WMT CNC210 User manual

CNC210 Operating Manual
CNC lathe
Model CNC210
OPERATING MANUAL
(Mechanical part)
WMT CNC INDUSTRIALCO.,LTD

CNC210 Operating Manual
Contents
1.General Instruction……………………………………………………2
2 Safety guide for operating this machine………………………………3
3.Lifting and Installing………………………………...........……..........8
4.Technical data………………………………………………………11
5.Machine structure……………………………………………………12
6.Operating instruction and safety protection……………………….…15
7.Inspection and maintenance…………………………………………16

CNC210 Operating Manual
Note:Please read the operation manual carefully before using the
machine.
1.General Instruction
1.1 The scope and purpose of this operation manual .
This manual is written for the flat bed CNC lathe to guide the user to accurately use the
machine which produced by our company , please read it carefully.
In the second part of the manual ,we providing the safety instructions for the operation of the
machine.which the operator can use it as a check item for daily work.
In the second part of the manual,we provide the method of how to install and matters what
we should pay attention to.
In the fourth and fifth part of the manual,you should understand the Technical data and the
Machine tool structure before using .
The sixth part of the use of machine tools and safety protection describes the operation of the
machine tools in the security situation
The seventh part of "inspection and repair" provides the operator with the knowledge and
methods of operation and maintenance of the machine tool.
The eighth part of the "easy-broken parts" provides the machine parts diagram
Please connect with our service or technical department,if any problems doesn’t mention in
the manual.
1.2 The main use of the machine.
The machine is mainly used for processing various kinds of shaft, disk type parts,can be
turned all kinds of thread, arc, cone and the inner and outer surface of the revolving surface, can
meet the needs of high-speed cutting of ferrous and non-ferrous metal materials,Suitable for the
processing of plumbing and heating equipment, valves, electrical appliances, instruments,
automobiles, motorcycles, bearings and other parts of the industry.With high speed, high
efficiency, high reliability, and nice work at the machining parts consistency ,and little influenced
by human factors.Machining accuracy can reach IT6~IT7 level.
1.3 Accuracy of the machine.
The precision of the machine is in accordance with the standard of the JB/T8324.1-1996
simple CNC horizontal lathe
1.4 The using environment of machine .
This machine is suitable for operation under the environment and conditions as specified
below.
A. Ambient temperature:5--40℃
B. Dampness:The maximum temperature of 40℃, the relative humidity shall not exceed
50% of the range

CNC210 Operating Manual
C.Altitude:1000 meters below
D. Radiation: Avoid the change of ambient temperature caused by direct sunlight or other
heat radiation
E.Installation position should be far away from the vibration source and inflammable and
explosive materials, away from the electromagnetic interference area
1.5 Impact of machine tools on the environment
When the machine idling,the noise is not more then 83db,no harmful gas or liquid emissions,
so there is any adverse impact on the environment.
2.Technical data
Item
Data(Metric)
Data(Inch)
Model Name
CNC210
CNC210
Max.swing over bed
210mm
8 1/4"
Max.swing over carriage
105mm
4 1/8"
Max. Machining length of work pieces
250mm
9 7/8"
Range of metric threads
0.25~4mm
0.00984-0.1575”
Range of imperial threads
6~80T.P.I
6~80T.P.I
Through spindle bore.
26mm
1.0236"
Spindle speed(DC stepless adjustment)
100~3000r/min
100-3000r/min
X travel
105mm
4 1/4"
Z travel
275mm
10 13/16"
Max.moving speed of X axis(step-motor)
2000mm/min
78 3/4"/min
Max.moving speed of Z axis(step by step)
2000mm/min
78 3/4"/min
Taper of tail stock
MT2
MT2
Tail stock diameter
22mm
7/8"
Max.travel of tail stock
55mm
2 3/16"
Positioning accuracy
0.02mm
0.0008"
Re-positioning accurancy
0.02mm
0.0008"
Spindle proximal bounce
0.01mm
0.0004"
Motor
1.2kw
1.2Kw
Lubricating pump power(manual operation)
Water pump power
40w
40w
Tool-Post
electrical 4- station
Size of tool arbor
12mm
1/2"
Overall size(L X W X H)
1105 x 925 x
1145mm
43 1/2”x 36 3/7”x
45 1/9”
Net weight(about)
260kg
573lbs
3.Safety protection
The machine tool with some necessary safety equipment and warning signs, please read the
instructions carefully before operator,in order to avoid the damage or other machine operation
accident ,please fully understand all the operation method ans the signs.

