2. Installation
Install:
2.1 Ready tools and cables. Right cables are recommended. Ensuring
that the current density <4mm², which is conductive to reducing the
line voltage drop. Recommended: 20A with 6mm² cable. Check weather
the installation sites compliance with the relevant safety requirements.
Please avoid using or installing the controller in damp, dusty places or
places with flammable, explosive and corrosive gases. .
2.2 Install the controller into a fixed vertical plane. In order to ensure
good ventilation and heat dissipation, please keep the instance over 10cm
around the inverter and also between the backboard of the inverter and the wall.
2.3 To connect the controller and the battery by cables with right
polarity. The battery indicator light on the controller will be on if successfully
connected, otherwise, to check and reconnect
2.4 To connect the solar panel and the controller by cables with right polarity. If there is sunshine, the battery indicator light will be on in a
circular manner to indicate right connection, otherwise, to check and reconnect.
2.5 To connect your load and the cables with right polarity and then connect with the load output port of the controller. Pay special attention to
+ - polarity to avoid reversed connection, otherwise, your load may be damaged.
Demolition: In case of any accident, please disconnect the solar panel, battery and load with controller in order.
Note:Reversed battery polarity will not damage the controller, but you may bear security risks on your load equipments.