3
ART 679 Rev 1
• Filter screen with 160µm mesh - protection of the system debris with easy access for
cleaning.
4. Valve Installation
• Albion Valves (UK) Ltd recommend that the installer adheres to the installation
requirementsasspeciedbytheWaterSupplyWaterFittingsRegulations1999.
• ConsiderationshouldalsobegiventoBSEN806-2(Specicationsforinstallationsinside
buildings conveying water for human consumption).
• ART 679 should be sited to ensure ease of access, for both use and maintenance.
• It is the responsibility of the installer to ensure the valve is suitable for service conditions
e.g., temperature, pressure, and service media.
• Consideration shold always be given to galvanic corrosion during installation.
• It is the responsibility of the installer to ensure that the valve, and adjoining pipework is
suitably supported to avoid any undue stresses being applied to the valve.
• Suitable sealing materials should be used during installation.
• Do not clean any parts of the valve with harsh chemicals that may cause damage.
• ART 679 is factory-set to 3 bar outlet pressure (for SP version).
• ART 679 must be installed in the pipeline without stress. Make sure that the correct seals
aretted,andonlysuitabletoolsareused.
• Itisadvisabletohaveanuninterruptedlengthof5xnominalpipediameterbothbefore
andafterthevalvetoensurelaminarowatboththeinletandoutletofthevalve.This
shouldbeincreasedto10xupstreamwheninstalledimmediatelyfollowingasystem
pump.
• Thepipelinemustbecarefullyushedthroughbeforethepressurereducerisinstalled.
This ensures that any impurities being carried along by the medium will not be trapped in
the valve as these may have a detrimental affect on the valve.
• The pressure gauge, positioned on the outlet side of the valve, enables the outlet pressure
to be validated and is screwed to the threads and sealed by means of a suitable sealing
tape.
• ART 679 can be installed in any given orientation.
• Aowvelocityofbetween1m/sand2m/sshouldbeadheredtoatalltimestoavoidthe
risk of cavitation and wear on the seat.
• Thedirectionofowmustmatchthearrowonthehousing.
• Albion Valves (UK) Ltd recommend that ‘shut-off’ valves are installed immediately before
and after pressure reducing valves.
Attention!
Before the pressure reducer is commissioned, it must be ensured that the two
pressure gauge connections on the housing are sealed by means of pressure
gauges or sealing plugs.