CNC210 Operating Manual
3.1 The requirement to the operation and maintenance person.
The operation who use the machine should be well trained and should be qualified.
Before using the machine ,the operation should carefully read the manual operation ,and
fully understand what mention in the manual operation.
In order to avoid accident ,the Maintenance should be assumed by the person who should
have the appropriate qualifications or professional maintenance knowledge.
3.2 Basic operation requirement.
Dangerous :
A:Control panel, electrical cabinets, transformers, motors, junction box and other high
voltage terminal parts of the untouchable, otherwise, it is easy to get a shock.
B:Don’t touch the bottom with wet hands,otherwise it will cause a short circuit, machine
malfunction, endanger personal safety.
Warning:
A: You should be very familiar with the emergency bottom switch .so that in any need
time ,you don’t need to find it.
B:Please make sure that the power of the machine should be offed ,before you replacement
the electrical components.
C:When the power supply part fails, the main circuit breaker should be turned off
immediately.
D:When a task needs to be completed by two or more than two people, each step in the
operation should be required to provide a coordinated signal,and you should get the signal and
accept it ,then you can do the next step work.
Attention:
A:Use recommended lubricants, oils or fats or oils that are recognized as equivalent to the
performance of oils or fats. Before replacement, the machine must be cleaned to avoid adverse
consequences of two different types of oil or fat.
B:The electrical components needed to be replaced which must be consistent with the
electrical parts list or equivalent.
C:We need to prevent the NC device operation panel electrical control panel etc. impact,
otherwise easily lead to failure, so that the machine can not work normally.
D:Do not change the parameters, values, or any other electrical devices . When you have to
change, record the original data so that you can return to the original number when you need it.
E:Don't dirty, damaged or mobile warning signs, if the signs on the handwriting has become
blurred sign or lost, please order from us new signs.
F:Needing enough space ,in order to avoid danger.
G:Water or oil can make slipping on the ground, resulting in danger, iron can cut the body, in
order to prevent accidents, the ground must be kept clean. Clean iron filings do not directly with
the hand

CNC210 Operating Manual
H:you should confirm in advance before you operation the switch,no mistakes,or prone to
accidents. Don’t touch the switch at will.
3.3 Requirement before power supply
Danger:
Cable, coil, wire, electrical components, if there is damage, will produce leakage, causing
electric shock accident. So you should check them carefully before using.
A:you must understand them which were required in the operation and programming
Manual.and you should clear about each function and operation .
B:Wear oil proof, non slip insulated shoes, and other requirements of the safety protection
facilities.
C:Check all NC devices, operating panel, electrical control panel, door and lid should be
closed.
Attention:
A:The cable conductor need have sufficient cross-sectional area,which from the power
supply switch to the total machine power switch.so that it can meet the demand of power
transmission.
B:the cable conductor which dew on the ground should be waterproof, prevent cuts, anti
wear protective measures ,in order to avoid the accidents.
C:we should clean the debris and antirust oil,when we start the machine,after a long-term
shutdown or unpacking machine before the first use.Each lubricating point, should be re-oiled,
and in accordance with the lubrication requirements. The machine should be coated with anti rust
oil neutral before the long-term stop.
D:The oil tank should be not less than the oil standard position, regular inspection and oiling.
E:For lubrication points, types of oil, please refer to the relevant lubrication instructions.
F:Each switch and handle should be flexible and smooth.
G:When the power supply to the machine, in turn connected to the factory power supply
switch, the total machine power switch, the operating board of the system power switch.
H:Check coolant and add coolant if necessary.
3.4 The demand after power supply
When the machine power supply, the NC system of the screen should be lit, display status in
accordance with the state of the NC system specification.
3.5 Routine checking
Warning:
When checking the tightness of the belt, do not extend the finger to the belt and the belt
pulley, easy to press the finger.
Attention:
A:Please check the electrical mechanical system, etc., to ensure that no abnormal noise.
B:Please check all parts of lubrication of machine tools.

