Quick Reference Manual Rel. 4.4, 12/2018, en-GB-DE (1)
JD00000 10-EN
with standard frames 50mm
S19
S25
S59
S75
S79
with frames for roof integration
S79 sol
For the aleo modules
with standard frame 35mm
P19
INSTALLATION
MANUAL
with standard frames 42mm
X59
X79

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 2/21
1 This manual in other languages 2 Product support
2.1 Detailed information
In addition to this Quick Reference Manual, aleo solar also
provides further information on its website.
2.2 Contact
aleo solar GmbH
Marius-Eriksen-Straße 1
17291 Prenzlau
Germany
T +49 (0)3984 8328-0
F +49 (0)3984 8328-115
E info@aleo-solar.com
W www.aleo-solar.com
2.3 Copyright
© 2018 aleo solar GmbH
This Quick Reference Manual is protected by copyright. All
rights reserved. Copying, reproduction, translation, or con-
version to any type of electronic media or machine readable
form, in its entirety or parts, is not permitted. An exception
will be made for a backup copy for your own use.
aleo solar reserves the right to change this document with-
hout prior notice.
aleo® and aleo solar® are registered, protected trademarks
of aleo solar GmbH.
Deutsch
(de-DE)
Wenn Sie diese Kurzanleitung in deut-
scher Sprache benötigen, wenden Sie
sich bitte an aleo solar, siehe Kap. 2.2.
English
(en-GB)
If you require this quick reference manu-
al in English, please contact aleo solar,
see chap. 2.2.
Français
(fr-FR)
Pour avoir cette notice d’installation en
Français contactez aleo solar (voir
chapitre 2.2).
Italiano
(it-IT)
Ove necessitaste delle seguenti istru-
zioni d’uso in lingua italiana, vogliate
gentilmente rivolgervi a aleo solar, vedi
cap 2.2.
Nederlands
(Benelux)
(nl-BE)
Wenst u deze handleiding in het Neder-
lands te ontvangen, neem dan contact
op met aleo solar zie hoofdstuk 2.2.
Ελληνικ
(el-GR)
Εάν χρειάζεστε αυτό το εγχειρίδιο στα
Αγγλικά, παρακαλώ επικοινωνήστε ε την
aleo solar, βλ. κεφάλαιο 2.2.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 3/21
3 Table of content
1 This manual in other languages . . . . . . . . . . . 2
2 Product support . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.1 Detailed instructions . . . . . . . . . . . . . . . . . . 2
2.2 Contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.3 Copyright . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
4 Explanation of safety guidelines . . . . . . . . . . . . 4
4.1 Warnings and notes in this manual . . . . . . . . 4
4.2 Notes on modules . . . . . . . . . . . . . . . . . . . . . . . . . 4
5 About this manual. . . . . . . . . . . . . . . . . . . . . . . . 4
5.1 Detailed information for installers and
planners . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
6 Handling aleo modules . . . . . . . . . . . . . . . . . . . 4
6.1 Intended use . . . . . . . . . . . . . . . . . . . . . . . . . . 4
6.2 Personal protection . . . . . . . . . . . . . . . . . . . . 5
7 Preparing for installation . . . . . . . . . . . . . . . . . 6
7.1 Handling aleo modules. . . . . . . . . . . . . . . . . 6
7.2 Safety precautions . . . . . . . . . . . . . . . . . . . . 6
8 Mechanical Installation . . . . . . . . . . . . . . . . . . . 7
8.1 Mounting orientation for modules . . . . . . . . 7
8.2 Safety precautions . . . . . . . . . . . . . . . . . . . . 7
8.3 Improper mounting . . . . . . . . . . . . . . . . . . . 7
8.4 Intervals . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
8.5 Avoiding seals . . . . . . . . . . . . . . . . . . . . . . . 8
8.6 Clearance under the modules . . . . . . . . . . . 8
8.7 Shadowing. . . . . . . . . . . . . . . . . . . . . . . . . . . .8
9 Electrical installation . . . . . . . . . . . . . . . . . . . . . 9
9.1 Connectors. . . . . . . . . . . . . . . . . . . . . . . . . . 9
9.2 Laying the string cables . . . . . . . . . . . . . . . . 9
9.3 Potential equalisation (earthing) of
module frames . . . . . . . . . . . . . . . . . . . . . . .10
9.4 Lightning protection . . . . . . . . . . . . . . . . . . 10
9.5 Parallel and serial connection . . . . . . . . . . . . 10
10 Details of mechanical mounting . . . . . . . . . .10
10.1 Aligning the mounting profiles . . . . . . . . . .10
10.2 Clamp mounting for modules with
standard frames. . . . . . . . . . . . . . . . . . . . . .10
10.3 Clamp mounting for modules with
Solrif® frames . . . . . . . . . . . . . . . . . . . . . . 11
10.4 Screw mounting . . . . . . . . . . . . . . . . . . . . . 11
10.5 Insertion mounting. . . . . . . . . . . . . . . . . . . 11
10.6 Load levels . . . . . . . . . . . . . . . . . . . . . . . . . 12
10.7 Key to symbols . . . . . . . . . . . . . . . . . . . . . . 12
10.8 Mounting drawings for modules with
standard frames. . . . . . . . . . . . . . . . . . . . . . 13
11 For operators: maintenance . . . . . . . . . . . . . 18
11.1 Inspections . . . . . . . . . . . . . . . . . . . . . . . . . 18
11.2 Review. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
11.3 Details for the inspections . . . . . . . . . . . . . 18
11.4 Cleaning . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
11.5 Repairs . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
12 For operators: decommissioning . . . . . . . . . 20
12.1 Safety precautions . . . . . . . . . . . . . . . . . . . 20
12.2 Disposal . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
12.3 Returns . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
12.4 PV Cycle . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 4/21
5 About this manual
This Quick Reference Manual is release 4.5 with the issue
date 08/2018. The publication of this manual renders all
previous releases (older than release 4.5) of this manual
invalid.
aleo solar constantly strives to improve its products and
their documentation. Therefore, we advise you to use the
latest version of the manual at all times.
Hand over this Quick Reference Manual to the operator aer
installation and ensure you have confirmation of receipt.
5.1 Detailed information for installers and planners
5.1.1 Information on the aleo solar website
You can find the latest release of the Quick Reference Man-
ual and additional information on aleo solar’s website:
www.aleo-solar.com.
Always use the latest version for your modules if you find a
more recent release of the manual.
5.1.2 Information sources for operators
If you have any queries about the latest release, contact your
aleo solar specialist partner or aleo solar directly
(see Ch. 2.2: „Contact“).
