Installation and Operating Instructions
GB

2 Installation and Operating Instructions
ABS lifting station Nirolift & Sanisett
ABS reserves the right to alter specications due to technical developments
Contents
1 General................................................................................................................................................... 3
1.1 Application areas..................................................................................................................................... 3
1.2 Installation example and dimensions. ..................................................................................................... 3
1.3 Commentary on the legal regulations covering the use of lifting stations for the pumping of faecal free
efuent. ................................................................................................................................................... 5
1.4 Description .............................................................................................................................................. 5
2 Safety ..................................................................................................................................................... 5
3 Transport................................................................................................................................................ 5
4 Set-up and Installation.......................................................................................................................... 6
4.1 Installation of the collection tank ............................................................................................................. 6
4.2 Installation of the submersible pump....................................................................................................... 6
4.3 Opening of the collection tank inlet ports ................................................................................................ 7
4.4 Discharge line ......................................................................................................................................... 7
4.5 Mounting of the upper tting.................................................................................................................... 7
4.6 Location of power supply cable and oat switch ..................................................................................... 7
4.7 Level control............................................................................................................................................ 8
4.8 Installation of the control unit .................................................................................................................. 8
5 Commissioning ..................................................................................................................................... 8
6 Maintenance .......................................................................................................................................... 9
6.1 Commentary on maintenance of lifting stations in accordance with EN 12056 ...................................... 9
6.2 General maintenance hints ..................................................................................................................... 9
ABS lifting station Nirolift & Sanisett

Installation and Operating Instructions 3
ABS lifting station Nirolift & Sanisett
1 General
1.1 Application areas
Synthetic-prefabricated, corrosion resistant sump for ABS submersible pumps designed as single pumping
station for automatic pumping of wastewater and sewage in accordance with DIN/EN 12056 from locations and
areas below the backwash level.
m These lifting stations may not be used for the collection or pumping of ammable or corrosive liquids.
Efuent containing grease, petrol, or oil should only be brought to the lifting station via a separation
device.
1.2 Installation example and dimensions.
1061-00
Figure 1 Nirolift installation example and dimensions

4 Installation and Operating Instructions
ABS lifting station Nirolift & Sanisett
1062-00
Figure 2 Sanisett installation example and dimensions
1063-00
1064-00
Figure 3 Opening connection ports Figure 4 Sanisett oat switch installation
1065-00
1066-00
Figure 5 Mounting of upper tting Figure 6 Sanisett above ground lid

Installation and Operating Instructions 5
ABS lifting station Nirolift & SanisettABS lifting station Nirolift & Sanisett
1.3 Commentary on the legal regulations covering the use of lifting stations for the
pumping of faecal free efuent.
Automatically operated lifting stations are prescribed if:
the water level in the odour lock of the efuent source lies below the sewer backwash level.
rainwater gullies are present where the upper edge of the inlet grid lies below the sewer backwash level.
The sewer backwash level is the maximum possible water level in the public sewer network. Information on this
can be obtained from your local authority. If the backwash level has not been xed by the local authority, then
the surface level of the roadway at the connection point is taken to be the level.
The regulations also require that all waste-water which can cause offensive odours must be collected in closed,
odour-tight, and free-standing collection tanks.
The collection tanks must be vented by vent pipes which are brought above roof level.
ATTENTION The regulations of DIN 1986/100 EN 12050 and 12056 should be observed!
1.4 Description
The waste-water lifting stations of the Nirolift/Sanisett consist of a synthetic collection tank which is waterproof
in according with DIN/EN 12050-2, together with a cover plate with odour preventing lter and lockable oor
inlet.
The Sanisett is also supplied with a junction piece for the discharge line and a bracket for the level control.
The collection tank is supplied as standard with a number of closed off inlet ports. The inlet ports DN 100
Nirolift and DN 100/150 Sanisett can be opened as required (See Figure 3).
The waste water entering via the inlet ports is collected in the collection tank. When a preset liquid level is
reached then the Nirolift/Sanisett with one submersible pump is started up either by means of the oat switch
tted to the pump itself, or connected into the control panel, and is switched off again when the tank is emptied.
NOTE In the case of twin units installed in accordance with DIN/EN 12056, one submersible
pump must be capable of pumping all the efuent. The second pump is only a stand-
by unit.
2 Safety
The general and specic health and safety hints are described in detail in the separate booklet Safety Hints. If
anything is not clear or you have any questions as to safety make certain to contact the manufacturer ABS.
3 Transport
m During transport the unit should not be dropped or thrown.
-
-

