Westbo of Sweden
Westbo Victoria 125 General instruction/connection to
chimney
Preparation of the stove
Cut off the strap that holds the cardboard in place around
the stove. Lift off the cardboard box and check that the
stove is undamaged.
Transport damage must be reported direct to the transport
company.
Lift the stove off the pallet. The top crown is placed under
the stove.The feets are adjustable and could be adjusted if
the level differs on the surface. Check this before doing the
measurements for hole making. Proceed to the next step.
Connection to new chimney
Follow the instructions from the chimney supplier.
The stove can only be connected backwards in the original
version, as optional it can be connected upwards by using
back/top ue collar.
Connection to existing chimney
Before starting interventions in the smoke channel, it is im-
portant to let an expert check and inspect. This to be sure
that it is dense and properly dimentioned for the stove.
Before start it is important to let the chimney sweeper
inspect your chimney. Do it in the following order:
1. Measure the centre of the hole
2. Use suitable tools to make the hole
3. We recommend you to use a ue spigot
4. Insert the ue pipe into the spigot. Then connect with the
stove seal between the spigot and the ue pipe (preferably
seal rope). The pipe should not go into the actual chimney,
cut if necessary. Apply additional sealant for other joints.
5. Important! If your connection kit includes a rosette collar
to cover the hole into the chimney, put it on before connec-
ting the stove.
6. Contact the chimney sweeper for inspection.
Building notication
Before installation of the re place and construction of a
chimney, it is a demand to do a building notication.
For piece of advise, contact your local authorities.
When receiving the stove
When the stove is received it is important to check the
goods to see that the stove is not damaged during the
transport. Damages should be notied to the freight com-
pany immediately.
Floor protection
The oor protection prevents the oor in front of the stove
from sparks. Check your local regulations by your domes-
tic authorites.The oor protection could consist of 0,7 mm
metal sheet, glass, tiles, natural stone etc.
Please read this folder carefully.
Good luck with your new
Westbo Victoria 125.
Westbo of Sweden
The Westbo Victoria 100
have adjustabele feets.
Westbo Victoria 125 is preassembled at the
factory with the connection to the rear.