6 Handling aleo modules
6.1 Intended use
6.1.1 Appropriate use
aleo modules are used for generating electrical power in
stationary, photovoltaic systems which are connected to
the grid. If you would like to use the modules for another
purpose, such as for charging an accumulator directly, you
may need additional components (e.g. string diodes).
aleo modules are suitable for installing near livestock farms
and coastal regions.
Observe all the applicable legislation, regulations, guidelines
and standards when installing and operating the modules.
6.1.2 Inappropriate use
NOTE
• Do not install aleo modules on vehicles and do not
use them in air, space or seafaring applications and
also not 2000m above sea level.
• Do not use aleo modules if they are exposed to con-
centrated sunlight or strong artificial light, or if they
could be immersed in water or other liquids or expo-
sed to vapour.
6.1.3 Product-specific information
Product-specific information (e.g. the data sheet) contains
details of a particular type of module.
Only use aleo modules for the intended purpose outlined in
the product-specific information.
4 Explanation of safety guidelines
This is the danger symbol. It is used in several ver-
sions in this manual to alert you to the potential risk
of personal injury.
4.1 Warnings and in this manual
The danger warnings are structured as follows:
Type and source of danger.
Possible consequences of non-observance.
• Measures or prohibitions to avoid the danger.
DANGER!
DANGER indicates an imminently dangerous
situation which inevitably leads to death or
serious injury if not avoided.
_______________________________________________
The information on warning and cautions is structured as
follows:
Type and source of danger. Possible
consequences of non-observance.
• Measures or prohibitions to avoid the danger.
WARNING!
• WARNING indicates a potentially dangerous situa-
tion which can lead to death or serious injury if not
avoided.
_______________________________________________
CAUTION!
• CAUTION indicates a potentially dangerous situation
which can lead to slight or semi-serious injury if not
avoided.
_______________________________________________
NOTE
NOTE indicates a potentially dangerous situation
which can cause material damage if not avoided.
4.2 Notes on modules
The following symbol is attached to the modules:
If this symbol also appears on a danger or warning
product label, it is warning you of the danger caused
by electric current or voltage which can lead to per
sonal injury if you fail to observe the instructions.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 5/21
Severe or fatal injuries from electric shock!
• If the circuit of your photovoltaic generator is
earthed, remove the earth before you carry out
electrical work on the generator.
_________________________________________________________________________
WARNING!
Contact with live parts due to unsuitable tools
or weather conditions. Risk of electric shock!
• Only use approved, insulated tools for maintenance
work on live parts.
• Work in dry conditions. Ensure that the electrical
connections of the solar module, the cables and the
tools, are dry.
_________________________________________________________________________
RECOMMENDATION
Work in pairs so that in an emergency one person is
able to help in the case of injury. This is because the
modules generate voltage as soon as they are expo-
sed to light. Therefore, parts of the system are
nearly always energised during the daytime.
6.2.2 Mechanical safety precautions
WARNING!
Glass can crack, break or splinter. Beware of
injury!
• Never step or sit on solar modules.
• Avoid knocking and bumping the surface,
the edges and corners of the glass panels.
________________________________________ _________________________________
WARNING!
Exposed live parts due to damaged glass. Risk of
electric shock!
• Only use modules with the insulation in perfect
condition.
________________________________________ _________________________________
CAUTION!
Sharp glass edges or flying glass splinters.
Beware of injury!
• Always use suitable protective equipment (e.g.
gloves and goggles).
• Be especially careful with the glass edges and
corners of laminates (frameless modules).
________________________________________ _________________________________
■ Insulating back sheet
WARNING!
Damaged insulating back sheet. Risk of electric
shock and burns!
• Avoid any contact with the back of the module with
sharp or pointed objects.
• Ensure that the back sheet remains undamaged.
_______________________________________________
This module is rated for use in application class A accor-
ding to iEC 61730. For the electrical data please refer to
the data sheet or the name plate.
Under normal conditions, solar modules are likely to
experience conditions that produce more current and/or
voltage than reported at standard test conditions.1
Accordingly, the values of ISC and VOC marked on the mo-
dules should be multiplied by a faktor of 1.25 when deter-
mining component voltage ratings, conductor ampacities,
fuse sizes, and size of controls connected to the PV output.
Data sheets may change without prior notice. If the infor-
mation in the data sheet differs from this manual, the data
sheet takes precedence
6.2 Personal protection
6.2.1 Electrical safety precautions
DANGER!
High DC voltages during storage, installation,
operation and maintenance.
Risk of fatal electric shock!
• aleo modules may only be installed by qualified
technicians with a high level of expertise.
________________________________________ _________________________________
DANGER!
Dangerous, high DC voltages generated even at
low levels of light, especially in a series
connection.
Risk of fatal electric shock!
• Never touch the electrical connections of a solar
module under any circumstances, not even if you
have disconnected the photovoltaic generator.
________________________________________ _________________________________
DANGER!
Electric arcs form when electrical connections
are made or disconnected incorrectly.
Severe or fatal injuries from electric shock or
severe injury from burns!
• Before you carry out any work on electrical compo
nents, disconnect the photovoltaic generator.
________________________________________ _________________________________
DANGER!
Contact with live parts due to defective insulation
or damaged/fallen off junction box covers.
Severe or fatal injuries from electric shock!
• Do not touch damaged parts with your bare hands.
• Use protective clothing and suitable, insulated tools.
________________________________________ _________________________________
DANGER!
High DC voltages, even when the photovoltaic
generator is disconnected if the generator is
earthed.
1 E.g. in the event of strong solar irradiation, low ambient temperature, and reections
from snow.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 6/21
7 Preparing for installation
7.1 Handling aleo modules
7.1.1 Storing modules
■ Framed modules
Modules in packaging units:
NOTE
• Store the aleo modules upright in the packaging
units. Make sure that each module has sufficient
support.
• Do not stack the packaging units. This could damage
the modules.
Individual modules:
NOTE
• Store individual aleo modules in an upright position
on wedges with suitable padding. Use adequate pad
ding between the individual modules.
• Avoid stacking individual modules, as well as the
pallets they rest on.
7.1.2 Unpacking modules
■ Framed modules
NOTE
• Using an underlay, incline the pallet (e.g. with a
beam, height approx. 10 cm for 5° inclination), so
that the opening on the front of the box is elevated.
The modules then lean back in the box which makes
it easier to remove them.
• Use an underlay for inclining which supports the
whole side of the pallet (e.g. a beam). This keeps
the modules supported in the box along their entire
width.
• Remove the module from this side only. Remove the
module with the help of another person, if possible.
• Observe the unpacking instructions on the module
box.