6 Installation and Operating Instructions
ABS lifting station Nirolift & Sanisett
4 Set-up and Installation
Installation and dimensions (mm) of the Nirolift/Sanisett (Figure 1-6)
1 Synthetic tank 12 Cable inlet, odour-tight
2Waste-water pump Robusta (not supplied with tank
must be ordered separately)
13 Socket
3Bend (Accessory) 14 Concrete
4Upper tting (adjustable 360°) 15 Screed
5Cover plate with oor run-off and odour lock (only
suitable for foot trafc).
16 Floor tiles
6 Two inlet ports DN 100 (Nirolift) 100/150 (Sanisett) 17 Motor connection cable
7 Discharge line for connection P.V.C pipe 40 mm
(Nirolift), 50 mm (Sanisett)
18 Branch pipe (T-piece)
8Seal to nished oor 1) Anti-siphon loop
9 Discharge line. --- Approximate excavation dimensions
10 Shut-off valve (Accessory) * Cable ties
11 Vent/cable pipe DN 70, lead to above roof level ** Installation cover (on completion replaced by Pos. 5)
4.1 Installation of the collection tank
Set the collection tank on a bed of sand in the prepared opening of dimensions approximately 600x600x750mm
Nirolift and 1100x900x850 mm Sanisett in a frost free area and ensure that it is horizontal in all directions.
Place the tank in such a manner that the vent openings are in line with the chosen pipe directions.
If for reasons of the progress of construction work it is impossible to install the venting and pressure pipes
before pouring of the concrete one has to use a polystyrene core between the tank and the intended wall to
allow an assembly of the pipes later.
NOTE During concreting, the collection tank should be prevented from oating upwards
and should also be closed off with the plastic cover. This will avoid the danger that
the edge of the tank could be pressed inwards.
If there is a danger of pressure arising due to ground water, then the concrete surround of the collection tank
must be laid at the same time as the cellar oor, and should be closed off tightly on all sides (including under
the tank). The pipes must also be laid in the concrete.
If there is no danger of ground water pressure then a gravel bed and cementing in of the upper portion of the
collection tank is adequate
4.2 Installation of the submersible pump
The Nirolift has been designed for tting of submersible pumps from the Robusta, Coronada or
MF 054-334 series.
The Sanisett has been designed for tting of submersible pumps from the Robusta, Coronada or MF or
Piranha 08/09 series.
A suitable installation Kit should be chosen depending on the type of pump selected.
NOTE The connection or junction piece is already tted in the Nirolift or Sanisett collection
tank.
The tting of the submersible pumps is given in the leaet supplied with the installation kit.

Installation and Operating Instructions 7
ABS lifting station Nirolift & SanisettABS lifting station Nirolift & Sanisett
4.3 Opening of the collection tank inlet ports
Only open inlet ports that are to be used. Only saw off as little as possible so that as much neck as possible is
left for the plug connection. (Note the notch on the port neck).
File down sharp edge inside and outside.
4.4 Discharge line
The discharge line must be installed in compliance with the relevant regulations.
DIN 1986/100 and EN 12056 applies in particular to the following:
The discharge line should be tted with a backwash loop (180° bend) located above the backwash level and
should then ow by gravity into the collection line or sewer.
The discharge line should not be connected to a down pipe.
No other inows or discharge lines should be connected to this discharge line.
ATTENTION The discharge line should be installed so that it is not affected by frost.
The vent line is connected by means of a push-on sleeve to the vertical outlet at the top of the collection tank.
It should be of constant cross-section (min. DN 70) and should have a continuous rise to above roof level.
4.5 Mounting of the upper tting
Insert the white plastic installation cover into the frame of the upper tting. The cover is only suitable for
foot trafc (See Figure 5).
Adjust the upper tting in the tank opening until the edge of the rim is level with the nished oor. The rim
should also be parallel with the wall or oor tiles.
When installation is complete remove the installation cover and insert the cover with siphon into the frame.
This cover is only suitable for foot trafc.
Height adjustments up to 130 mm is possible by pushing in or pushing out the upper tting. It is possible to
increase the depth at which the collection tank is installed by the use of one sump extension piece. These
extend the sump by 150 mm.
ATTENTION A maximum of 1 sump extension piece may be tted.
4.6 Location of power supply cable and oat switch
The connection cable for the pump is fed through the cable pipe and brought into the room where the power
supply is located by means of a branch pipe (T-piece). The connection cable is fed through the slot in the cable
inlet and the cable inlet itself is pushed rmly into the branch pipe.
NOTE In the case of twin units the connection cables for the oat switches should be laid in
a similar manner to the pump power cable.
Branch pipe (T-piece)
Cable inlet
Vent line
Motor connection cable
1.
2.
3.
4.
1067-00
Figure 7 Cable inlet
-
-
-
1.
2.
3.

