Airflow Fans)
Figure 13.

S9300-32D Hardware Installation Guide | 13
Port Overview
Port ID
Form Factor
Maximum Support Distance
Support Speed
0 ~ 31
QSFP-DD
238.01ft (100m)
400GE
Figure 14.

S9300-32D Hardware Installation Guide | 14
5Rack Mounting
It is recommended that installation be done by two trained professionals. One
individual should hold the equipment in position on the rack while the other
secures it in place.
1. Separate the adjustable rail slides.
1.1 Pull apart the inner and outer rails until it is locked in place. An audible click can be heard
when the rails are locked in place.
1.2 Pull the white tab forward to unlock the rails in order to completely separate the inner rail
from the outer rail. The white tab is located on the inner rail.
1.3 Once the inner rail is separated, push the tab located on the outer rail to unlock and slide
the middle rail back.
Figure 15.
2Install the inner rails onto the chassis.
2.1 The inner rail has key-shaped holes where attachment pins on the chassis can be aligned.
The chassis has 5 attachment pins on each side, for a total of 10 pins. Fit the key-shaped
holes with the attachment pins and pull back to hold the inner rack in place.
Make sure the captive screw of the inner rail is positioned at the front of the
chassis.
2.2 After the attachment pins are secured to the inner rail, lock the inner rail to the chassis
using two M4 screws (one on each chassis side). See Figure 16.

S9300-32D Hardware Installation Guide | 15
Figure 16.
Figure 17.
3Fix the outer rails onto the rack.
3.1 The outer rails have two brackets on the front and rear. Pull back the clip of the rear
bracket to attach it onto the rack. An audible click can be hear when the bracket is secured
onto the rack.
3.2 Once the rear bracket is secured, pull back the clip of the front bracket attach it to the rack.
An audible click can be heard when the bracket is secured onto the rack.
Figure 18.

S9300-32D Hardware Installation Guide | 16
4Insert the Chassis to complete the installation.
4.1 Pull the middle rail fully extended into lock position, an audible click can be heard when the
middle rail is fully extended and locked into position.
4.2 Insert the chassis by lining up the inner rails into the slot of the middle rail.
4.3 Slide the chassis into the middle rail until it hits a stop.
4.4 Push the blue release tab on each rail to unlock the rails and slide the chassis all the way
into the rack.
4.5 Lock the chassis into place by using the captive screw on the front of the inner rail.
Figure 19.

S9300-32D Hardware Installation Guide | 17
6Installing Fan Modules
The fan modules are hot swappable field replaceable units (FRUs), which can be replaced while the
router is operating as long as all the remaining modules are installed and in operation. The fans
come pre-installed and the following steps are instructions on how to install a new fan module.
1. Loosen the captive screw located on the fan module.
Figure 20.
2. Grip the fan's handle and firmly pull it out of the fan bay.
Figure 21.
3. Align the new fan module with the fan bay.
4. Carefully slide the new fan module into the fan bay and gently push until it is flush with the
case.
5. Secure the captive screw on the fan module to lock the fan in place.
Figure 22.
Table of contents
Other UfiSpace Network Hardware manuals