7.1.3 Checking modules
NOTE
• Before installation, check each aleo module forme-
chanical defects. Pay particular attention to possible
damage to glass panels and insulated back sheets.
• In addition, check the insulation on the cables,
connectors and junction boxes.
• If you discover any defects, report them to the
supplier or transport company immediately.
7.1.4 Transporting modules to the installation site
■ Framed modules
NOTE
• Always carry the aleo module with one other per
son. Take hold of the module on its long sides.
• When transporting individual modules, make sure
that you do not put any strain or pressure on the
junction box and cables.
7.2 Safety precautions
DANGER!
When installing on roofs or other elevated sites,
objects may fall down.
Severe or fatal injuries are possible!
• Block off the danger zone for people and animals
before beginning installation work. If possible,
remove all objects from the danger zone.
_______________________________________________
DANGER!
Electric arcs form when electrical connections
are made or disconnected incorrectly.
Severe or fatal injuries from electric shock or
severe injury from burns!
• Disconnect the photovoltaic generator before you
carry out any work on the electrical components of
the photovoltaic generator.
_______________________________________________
DANGER!
High DC voltages, even when the photovoltaic
generator is disconnected, if the generator is
earthed.
Severe or fatal injuries from electric shock!
• If the circuit of your photovoltaic generator is
earthed, remove the earth before carrying out
electrical work on the generator.
_______________________________________________
WARNING!
Exposed live parts on damaged modules.
Danger of electric shock!
• Only use components which are in perfect condition
for use in photovoltaic systems. Do not install solar
modules with visible damage to the glass panels,
the insulating back sheet or on the insulation of
electrical connections.
_______________________________________________

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 7/21
WARNING!
Contact with live parts due to unsuitable tools
or wet conditions. Danger of electric shock!
• Only use approved, insulated tools for installation or
maintenance work on live parts.
• Work in dry conditions. Make sure that the electrical
connections on the solar module, the cables used
for installation and the tools, are dry.
7.2.1 Health and safety
CAUTION!
Risk of slipping due to wind, rain, snow or ice.
Risk of injury due to falling or colliding with
objects!
• Avoid unfavourable weather conditions, such as
strong wind or rain.
• Also avoid working on the installation site in ice and
snow.
• Use the safety equipment required or recommended
by local regulations, such as hard hats, steel-capped
shoes with rubber soles, protective goggles, gloves
or fall-protection systems.
_______________________________________________
CAUTION!
Hot module parts in strong sunlight. Risk of
burning!
• Protect yourself from burning by wearing gloves and
suitable clothing.
_______________________________________________
8 Mechanical Installation
8.1 Mounting orientation for modules
8.1.1 Vertical (portrait) mounting
When mounting the module vertically, make sure that the
cables are facing towards the ground and the junction box
is facing upwards.
8.1.2 Horizontal (landscape) mounting
When mounting horizontally, make sure that the exit holes
for the cables on the module or the junction box are positi-
oned on the inside of the photovoltaic generator. Avoid the
lateral outer edges of the photovoltaic generator to minimi-
se the effect of ambient conditions, such as wind or rain.
8.1.3 Inclination
Incline the surface of the modules at an angle of at least
10° horizontally, so that precipitation can drain off which
supports the modules self-cleaning.
For optimum self-cleaning, we recommend an angle of at
least 15° horizontally.
Fig.1 Recommended position of the junction boxes for
horizontal mounting (facing the middle of the
generator)
8.2 Safety precautions
NOTE
• Do not drill any additional holes in aleo modules
or their frames.
8.3 Improper mounting
NOTE
• Do not attach the modules using nails. The
vibration created in the process can cause micro
fissures and loss of yield, and results in loss of
warranty rights.
• Do not attach the modules by welding. The
temperatures created in the process can cause
delamination, micro fissures and loss of yield, and
results in loss of warranty rights.
8.4 Intervals
8.4.1 Intervals between modules with standard frames
NOTE
• Leave a minimum clearance when mounting
modules. This prevents mechanical tension due to
thermal expansion.
•
When mounting at intervals
Leave a clearance of 3 mm or more between the
individual module frames.
• For
edge-to-edge mounting
Allow for an expansion joint of 20 mm aer a
maximum of 7 m.
• The recommended maximum clearance is 30 cm,
based on the modules‘ standard cable length.
aleo solar recommends mounting at intervals. Also note
the information from the mounting equipment vendor.
This could specify larger intervals.
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 7/19
WARNING!
Contact with live parts due to unsuitable tools
or wet conditions. Danger of electric shock!
• Only use approved, insulated tools for installation or
maintenance work on live parts.
• Work in dry conditions. Make sure that the electrical
connections on the solar module, the cables used
for installation and the tools, are dry.
7.2.1 Health and safety
CAUTION!
Risk of slipping due to wind, rain, snow or ice.
Risk of injury due to falling or colliding with
objects!
• Avoid unfavourable weather conditions, such as
strong wind or rain.
• Also avoid working on the installation site in ice and
snow.
• Use the safety equipment required or recommended
by local regulations, such as hard hats, steel-capped
shoes with rubber soles, protective goggles, gloves
or fall-protection systems.
CAUTION!
Hot module parts in strong sunlight. Risk of
burning!
• Protect yourself from burning by wearing gloves and
suitable clothing.
8 Mechanical Installation
8.1 Mounting orientation for modules
8.1.1 Vertical (portrait) mounting
When mounting the module vertically, make sure that the
exit holes for the cables on the module or its junction box are
facing towards the ground.
8.1.2 Horizontal (landscape) mounting
When mounting horizontally, make sure that the exit holes
for the cables on the module or the junction box are posi-
tioned on the inside of the photovoltaic generator. Avoid the
lateral outer edges of the photovoltaic generator to minimise
the effect of ambient conditions, such as wind or rain.
Fig.1 Recommended position of the junction boxes for
horizontal mounting (facing the middle of the gen-
erator)
8.2 Safety precautions
NOTE
• Do not drill any additional holes in aleo modules or
their frames.
8.3 Improper mounting
NOTE
• Do not attach the modules using nails. The vibration
created in the process can cause micro fissures and
loss of yield, and results in loss of warranty rights.
• Do not attach the modules by welding. The temper-
atures created in the process can cause delamina-
tion, micro fissures and loss of yield, and results in
loss of warranty rights.
8.4 Intervals
8.4.1 Intervals between modules with standard frames
NOTE
• Leave a minimum clearance when mounting mod-
ules. This prevents mechanical tension due to ther-
mal expansion.
•When mounting at intervals
Leave a clearance of 3 mm or more between the
individual module frames.