CNC210 Operating Manual
C:Please check the protective cover and door and other safety devices are safe, normal work.
D:Please check the belt, if not meet the requirements of the specification, please adjust or
replace. The belt should be intact without damage.
E:The chuck should be locked,before the main chuck running,in order to prevent the chuck
out.
3.6 Temperature rise
Attention:
A:To heat up the machine should be in the state of automatic operation of the machine
without load, the maximum speed of the machine tool movement of half or 1/3 to make the
machine running 10~20 minutes, so that the machine to achieve stable temperature
B:In automatic operation, the machine tool on each moving parts should be in accordance
with the program automatic action, at the same time to check the movement of the various parts of
the movement, should be smooth without abnormal noise.
C:If the machine idle for a period of time, we must carry out the temperature rise of the
machine In order to make the machine tool life lasting, stable and reliable accuracy.
3.7 Preparation before starting
Warning:
A:The tooling should accord with the technical parameters ,no over loading ,or affect the
balance of the machine.
B:Tool wear transition or damage, not only affect the machining accuracy of parts, and will
damage the machine tool, it must always check the tool condition, timely replacement or repair.
C:Processing areas should have good lighting, in order to facilitate the safety detection.
D:Tools and other items around the machine tool should be kept in an orderly, reliable, clean
and orderly environment.
E:tools,work piece and any other items should not put on the spindle box cutter, spindle,
carriage and other similar parts, in order to avoid the accident.
F: the center hole of the work piece should match its weight,so can we prevent the work
piece from sliding out of the center.
Attention:
A:The length should be in the limited range ,so that we can avoid interference.
B:After the tool is installed, try to run, and pay attention to the adjustment of tool parameters.
3.8 Matters needing attention in works
Danger:
A:The operator with long hair ,should wear hat ,and plate the hair in the hat,and avoid the hat
blown off by the exhaust fan .shall not wear gloves,and operator not allow to romp and play.
B:The work piece should be clipped,the wrenches on the spindle and chuck should be taken
down.
C:adjusting the nozzle of the coolant should under the machine shutdown state.

CNC210 Operating Manual
D: Don’t use hands or clothes in contact with rotating work piece and the main spindle.
E:In the process of automatic ,please don’t open the guard door of the machine.
F:In heavy duty processing, should avoid chip accumulation, because hot chips may cause
fire, heat accumulation will cause the thermal deformation of the machine, affect the processing
precision.
Warning :
A:The operation of the switch is not allowed to wear gloves, may cause malfunction of the
machine.
B: Only after the Tool carrier ,spindle and other parts of the machine is stopped ,can be allow
replace the work piece and tools.
C: Don’t clean up the chip when the machine work.
D:Not allow to open the door or guard cover ,when operation the machine.
Attention :
A:when heavy work piece need to be moved ,you should work with two or more than two
people ,in order to avoid danger.
B:If the work piece need to be moved by elevator or forklift, crane and other similar
equipment,the operator should be trained and approved by the enterprise.
C:Should use the brush to clean the knife cutting head, not directly to clean with hands.
D:Processing of magnesium alloy, the operator should wear gas masks; processing of large
dust materials, should wear masks and other protective equipment
3.9Interrupt processing
Attention:
After the completion of the processing,the operating panel should be on the power switch off,
and disconnect the main circuit switch,when you need leave the machine for a while.
3.10 Finish machining
Attention:
A:don’t clean up the machine before the machine stopped
B:the machine should be clean up after stop working,remove iron, wipe the door, window
cover, etc.
C:Return each component of the machine to the initial position.
D:To check the shaving device whether is not damaged or not, if there is any damage please
replace it immediately.
E:Check the contamination of the coolant and lubricating ,and replace it if necessary.
F:Check the amount and coolant and lubricating oil,please add if necessary.
G:Clean the iron box position filter to prevent clogging
H: please power off the switches,Power switch on the operation panel, the main circuit
switch of the machine tool, and the electric switch of the workshop,when you knock off.
3.11 Safety protection device