8 Installation and Operating Instructions
ABS lifting station Nirolift & Sanisett
4.7 Level control
The oat switches required for the twin unit Sanisett should be tted into the collection tank at the correct level
setting. (See Figure 4)
NOTE Press the oat switch cable into the plastic swivel in the holding bracket at distance
of 15 mm between the oat switch housing and swivel. The Float must point away
from the wall.
When oat switches are installed, the Robusta pump(s) should be set to ”Hand” operation
The connection lines for the oat switches should be connected in accordance with their designation Level 1 /
Level 2 to the control panel in accordance with the circuit diagram by a qualied person.
4.8 Installation of the control unit
ATTENTION The control unit should be tted above possible ood level in a well ventilated room
and in an easily accessible position. Protection Class of the control unit IP 54.
The control unit should be secured at all xing points. The xing holes are accessible after unscrewing the
lower housing cover.
ATTENTION Do not drill through the housing of the control unit itself.
NOTE A number of different control box models exist. Please check the wiring diagram/
instruction manual in the control box.
5 Commissioning
m The safety hints in the previous sections must be observed!
Before commissioning the unit should be checked and a functional test carried out. Particular attention should
be paid to the following:
Have the electrical connections been carried out in accordance with regulations?
Is the motor overload switch correctly set?
Have the power and control circuit cables been correctly tted?
Was the sump cleaned out?
Have the inow and outows of the pump station been cleaned and checked?
Is the direction of rotation correct - even if run via an emergency generator?
Are the level controls functioning correctly?
Are the required gates valves (where tted) open?
Do the non-return valves (where tted) function easily?
ATTENTION Before commissioning the collection tank should be cleaned of any large particles
and lled with water. After commissioning the lifting unit is normally operated with
the selector switch in position “Auto”.
-
-
-
-
-
-
-
-
-

Installation and Operating Instructions 9
ABS lifting station Nirolift & SanisettABS lifting station Nirolift & Sanisett
6 Maintenance
c Before commencing any maintenance work the unit should be completely disconnected from the
mains by a qualied person and care should be taken that it cannot be inadvertently switched back on.
m When carrying out any repair or maintenance work, the safety regulations covering work in enclosed
areas of sewage installations as well as good general technical pratices should be followed.
NOTE The maintenance hints given here are not designed for “do-it-yourself” repairs as
special technical knowledge is required.
NOTE A maintenance contract with our works service department will guarantee you the
best technical service under all circumstances.
6.1 Commentary on maintenance of lifting stations in accordance with EN 12056
It is recommended that the lifting station be inspected monthly and its function checked.
In accordance with EN regulations, the lifting station should be maintained by a qualied person at the following
intervals:
in commercial premises - every three months.
in apartment blocks - every six months.
in a single family home - once a year.
In addition we recommend that a maintenance contract be taken out with a qualied company.
6.2 General maintenance hints
ABS submersible pumps are reliable quality products each being subjected to careful nal inspection.
Lubricated-for-life ball bearings together with monitoring devices ensure optimum pump reliability provided that
the pump has been connected and operated in accordance with the operating instructions.
Should, nevertheless, a malfunction occur, do not improvise but ask your ABS customer service department for
assistance.
This applies particularly if the unit is continually switched off by the current overload in the control panel, by the
thermal sensors of the thermo-control system or by the seal monitoring system (DI).
Regular inspection and care is recommended to ensure a long service life.
NOTE The ABS service organisation would be pleased to advise you on any applications
you may have and to assist you in solving your pumping problems.
NOTE The ABS warranty conditions are only valid provided that any repair work has been
carried out in ABS approved workshop and where original ABS spare parts have
been used.
-
-
-

ABS Production Wexford Ltd., Clonard Road, Wexford, Ireland
Tel. +353 53 91 63 200 Fax +353 53 91 42335. www.absgroup.com
This manual suits for next models
1
Table of contents
Other ABS Water Pump manuals
Popular Water Pump manuals by other brands

BLACKMER
BLACKMER EBSRAY RC20 Installation, operation and maintenance instructions

Bosch
Bosch VP44 instruction sheet

Pompetravaini
Pompetravaini TRH Series operating manual

Goulds Pumps
Goulds Pumps 5500 Installation, operation and maintenance manual

Aspen
Aspen ALARM manual

Seko
Seko TEKNA EVO TPG installation manual

Graco
Graco G3 Pro instructions

STM
STM DPA25090 instruction manual

Pfeiffer Vacuum
Pfeiffer Vacuum MVP 006-4 operating instructions

GORMAN-RUPP PUMPS
GORMAN-RUPP PUMPS SF6C Installation, operation and maintenance manual

JOHN BLUE
JOHN BLUE CS-155RG Installation and operation manual

EasyPro
EasyPro TH Series Instructions for operation