•For edge-to-edge mounting
Allow for an expansion joint of 20 mm after a
maximum of 7 m.
• The recommended maximum clearance is 30 cm,
based on the modules' standard cable length.
aleo solar recommends mounting at intervals. Also note the
information from the mounting equipment vendor. This could
specify larger intervals.
GID AS009b

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 8/21
8.4.2 Clearance under the modules
■ Minimum clearance
NOTE
• Rooop or freefield mounting
Ensure a clearance of at least 4 cm between the rear
edge of the frame and the mounting surface (e.g.
the roof tiles) for the rear ventilation ohe aleo
module.
• Roof-integrated mounting
Ensure an appropriate interval, for example, to the
trough of the mounting system. Also ensure ade-
quate ridge ventilation, for example, with a roof
ridge ventilator.
■ Maximum clearance
NOTE
• The largest permissible clearance is defined by
national standards. This is used to design the instal
lation on the assumed effects of wind and suction.
• The
actual maximum clearance of an installation is
determined by the sub-structure. Ensure that your
sub-structure adheres to the permissible
clearances.
8.5 Avoiding seals
NOTE
• Avoid the use of a seal between aleo modules and
their mounting surface.
• Dry and cool operation can have a positive effect
on the performance as well as the service life of an
aleo module.
• Also for roof-integrated mounting, ensure good
rear ventilation to minimise loss of output which
results from a higher module temperature. Ensure
adequate ridge ventilation, for example, with a
roof ridge ventilator.
8.6 Clearance under the modules
NOTE
• Keep the space behind the laminate free of any
objects. This prevents damage to the insulating
back sheet and the junction box.
• Ensure that sharp or conductive parts (e.g. screws
or nails) do not protrude into the space behind the
module.
• If possible, take measures to prevent foreign
objects (e.g. snow, ice, leaves, twigs, branches
from being able to get behind the module.
8.7 Shadowing
8.7.1 Avoidance of shadowing
NOTE
• Avoid shadowing of solar modules. This applies also
and especially for shadowing of small areas due to close
small objects like antennas or lightning protectors.
• If there is systematical shadowing in the course of the
day or year because of adjacent objects at the site and
you do not have any opportunity to affect the shado-
wing, then:
- take another site into consideration
- only plan with the non-shadowed parts of your site
when you configure your photovoltaic-generator
8.7.2 Effects of shadowing
NOTE
Even shadowing of a single module or solar cell can
appreciably affect the power output of your photovoltaic
plant.
If shadow falls on single solar modules of a photovoltaic
generator or on single solar cells of a solar module, the
shadowed parts generate less or no electrical power
anymore. This may affect the yield of the whole module
string and therefore the whole generator.
Furthermore, shadowing oen causes the solar cells to
consume the otherwise in the module generated electri-
cal power. This may cause warming of the shadowed cells
in comparison to the not shaded cells, which in extreme
cases can raise the risk of fire.
Constant or systematic shadowing can cause a serious
yield loss and may accelerate the aging process and
therefore causes power loss or failures of the photovol-
taic generator. Avoid shadowing e.g. caused by building
parts, depending on day time or season (esp. in winter) to
optimize the yield and durability of your plant.
8.7.3 Protective devices of the modules
Aleo modules are equipped with bypass-elements to limit
the temperature rising because of the internal power con-
sumption induced by shadowing to a non-critical grade and
thus protect the module. Avoid systematic shadowing also
because the bypass-elements are not suited for constant,
long lasting loads.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 9/21
9 Electrical installation
9.1 Connectors
WARNING!
Incompatible or unsuitable connectors can
overheat. Fire hazard!
• Only use connectors that are the same type and
from the same manufacturer.
• Avoid using different types of connectors or ones
from different manufacturers, even:
- if connecting is possible
- if the connectors have the same basic
designation (e.g. “MC4”) or
- if they are designated as “compatible”.
______________________________________________
You can find more details on this in the next two sections
9.1.1 Module connectors
The various module types can be fitted with the following
connectors:
• Original Multicontact®MC4 (with locking)
• PV-JM601 (with locking)
You can find the specific connectors in the module data
sheet.
9.1.2 Connector peculiarities
NOTE
• Original Multicontact® MC4 connectors
• Only plug original Multicontact®MC4
connectors into original Multicontact®MC4
connectors.2
• PV-JM601 connectors
• Only plug PV-JM601 connectors into PV-JM601
connectors.
9.1.3 Replacing the connectors
You can remove the connector on a module and replace it
with another connector, if necessary. If you want to use a
connector other than listed in Chapter 9.1.1, please con-
tact aleo ( see Ch. 2.2).You retain the manufacturing war-
ranty if you remove and mount with approved tools in the
proper way and according to the connector manufacturer‘s
instructions.
9.2 Laying the string cables
CAUTION!
Brittle fractures in junction boxes due to contact
with unsuitable connection cables: Risk of fire!
• Only use connection cables without plasticisers.
______________________________________________
2The original Multicontact® MC4 connectors are referred to as “MC4” in the data sheet.
NOTE
• Avoid any tensile and pressure loads on the
junction box when mounting.
• When mounting, avoid heavy tensile loads on any
connectors already plugged in.
NOTE
• Bend the cables from the connector at least 4 cm
aer they exit from the connector.
• Bend the cables from the junction box as well, at
least 4 cm aer they exit from the connector.
• This keeps the cables waterproof at the cable
outlet.
Observe the guidelines on laying the respective cables.
Lay all cables ensuring that:
• You adhere to the minimum bend radius (e.g.
5-fold cable diameter).
• You avoid laying near sharp corners and edges or
protect the cables accordingly.
• cables must not lay between module backside and
mounting system parts.
• You protect them from direct sunlight and
precipitation.
• You secure the cables with UV resistant cable clips4
or other suitable cable fasteners which protect the
cable insulation.
• Cables from module strings are laid as near to
each other as possible to minimise the effects of
being struck by lightning.
9.2.1 Weather protection
NOTE
• Lay the cables so that they exit the junction box
from below. This prevents water, which runs along
the cable, from collecting at the point where the
cables exit the junction box.
• For modules mounted horizontally, lay the cables
in a U-form away from the junction box.
• Modules mounted vertically do not usually need
any additional adjustments.
Fig.2 U-form cables at the junction box for a horizon-
tally mounted module
3Some countries specify a larger bend radius, e.g. 8-fold wire diameter in the USA (NEC
Codebook 2011).
4For attaching the cable clip, use a suitable tool which can fully tighten at a defined
low force. Avoid cable clips and tools which constrict or damage the cable insulation
when tightening.