CNC210 Operating Manual
A:Front and behind protection and cooling protection.
B:exceed range limited device(According to the specific configuration)
C:Storage stroke limiting device(NC software)
3.12 The work before repair
Warning:
A: Without permission to do any maintenance work.
B:Replacement parts, vulnerable parts should be arranged advanced.
C:Use right maintenance methods.
Attention:
A:Read carefully and fully understand the safety precautions specified in the manual.
B:Read this manual carefully and understand the relevant principle and contains notes
3.13 Maintenance operation.
Danger :
A:The control power switch on the main circuit breaker or the operation panel shall not be
operated by the personnel who are not related to the maintenance work.In such a switch or other
appropriate places should be hung "no flipping a switch, maintenance!" the warning signs. And
such signs hung on the obvious and not easy to pick the location
B:When maintenance of machine tools, live operation is dangerous, please be careful. Try to
close the main circuit power supply operation
Danger:
A:Electrical maintenance personnel should be familiar with the corresponding business
personnel to play
B:The protective device and the interlock function of the machine can not be removed at
will.
C:Replacement of the electrical components should be strictly in accordance with the list
which provide by the manufacturers.
3.14 The works after maintenance.
Warning:
A:We should clean up and arrange the working environment ,in order to provide a good
working environment ,when we finish maintenance.
B:Remove the parts and clean out the waste oil, waste water should be placed away from the
machine according to the relevant regulations for processing
C:Maintenance personnel should check whether there is a security risk in the operation of the
machine after the completion of the maintenance
D:Record of maintenance and inspection data for future reference.
4 Lifting and Installing
4.1 transport and storage of machine

CNC210 Operating Manual
The machine adopts waterproof package, and the key parts coated with antirust oil,
packaging box using the anti vibration and impact measures, can guarantee in ℃to 55℃
temperature range safety transportation and storage. But the packaging box absolutely not allow
upside down or tilt more than 50, does not allow violent impact and vibration, so as to avoid
damage to the internal device.
4.2 Preparation before installation
4.2.1 Environments for the machine
Machine tools should not be placed in the following position:
A:Temperature has a significant change in the environment, such as direct light or near a
large heat source
B:high humidity place.
C:dust is too big, too dirty place.
D:the machine around have punch and other types of source place,If the machine installation
near the location of the source ,must dug anti vibration ditch or a similar measure of anti
vibration.
4.2.2 Environment demands of NC system.
temperature 5 degrees C ~40 C; relative humidity below 50%.
4.2.3 power interface
The power line connecting terminal is located on the outside of the machine tool electric
cabinet.
4.3 Install
4.3.1 lifting schematic diagram shown below

CNC210 Operating Manual
Attention: The best way to adjust the install position is the forklift.
Note: using the circular vibration pad iron (Random)
4.3.2 lifting requirements
The machine and the packing box is not recommended for lifting and adjusting the
installation position, it is best to use a forklift truck, if not to have to be suspended, please pay
attention to the following requirements.
A:Hoisting machine should be especially careful, avoid shock and impact especially the NC
system of the machine tool, control circuit plate, electrical components. Before lifting should
inspect each part of the machine is fixed, the machine tool tail stock should lock, the door to
appropriate fixed, no freely objects on the machine , some accessories and do not belong to the
objects of the machine itself should be removed.
B:Lifting boxes must be in accordance with the outer container lifting sign,steel wire shall
not serious squeeze packing box, not to have access to the machine, and minimize the packing
box subject to impact and vibration. Packing crates tilt shall not exceed 15 degrees. You are not
allowed to take the machine box on the objects with edges and corners or upside down, so as not
to affect the machine's accuracy. Using roller moving boxes on the slope, roll bar diameter shall
not be more than 70mm.
C:the first thing you should do is checking the external conditions of the machine tool,
according to the packing list and the tool is complete.
D:To keep up the machine or the packing box to keep balance in all directions,and should do
adjust when the machine hanging from the ground.
E:The included angle of the hoisting wire rope shall not be more than 60 degrees.
F:When the machine is operated, the operator should be coordinated.
G:when using the forklift ,we also need to follow the above considerations.Forklift should try
to slow down the speed, avoid fast start, stop the inertia in the runaway phenomenon. Driving
forklift personnel must be after the training of qualified drivers, driving the process should be
cautious, careful not to hurt the cooperative work, don't bump machine, so that the machine
excessive tilt.
4.4 Install of the machine
The method of install the machine will have a great effect to the function and
performance,improper installation will make the machine can not meet the requirements of the
processing accuracy, or can not maintain a long-term accuracy requirements.Must carefully read
the installation steps, and refer to the requirements of the installation of the machine in order to
make high precision machining.
4.4.1 Foundation
The position of the machine should be level, and then determine the installation space
according to the specified environment and the shape of the machine tool, and finish the job of the
foundation.