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 9/19
9.2 Laying the string cables
CAUTION!
Brittle fractures in junction boxes due to contact
with unsuitable connection cables: Risk of fire!
• Only use connection cables without plasticisers.
NOTE
• Avoid any tensile and pressure loads on the junction
box when mounting.
• When mounting, avoid heavy tensile loads on any
connectors already plugged in.
NOTE
• Bend the cables from the connector at least 4 cm
after they exit from the connector.
• Bend the cables from the junction box as well, at
least 4 cm after they exit from the connector.
• This keeps the cables waterproof at the cable outlet.
Observe the guidelines on laying the respective cables. Lay
all cables ensuring that:
• You adhere to the minimum bend radius (e.g. 5-fold
cable diameter
2
),
• You avoid laying near sharp corners and edges or
protect the cables accordingly
• You protect them from direct sunlight and precipi-
tation
• You secure the cables with UV resistant cable clips
3
or other suitable cable fasteners which protect the
cable insulation,
• Cables from module strings are laid as near to each
other as possible to minimise the effects of being
struck by lightning
9.2.1 Weather protection
NOTE
• Lay the cables so that they exit the junction box from
below. This prevents water, which runs along the ca-
ble, from collecting at the point where the cables
exit the junction box.
• For modules mounted horizontally, lay the cables
in a U-form away from the junction box.
• Modules mounted vertically do not usually need
any additional adjustments.
Fig.2 U-form cables at the junction box for a horizontally
mounted module
Lay cables carefully to protect against damage from:
• Direct environmental factors, such as precipitation
• movement (e.g. from wind)
• Indirect environmental factors, e.g. snow or ice,
which slip down behind the modules, and
• Chaffing on the insulation due to the cable moving
(e.g. from wind or ice).
9.3 Potential equalisation (earthing) of module
frames
NOTE
• Local regulations may specify potential equalisation
(earthing).
• When earthing the module frame, establish a safe
electrical connection to the earth potential or
earthed sub-structure.
• Observe the requirements and recommendations
of the inverter manufacturer, as well as insurance
policies.
• The module frames are made of aluminium. When
mounting onto other materials, take suitable mea-
sures to prevent electric corrosion, e.g. by using a
coating.
NOTE
Potential equalization does not serve as lightning
protection. Lightning protection may be necessary
in addition to potential equalization.
2Some countries specify a larger bend radius, e.g. 8-fold wire diameter in the
USA (NEC Codebook 2011).
3For attaching the cable clip, use a suitable tool which can fully tighten at a de-
fined low force. Avoid cable clips and tools which constrict or damage the cable
insulation when tightening.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 10/21
9.5 Parallel and serial connection
PV modules of the same type can be connected in parallel.
The PV modules in this series are fundamentally designed
for series connection.
• Only use PV modules of the same type and output
for parallel connection. Take measures for over-
current protection (e.g. line fuses) if necessary. Never
exceed the specified reverse current loadability of
the PV modules. Maximum number of module strings
that are allowed to be switched in parallel: 2 (fuse
rating / (short-circuit current x1.25)+1)
• Make sure that only PV modules with the same
amperage (Impp) are interconnected for series con-
nection and make sure that the voltages of strings
connected in parallel are the same. Even at low tem-
peratures, never exceed the maximum permissible
system voltage of the PV modules. Maximum number
of PV modules that are allowed to be switched in
series: maximum system voltage / (open circuit
voltage x 1.25), with respect to the temperature
coefficient.
• Make sure that the number and connection of the
PV modules match the electrical values specified by
the devices connected to the photovoltaic system.
• Make sure that the polarity is correct.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another;
b: Profiles neither parallel nor perpendicular to the
module edges;
c: The profile ends for the sides of a module are not
connected.
10.2 Clamp mounting for modules with standard
frames
Lay cables carefully to protect against damage from:
• Direct environmental factors, such as precipitation
• movement (e.g. from wind)
• Indirect environmental factors, e.g. snow or ice,
which slip down behind the modules, and
• Chaffing on the insulation due to the cable
moving (e.g. from wind or ice).
9.3 Potential equalisation (earthing) of module
frames
NOTE
• Local regulations may specify potential
equalisation (earthing).
• When earthing the module frame, establish a safe
electrical connection to the earth potential or
earthed sub-structure.
• Observe the requirements and recommendations
of the inverter manufacturer, as well as insurance
policies.
• The module frames are made of aluminium. When
mounting onto other materials, take suitable
measures to prevent electric corrosion, e.g. by
using a coating.
NOTE
Potential equalization does not serve as lightning
protection. Lightning protection may be necessary
in addition to potential equalization.
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for
connecting the lightning rod with the lightning
protection. This ensures the safety and reliability
of the lightning protection as well as the
photovoltaic system.
• Do not under any circumstances include the
module frame or its earth as an active part of the
lightning protection (e.g. as a lightning arrestor).
_______________________________________________
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the
module frame and the supporting structure.
Page 10/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for connecting
the lightning rod with the lightning protection. This
ensures the safety and reliability of the lightning pro-
tection as well as the photovoltaic system.
• Do not under any circumstances include the module
frame or its earth as an active part of the lightning
protection (e.g. as a lightning arrestor).
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the mod-
ule frame and the supporting structure.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another; b: Profiles neither par-
allel nor perpendicular to the module edges; c: The profile
ends for the sides of a module are not connected.
10.2 Clamp mounting for modules with standard
frames
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 55Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides, b: Asymmetrical
clamping on the long sides (acceptable for certain load
levels), c: Symmetrical clamping on the short sides.
■ Impermissible arrangement
Fig.6 55Impermissible clamp arrangement for framed
modulesPermissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules
(1)a: Missing clamps, b, c: Clamping on both short and long
sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
d: Protruding clamps, e: Opposing clamps have different
distances to the module corners, f: Asymmetrical clamps on
the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
GID AS022b
a b c
GID AS023b
a b c
a b c
GID AS024a
GID AS025b
ab c
d e f
GID AS069b
Page 10/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for connecting
the lightning rod with the lightning protection. This
ensures the safety and reliability of the lightning pro-
tection as well as the photovoltaic system.
• Do not under any circumstances include the module
frame or its earth as an active part of the lightning
protection (e.g. as a lightning arrestor).
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the mod-
ule frame and the supporting structure.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another; b: Profiles neither par-
allel nor perpendicular to the module edges; c: The profile
ends for the sides of a module are not connected.
10.2 Clamp mounting for modules with standard
frames
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 55Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides, b: Asymmetrical
clamping on the long sides (acceptable for certain load
levels), c: Symmetrical clamping on the short sides.