CNC210 Operating Manual
Covers an area including the machine tool itself covers an area of operation (see figure
below).
4.4.2 Temporary level adjustment
A:Lift or fork the machine, adjusting the pad iron bolts penetrated into the base of the anchor
bolt hole. Then the machine slowly down, and ensure uniform contact.
B:adjusting bolt,for coarse level of the machine.
4.5 Inspection of internal device connection
After finish adjust the temporary level of the machine, the mechanical and electrical system
of the machine shall be checked in accordance with the following provisions.
A:Cleaning. To rust, machine sliding surface and some pieces of metal surface has been
coated on the a layer of anti rust oil,they may pollution by the transport process. anti rust oil must
be clean before use, otherwise there is the danger of damage to the sliding surface. Clean cloth
dipped in oil cleaning, after cleaning we should lubricating the machine in accordance with the
requirements of lubrication.
B:Machine check.Check the machine parts if there have damaged, missing parts or
accessories, whether lubrication is good, hydraulic pipeline whether reliable connection.
C:Electrical system inspection should be carried out before the electrical connection is
switched on
D:After the machine is shut down for a long time, the lubricating system must be started to
make full lubrication.
4.7 The final adjust of the machine.
Re-adjusting the machine in the longitudinal and transverse,the adjust step and allow poor,
please refer to the attached to each machine accuracy test. With the scale of the level meter is
0.02mm.
4.8 Maintenance of initial installation
After the installation of the initial stage, due to the change of base and foundation of the
unstable because of factors, the level of machine will have obvious change, may greatly influence
the machine precision. On the other hand machine initial wear, as well as by the machine
pollution .Extremely easily cause changes in the performance of the machine . So, please
according to the following method for initial and maintenance:
A:Test: after the installation of machine ,the initial test should be very cautious. Test time is
about 1 hours, during the whole test period shall not be heavy load cutting and machining parts.
B:Check at the initial stage of the bed level: from machine installation date six months
should check the bed level, if found any abnormal phenomenon, should be promptly corrected, to
ensure that the requirements of the bed level accuracy is achieved.

CNC210 Operating Manual
C:6 months later, we can change the appropriate extension of the inspection period,
according to the machine ,until the change is stable to a certain extent, a year can be one to two
times the inspection.
5 Structure of machine
5.1 Machine layout
5.2 Machine transmission system and bearing distribution

CNC210 Operating Manual
1.main motor 2.Multi wedge belt 3.Z axis feed motor 4.Angular contact bearing 5.Deep
groove ball bearing 6. Spindle 7. Angular contact bearing 8.Longitudinal lead screw 9.Deep
groove ball bearing, 10, X axis feed motor 11.Synchronous belt 12.Angular contact bearing
2.13. Transverse lead screw 14.Deep groove ball bearing
Note: this drive system diagram, just roughly indicates the installation position of the
components. In the bearing distribution table, will be "close to the motor side", "far away
from the motor side" to explain the text.
Table 5-1 important bearing distribution table
Note: bearing models refer to the country's latest standards.
5.2.1 Main drive system
The machine main motor direct drive spindle motor, spindle box has cancelled the gear
transmission mechanism, simple structure, easy maintenance, high reliability. Transmission
through the main motor by DC brushless motor, DC stepless speed regulation. Spindle positive
inversion through the electrical system control, positive inversion has the same speed.
5.2.2 Work piece clamping mechanism
The configuration of the machine tool work piece clamping mechanism is three jaw chuck
and the power source is manual .
Warning :
All tooling and work piece clamping mechanism installed on the spindle must consider its
dynamic balance, otherwise it will greatly damage the spindle bearings, severely punish will cause
the body to scrap or damage the safety of the operator.
5.2.3 Feed drive system
4 one pairs of Angular contact bearing
(Near the motor)
7200C/DB
1 pairs
P5
7 Deep groove ball bearing
6007-Z
2
P5
9 one pairs of Angular contact bearing
7008C/DB
1 pairs
P4
11 Deep groove ball bearing(Far from the
motor)
6200-2Z
1
P5
14Angular contact bearing(Near the motor)
71900C/DB
1 pairs
P5
14 Deep groove ball bearing(Far from the
motor)
619/8-2Z
1
P5

CNC210 Operating Manual
X axis, Z axis feed motion is by two step through the coupling (synchronous belt and
synchronous belt wheel) connected with the ball screw nut pair then by the ball screw nut transfer
to the carriage or in a small trailer to achieve. Ball screw nut pair has been pre- tight, can achieve
high precision gap less transmission
5.2.4 photoelectric encoder drive system
The main spindle photoelectric encoder is driven by the synchronous belt wheel on the main
spindle to drive the synchronous belt wheel on the encoder seat.
5.2.5 tool post
The machine can be used in two rows tool carriers,and can be equipped with four electric
station.The electric post’s transposition locking directly from the electric post built-in motor drive,
direct control by the NC system.
5.2.6 tail seat
Tail stock is manual tail stock. Tail stock manually according to the eccentric principle
locking on the bed, with the hand cranking wheel moving screw the tail stock sleeve forward
backward; loosen eccentric locking mechanism, manual movement of the tail stock body sliding
back and forth.
When the work is carried out by using the tail seat, the locking sleeve is needed to be locked.
5.2.7 Lubricating System
5.2.7.1 the bearing of the spindle
The machine spindle bearings using 3 lithium grease lubrication, filling the number of 1/3 to
2/3, the machine tool factory has filled with grease.The bearings should be clean up every time
and add the same type of grease,when overhaul the machine.
5.2.7.2 The lubricating of the feeding system.
Feed system of the sliding interface using lubricating oil, consisting of a manual centralized
lubrication system and pipeline.And Z axis screw support bearing adopts 3 lithium grease
lubrication, we have add in the assembly. We can replacement according to the situation ,but the
first thing you should do is cleaning.The concentration oil lubricating tank should keep sufficient
oil , liquid level shall not be lower than the half of the calibration standard oil. Each shift before
starting machine, the first thing is to pull up hand pull the pump handle more than 3 times and
wait for after a few minutes before operating the machine. In order to ensure the lubrication points
to obtain the full lubrication.

CNC210 Operating Manual
Lubrication diagram
Note: before processing should clean up the rail surface, especially machining of cast iron or
to produce debris non-ferrous metal pieces should be often wipe the surface of the guide rail,
and to ensure adequate lubrication.
6 The operation and the safety of the machine.
6.1 The operation of the machine.
Starting the machine ,Operating procedures during the process, shutdown
procedures,operating methods and precautions, and the occurrence of errors in the operation
process of the machine, as well as the wrong operation and preventive measures, please see the
machine’s NC system specification.
6.2 Safety protection
A:Sheet metal protection
This machine use closed shield door. Closed door machine has the advantages of beautiful
appearance,when processing the iron ,cutting fluid does not fly out of guard,well protect the