■ Impermissible arrangement
Fig.6 55Impermissible clamp arrangement for framed
modulesPermissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules
(1)a: Missing clamps, b, c: Clamping on both short and long
sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
d: Protruding clamps, e: Opposing clamps have different
distances to the module corners, f: Asymmetrical clamps on
the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
GID AS022b
a b c
GID AS023b
a b c
a b c
GID AS024a
GID AS025b
ab c
d e f
GID AS069b
Page 10/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for connecting
the lightning rod with the lightning protection. This
ensures the safety and reliability of the lightning pro-
tection as well as the photovoltaic system.
• Do not under any circumstances include the module
frame or its earth as an active part of the lightning
protection (e.g. as a lightning arrestor).
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the mod-
ule frame and the supporting structure.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another; b: Profiles neither par-
allel nor perpendicular to the module edges; c: The profile
ends for the sides of a module are not connected.
10.2 Clamp mounting for modules with standard
frames
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 55Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides, b: Asymmetrical
clamping on the long sides (acceptable for certain load
levels), c: Symmetrical clamping on the short sides.
■ Impermissible arrangement
Fig.6 55Impermissible clamp arrangement for framed
modulesPermissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules
(1)a: Missing clamps, b, c: Clamping on both short and long
sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
d: Protruding clamps, e: Opposing clamps have different
distances to the module corners, f: Asymmetrical clamps on
the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
GID AS022b
a b c
GID AS023b
a b c
a b c
GID AS024a
GID AS025b
ab c
d e f
GID AS069b

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 11/21
Page 10/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for connecting
the lightning rod with the lightning protection. This
ensures the safety and reliability of the lightning pro-
tection as well as the photovoltaic system.
• Do not under any circumstances include the module
frame or its earth as an active part of the lightning
protection (e.g. as a lightning arrestor).
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the mod-
ule frame and the supporting structure.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another; b: Profiles neither par-
allel nor perpendicular to the module edges; c: The profile
ends for the sides of a module are not connected.
10.2 Clamp mounting for modules with standard
frames
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 55Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides, b: Asymmetrical
clamping on the long sides (acceptable for certain load
levels), c: Symmetrical clamping on the short sides.
■ Impermissible arrangement
Fig.6 55Impermissible clamp arrangement for framed
modulesPermissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules
(1)a: Missing clamps, b, c: Clamping on both short and long
sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
d: Protruding clamps, e: Opposing clamps have different
distances to the module corners, f: Asymmetrical clamps on
the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
GID AS022b
a b c
GID AS023b
a b c
a
b c
GID AS024a
GID AS025b
ab c
d e f
GID AS069b
Page 10/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for connecting
the lightning rod with the lightning protection. This
ensures the safety and reliability of the lightning pro-
tection as well as the photovoltaic system.
• Do not under any circumstances include the module
frame or its earth as an active part of the lightning
protection (e.g. as a lightning arrestor).
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the mod-
ule frame and the supporting structure.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another; b: Profiles neither par-
allel nor perpendicular to the module edges; c: The profile
ends for the sides of a module are not connected.
10.2 Clamp mounting for modules with standard
frames
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 55Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides, b: Asymmetrical
clamping on the long sides (acceptable for certain load
levels), c: Symmetrical clamping on the short sides.
■ Impermissible arrangement
Fig.6 55Impermissible clamp arrangement for framed
modulesPermissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules
(1)a: Missing clamps, b, c: Clamping on both short and long
sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
d: Protruding clamps, e: Opposing clamps have different
distances to the module corners, f: Asymmetrical clamps on
the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
GID AS022b
a b c
GID AS023b
a b c
a b c
GID AS024a
GID AS025b
ab c
d e f
GID AS069b
Page 10/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
9.4 Lightning protection
WARNING!
Absence of or inadequate lightning protection.
Risk of fire or electric shock!
• Leave the planning and installation of the external,
and if required internal, lightning protection to be
carried out by qualified technicians at all times.
• It is essential to integrate an arrestor for connecting
the lightning rod with the lightning protection. This
ensures the safety and reliability of the lightning pro-
tection as well as the photovoltaic system.
• Do not under any circumstances include the module
frame or its earth as an active part of the lightning
protection (e.g. as a lightning arrestor).
NOTE
If you earth the module frame, the only task of this
earth is the potential equalisation between the mod-
ule frame and the supporting structure.
10 Details of mechanical mounting
10.1 Aligning the mounting profiles
10.1.1 Permissible alignment
Fig.3 Permissible alignment of mounting profiles
a, b: Parallel profiles for mounting; c: Parallel, aligned
fingers of a mounting system.
10.1.2 Impermissible alignment
Fig.4 Impermissible alignment of mounting profiles
a: Profiles not parallel to one another; b: Profiles neither par-
allel nor perpendicular to the module edges; c: The profile
ends for the sides of a module are not connected.
10.2 Clamp mounting for modules with standard
frames
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 55Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides, b: Asymmetrical
clamping on the long sides (acceptable for certain load
levels), c: Symmetrical clamping on the short sides.
■ Impermissible arrangement
Fig.6 55Impermissible clamp arrangement for framed
modulesPermissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules
(1)a: Missing clamps, b, c: Clamping on both short and long
sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
d: Protruding clamps, e: Opposing clamps have different
distances to the module corners, f: Asymmetrical clamps on
the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
GID AS022b
a b c
GID AS023b
a b c
a b c
GID AS024a
GID AS025b
ab c
d e f
GID AS069b
10.2.1 Arranging the clamps
■ Permissible arrangement
Fig.5 Permissible clamp arrangement for framed
modules
a: Symmetrical clamping on the long sides,
b: Asymmetrical clamping on the long sides
(acceptable for certain load levels),
c: Symmetrical clamping on the short sides.
d: Clamping on both short and long sides.
■ Impermissible arrangement
Fig.6 Impermissible clamp arrangement for framed
modules Permissible clamp arrangement for
framed modules
Impermissible clamp arrangement for framed modules(1)
a: Missing clamps,
b: Clamping on both short and long sides.
Fig.7 Impermissible clamp arrangement for framed
modules (2)
c: Protruding clamps,
d: Opposing clamps have
different distances to the module corners,
e: Asymmetrical clamps on the short sides.
10.2.2 Clamp dimensions
Observe the following information for clamp lengths and
depths.
■ Clamp lengths and depths
Fig. 8 Definition of clamp length and depth for framed
modules
a: Clamp length, b: Clamp depth.
NOTE
• The required minimum length of a clamp (parallel
to the frame side) is 30 mm.
• The required minimum depth of a clamp
(perpendicular to the frame side) is 3 mm.
• aleo solar recommends a clamp depth of 5 mm.
• Depending on the ambient conditions (e.g. angle,
suction load or tolerances of the substructure) a
higher minimum area per clamp may be required.
• The clamps determine the actual clamp depth and
length.
• Observe the instructions of the clamp
manufacturer.
10.2.3 Tightening torque for clamp mounting
Tighten the screws on the clamp manually. If you use
an automatic screwdriver, then set a suitable maximum
tightening torque. You can find details for this in the
manufacturer‘s documentation for the substructure.
10.3 Clamp mounting for modules with Solrif®frames
NOTE
• Avoid clamp mounting for modules with Solrif®
frames. Only mount these modules with the Solrif®
mounting system.
• You can also contact the aleo solar branch in your
country. They will provide you with information on
mounting systems which are already in use on a
greater scale.
10.4 Screw mounting
10.4.1 Modules with standard frames
The aleo modules have the following mounting holes:
• either with a diameter of 9 mm or
• for gen2: long holes with a width of 9 mm and a
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 11/19
■ Clamp lengths and depths
Fig.8 Definition of clamp length and depth for framed
modules
a: Clamp length, b: Clamp depth.
NOTE
• The required minimum length of a clamp (parallel to
the frame side) is 30 mm.
• The required minimum depth of a clamp (perpen-
dicular to the frame side) is 3 mm.
• aleo solar recommends a clamp depth of 5 mm.
• Depending on the ambient conditions (e.g. angle,
suction load or tolerances of the substructure) a
higher minimum area per clamp may be required.
• The clamps determine the actual clamp depth and
length.
• Observe the instructions of the clamp manufacturer.
10.2.3 Tightening torque for clamp mounting
Tighten the screws on the clamp manually. If you use an au-
tomatic screwdriver, then set a suitable maximum tightening
torque. You can find details for this in the manufacturer's
documentation for the substructure.
10.3 Clamp mounting for modules with Solrif®
frames
NOTE
• Avoid clamp mounting for modules with Solrif®
frames. Only mount these modules with the Solrif®
mounting system.
• You can also contact the aleo solar branch in your
country. They will provide you with information on
mounting systems which are already in use on a
greater scale.
10.4 Screw mounting
10.4.1 Modules with standard frames
The aleo modules have the following mounting holes:
• either with a diameter of 9 mm or
• for gen2: long holes with a width of 9 mm and a
length of 22.5 mm.4
10.4.2 Modules with Solrif® frames
NOTE
Avoid screw mounting for Solrif® modules. Only
mount Solrif® modules with the Solrif® mounting
system.
10.4.3 Tightening torque for screw mounting
For M8 stainless steel screws, use a maximum torque of
24 Nm.5
10.5 Insertion mounting
10.5.1 Modules with standard frames
Observe the manufacturer's instructions for the mounting
system. Use the earthing holes for the potential equalisation.
Although edge-to-edge mounting is possible (see also
Ch. 8.4.1: „Intervals between modules with standard
frames“), aleo solar recommends mounting at intervals.
10.5.2 Modules with Solrif® frames
Only mount modules with Solrif® frames with the Solrif®
mounting system.
10.6 Load levels
A load can be a pressure load as well as a a suction load.
Loads from snow and wind are grouped into three levels,
which need to be taken into account wherever the module is
installed. Higher load levels make the requirements for prop-
er installation more stringent. The values listed below as-
sume an appropriate installation.
10.6.1 Permissible loads for modules with standard frames
a
b
GID AS014a
4The total length is 22.5 mm. The distance between the hole centres
is 13.5 mm.
5This applies to unlubricated screws with standard thread and strength class
of 8.8 (minimum breaking load 29.2 kN).
Load level Permissible
pressure
Permissible
suction
Load level I 2400 Pa 2400 Pa
Load level II 3900 Pa 3900 Pa
Load level III 5400 Pa 5400 Pa a
5The total length is 22.5 mm. The distance between the hole centres is 13.5 mm.
6This applies to unlubricated screws with standard thread and strength class of 8.8
(minimum breaking load 29.2 kN).

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 12/21
10.6.3. Permissible loads for modules with Solrif®frames
10.6.4 Permissible loads for modules with standard
frames 42mm
Load level Permissible
pressure
Permissible
suction
Load level I 2400 Pa 2400 Pa
Load level II 3900 Pa 2400 Pa
Load level III 5400 Pa 2400 Pa
Load level IV 8000 Pa 2400 Pa
10.6.4 Snow Load
For the Load levels II and III provide device for additional
mounting of the lowest panels.
The lowest frame part need to be reinforced (e.g. hook for
snow load)
10.7 Key to symbols
length of 22.5 mm.5
10.4.2 Modules with Solrif® frames
NOTE
Avoid screw mounting for Solrif®modules. Only
mount Solrif®modules with the Solrif®mounting
system.
10.4.3 Tightening torque for screw mounting
For M8 stainless steel screws, use a maximum torque of
24 Nm.6
10.5 Insertion mounting
10.5.1 Modules with standard frames
Observe the manufacturer‘s instructions for the mounting
system. Use the earthing holes for the potential equalisation.
Although edge-to-edge mounting is possible (see also
Ch. 8.4.1: „Intervals between modules with standard
frames“), aleo solar recommends mounting at intervals.
10.5.2 Modules with Solrif®frames
Only mount modules with Solrif®frames with the Solrif®
mounting system.
10.6 Load levels
A load can be a pressure load as well as a a suction load.
Loads from snow and wind are grouped into three levels,
which need to be taken into account wherever the module
is installed. Higher load levels make the requirements for
proper installation more stringent. The values listed below
assume an appropriate installation.
10.6.1 Permissible loads for modules with standard
frames 50mm
a:For screw, clamp or lay-in system on long side.
10.6.2 Permissible loads for modules with standard
frames 35mm
5The total length is 22.5 mm. The distance between the hole centres is 13.5 mm.
6This applies to unlubricated screws with standard thread and strength class of 8.8
(minimum breaking load 29.2 kN).
7based on IEC 61215
Load level Permissible
pressure
Permissible
suction
Load level I 1400 Pa 1400 Pa
Load level II 2400 Pa 2400 Pa
Load level III 5400 Pa 2400 Pa
Symbol Explanation
GID AS034a Permissible clamping area (criss-
crossed, red)
GID AS035a Extra clamp required in this area
(diagonally-crossed, green)
GID AS036a Extra support required in this area
(transversal lines, blue)
GID AS037a Clamping point (middle of the clamp
length)
GID AS038a Linear support
H Clearance (height) between the bottom
edge of the module frame and the
mounting surface in millimetres (mm).