CNC210 Operating Manual
operator and the environment ,the protective doors with transparent material, we can clearly see
the machine’s running situation when in processing.
B: The protection of X and Z axis.
X, Z axis adopts metal protection, can effectively block cutting fluid and scrap iron .
C:Z, X axis has a dead limit, it can avoid errors in the operation and programming data errors
caused by failure, etc.
D:Cooling liquid flows back to the water tank,filtered through the mesh filter cover, you can
filter out most of the iron filings. Inside the water tank is provided with separating strips, the
clastic which didn’t filtered will deposit at one end of the water tank, does not enter the pump.and
please clean the tank regularly.
E: fully closed design electrical cabinet,and it is easy to expansion for the reserved in the
electrical cabinet.
F: The protection of power failure or breakdown.
When machine encounter outside a sudden power failure or failure, the parts which in the
start state will automatically to the stop state, in the stop state will not automatically start.NC
system built in the battery, when the system fault always, storage processing program will not
lost.
H:Machine equip with alarm function and emergency stop button, can prevent all kinds of
sudden failure of the machine caused damage to the machine .NC system will give alarm
signal,we can find the fault location according to the system specification.
6.3 set the necessary safety warning signs
Despite adopting many safety measures, but there will still some potential, not obvious
danger, in order to prompt the operator, we set necessary safety warning signs, please don’t
violate the above tips.
7 Inspection and maintenance
7.1 Routine check
Order NO.
Check position
Check items
Remarks
1
The oil level of the
lubrication parts
1.Whether there is enough oil
2.Whether the oil is polluted obviously
Please add,if the oil is not enough,
replace the oil when polluted
2
Coolant level
1.Whether the coolant level is suitable
2.Whether the coolant is polluted
Whether Sediment has exceeded the height of the
bottom of the water tank.
Please add if necessary
Please replace if necessary
Please replace and clean up if
necessary.
3
Guideway
1.Whether the lubricating oil is enough
2.Whether the scraping board is damaged
4
ribbed belt
1.Whether the tension is appropriate
2.Is there a crack or scratch on the surface
5
The surface of the
bed and pipeline
1.Whether there is oil, water leakage
2.Whether they are unimpeded.

CNC210 Operating Manual
7.2 Regular check
Order NO.
Checking parts
Maintain items
time interval
1
Lubrication
system
Lubricating device
pipeline
Clean up the Version filter
Check for oil leakage, blockage and rupture.
Six months
2
Lubricating
system.
filter
Clean up the drain opening filter
Timely
3
Ribbed belt
Belt
Belt pulley
Check appearance and tightness
Clean up the pulley
Six months
4
Spindle motor
Sound, vibration,
temperature rise,
insulation resistance
Check the abnormal noise on the bearing and
any other parts.
Clean up the Belt pulley
Six months
5
the motor of X&Z
axis
Sound and
temperature rise
Check the abnormal noise and temperature
rise on the bearing.
1 month
6
chuck
chuck
Removing chuck and clean up the cutting
chips in the chuck
Three months
7
Control panel
Electrical device
and connection
screw
Check whether the electrical device has
peculiar smell, color change, whether the
contact surface have wear and screw loose
Dust and so on
Three months
8
The clearance of
X&Z axis
Check the clearance
Check it with dial gauge
Six months
9
foundation
The level of the bed
Check with gradienter and adjust the level of
the bed
Twelve months
7.3 lubrication and coolant
7.3.1 lubricating device
The items of check the lubricating device as below:
A: timely add the oil according to the provisions.
B: The lubricating parts’ check.To ensure that each of the lubricating parts can be well
lubricated, if the lubrication is not good somewhere, may be the lubrication pipeline blockage,
please remove the joint, clean or replace.
7.3.2 coolant device
The check items as below:
6
Moving parts
1.Whether there is noise and shake
2.Whether the shift is smooth and normal.
7
Operation panel
1.Whether the switch and the hand shank is
normal
2.Whether can display the alarm.
8
Safety device
Function is normal.
9
The external wire
cable
1.Whether there is break
2. there is no short circuit,whether the insulation
of wire is damaged.
10
Motor and other
rotating parts
1.Whether there have unusual noise and shake.
2.Whether there have abnormal fever.
11
Clean up
Clean the surface of the chuck, X, Z axis guard
surface
After working
12
Chuck lubrication
Lubricating around the chuck
Every weeks
13
accuracy of machine
Whether the accuracy of the machine in a permit
range.

CNC210 Operating Manual
A:whether the cooling pump is working properly ,no noise, flow and rated value.
B:whether the cooling liquid need to be replaced:when the nozzle out of the water reduction,
should check the level of the tank, timely replenishment. If it is too dirty, please timely
replacement.
Clean the sediment in the cooling water tank in time.
7.4 Adjust and maintain of the machine.
7.4.1 Headstock
Factory has adjusted the spindle bearing preload, within a short period of time it do not need
to be adjusted.After been used a period of time , the bearing clearance will increases, leading to
reduce the precision of rotary spindle, influences the machining accuracy of the products.In
normal use, spindle bearing temperature rise shall not exceed 40 degrees centigrade, temperature
shall not exceed 70 DEG.Otherwise, the bearing preload should be re adjust.if the accuracy of the
spindle can not achieve the accuracy requirement, also need to adjust bearing preload.For paired
angular contact ball bearings, they need to be removed and in accordance with the standard
method ,and determination under the predetermined pressure inside and outside the ring height
difference, and cooperate with each other, re installed onto the spindle box, preloaded with radial
locking screws, locking nut, and check the spindle of the precision, adjust bearing installation and
meets the requirement of accuracy, running 1 hour, meet the highest temperature and temperature
rise requirements.
Attention: The personal who adjust of spindle bearing shall have the professional and
technical qualifications .Adjustment should avoid pollution bearing. Very fine dust and impurities
will cause bearing excessive wear. The series of machine spindle bearing box have two kinds of
position, front and rear ,please pay attention while adjusting.
7.4.2 Adjustment of multi wedge belt
If the tension of the belt is greater than the allowable value, it may shorten the belt and the
main shaft bearing life. Instead, the tension is too small, there is not enough friction force to
transfer the amount of power.
The first belt tightness inspection should be in 3 months and then every 6 months.
Please see the below chart, Pressing belt by hand in the direction perpendicular to the belt,
the force must be in the middle position of belt wheel.
PK between 15-22N, H in 16 mm or so, if it is too large or too small, it will need to be
adjusted.
Release motor mounting plate and mounting screws, adjust the motor mounting plate, you
can adjust the tightness of the belt, while please attention that the belt and any other parts can not
be touched.
7.4.3 The adjust of lead screw.
The ball screw and drive motor Z axis of the machine using direct coupling, screw
positioning using near the end of the motor positioning, only need to adjust the positioning end
bearing elastic.
7.4.4 the adjust of the clearance for the different planker (adjust the clearance of guide way)

CNC210 Operating Manual
Between small carriage and the carriage, carriage and bed ,the sliding surface are used angle
plug iron, the plug iron inclination to 1:100. Inclined plane with the surface after distribution
scraping, and ensure good contact, when the gap is bigger, you can use the screws at the ends of
the gradual adjustment of the position of the plug iron to adjust the size of the gap. After
adjustment the ends of the two screws should contact with the plug iron, in order to ensure the
plug iron rigid.Adjustment should be in a moderate gap, not only to meet the accuracy
requirements of the machine tool, see precision test list , but also flexible sliding. Friction is too
large, although the detection accuracy is good, but it will lead to wear too fast.
7.5 Common failure and cause
7.5.1 coolant can not flow out
A:whether operating panel on the coolant switch is set to normal; M instructions are wrong.
B:whether the cooling pump suction entrance is fully inserted into the coolant
C:whether the chip tray filter and pump suction filter is blocked.
D:whether the coolant pump motor is working.
E:whether the cooling pump motor protection device is disengaged in the control circuit
board.
7.5.2 spindle didn’t work.
A:M instructions are correct.
B:Electrical components - main motor and control circuit board is normal
C:If there is urgent stop alarm.
7.5.3 Spindle box abnormal temperature rise.
The main chuck bearing preload setting is not appropriate.
7.5.4 the zero point of X&Z disappear (this function needs to be ordered)
The zero point switch loosen.
7.5.5 Repeated positioning accuracy is not good.
A:Iron adjustment is not appropriate.
B:The rail lubrication is not suitable.
C:The coupling loose
7.5.6 machine notwork
A:NC device display alarm signal.
B:part of the machine may injured.
7.5.7 The work piece can not be clamped
A: three jaws didn’t work at the same time.
B:the jaws seized by other things.
C:the lubricating of the jaws are not good.
D:the three jaw chuck may damaged.
7.5.8 Appear tamper in fine machining.
Processing disc type :spindle disc centering is not suitable.
Processing axle type:tail stock centering is not suitable
The guide way gap is too large.
7.5.9Tail sleeve does not move
Table of contents
Other WMT Lathe manuals