Dimensions All dimensions are shown in mm. Note:
drawings are not always true to scale.
The numerical values are binding.
Load level Permissible
pressure
Permissible
suction
Load level I 2400 Pa 2400 Pa
Load level III 5400 Pa 2400 Pa
Please observe the instructions from Schweizer for the
mounting of modules with Solrif frame.
You can find the manual on the website from Ernst Schwei-
zer AG Metallbau or on aleo solar website:
www.aleo-solar.com.
Load level Permissible
pressure
Permissible
suction
Load level I 2400 Pa 2400 Pa
Load level II 3900 Pa 3900 Pa7
Load level III 5400 Pa 5400 Pa a, 7

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 13/21
8On lower frame part against sliding show.
Bolting
– horizontal/vertical –
Clamping
– Long module side, h/v –
Clamping
– Short module
side, h./v.–
Clamping
– Long and short
module side, h./v.–
Lay-in system
– Short side,
h./v. –
Lay-in system
– Long side, h./v. –
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Option 1: Option 2: Assymetrical
clamping
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79, S59
■ Load levels I and II
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Fig.9 Mounting drawing for modules S18, S19, S59 and S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S59 and S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
min. 1 brace⁸ min. 1 brace⁸
Bolting
– horizontal/vertical –
Clamping
– Long module side, h/v –
Clamping
– Short module side,
h./v. –
Clamping
– Long and short
module side, h./v.–
Lay-in system
– Short side,
h./v. –
Lay-in system
– Long side, h./v. –
Load level III (pressure, suction)
Up to 5400 Pa (approx. 540 kg/m²)
ΔH < 45 mm
Option 1: Option 2:
Assymetrical clamping
ΔH > 45 mm
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430
430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
For 430 ≤ a ≤ 560
select: b ≥ 300 and
c ≥ 800 a and b
can be exchanged.
only for on-roof
or free-field
installation
only for on-roof or
free-field installation
max. suction load
3900 Pa!
only for on-roof or
free-field installation
max. suction load
3900 Pa!
only for on-roof
or free-field
installation
For a <200
For 330 < a < 430
Mounting hole
Mounting hole
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
min. 1 brace⁸ min. 1 brace⁸

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 14/21
Bolting
– horizontal/vertical –
Clamping
– Long module side, h/v –
Clamping
– Short module side, h./v.–
Lay-in system
– Short side, h./v. –
Lay-in system
– Long side, h./v. –
Load level I
(pressure)
Up to 2400 Pa
(approx. 240 kg/m²)
only for on-roof
or free-field installation
Load level II
(pressure)
Up to 3900 Pa
(approx. 390 kg/m²)
only for on-roof
or free-field installation
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
8On lower frame part against sliding show.
Option1: Option 2:
Assymetrical
clamping
min. 1 brace⁸ min. 1 brace⁸
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 16 von 23
10.8.2 Modul S25, S75
■Laststufen I und II
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ verti-
kal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Laststufe II(Druck, Sog)
Bis 3900 Pa
(ca. 390 kg/ m²)
min. 1 Stütze
min. 1 Stütze
Abb. 11 Montage-Zeichnung für das Modul S25, S75 bei den Laststufen I und II
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
■Laststufe III
Verschraubung
-Horizontal/ vertikal-
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe III (Druck, Sog) bis 5400 Pa (ca. 540 kg/ m²)
ΔH < 45 mm
ΔH ≥45 mm
Abb. 12 Montage-Zeichnung für das Modul S25, S75 bei Laststufe III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
min. 1 Stüt-
ze
min. 1 Stüt-
ze
Bolting
– horizontal / vertical –
Clapming
– Long module side, h/v –
Clamping
– Short module side, h. / v. –
Lay-in system
– Short side, h. / v. –
Lay-in system
– Long side, h. / v. –
Load level III (pressure)
Up to 5400 Pa (approx. 540 kg/m²)
ΔH < 45 mm
Option 1: Option 2: Assymetrical
clamping
ΔH > 45 mm
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522
301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522
301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Page 14/19 Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1)
10.8.2 Module S25, S75
■ Load levels I and II
Fig.11 Mounting drawing for module S25, S75 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.12 Mounting drawing for module S25, S75 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS030f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
800
1345
Mounting hole
272
272
For 272 ≤ a ≤ 300 select:
b ≥ 240 and c ≥ 800.
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
Option 2: Asymmetrical
clamping
272.5 272.5
800
272.5 272.5
272
272
200 200
200 200
only for on-roof
or free-field installation
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
∆H < 45 mm∆H ≥ 45 mm
– Long module side, horizontal / vertical –
– Short module side, h. / v. –
– horizontal / vertical – – Short side, h. / v. – – Long side, h. / v. –
GID AS031f2-en-GBGID AS031f2-en-GB
Mounting hole
800
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
522 522301
672.5672.5
272.5 272.5
Option 1: Option 2: Asymmetrical
clamping
83 190190
272272
522522
190190
301
200 200
200 200
522 522301
672.5672.5
only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
only for on-roof
or free-field installation
Max. suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
Note: max. permitted
suction load 3900 Pa!
min. 1 brace⁸
min. 1 brace⁸
only for on-roof
or free-field installation
max. suction load
3900 Pa!
only for on-roof
or free-field installation
max. suction load
3900 Pa!
For 272 ≤ a ≤ 300
select: b ≥ 240 and c
≥ 800. a and b can be
exchanged.
Mounting hole
Mounting hole

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 15/21
Clamping
– Long module side, h/v –
Lay-in system
– Long side, h./v. –
Load level II
(pressure)
Up to 2400 Pa (approx. 240 kg/m²)
10.8.3 Module P18, P19
■ Load level I
Fig.14 Mounting drawing for module P18, P19 at load level II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.15 Mounting drawing for module P18, P19 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
8On lower frame part against sliding show.
Clamping
– Long module side, h/v –
Load level III
(pressure)
Up to 5400 Pa (approx. 540 kg/m²)
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
Option1: Option 2:
Assymetrical clamping
■ Load level II
Clamping
– Long module side, h/v –
Clamping
– Short module side, h./v.–
Lay-in system
– Long side, h./v. –
Load level I
(pressure)
Up to 1400 Pa (approx. 140 kg/m²)
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
Option1: Option 2:
Assymetrical clamping
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Fig.13 Mounting drawing for module P18, P19 at load level I
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
min. 1 brace⁸
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 16/21
10.8.4 Module X59, X79
■ Load level I
Clamping
– Long module side, h/v –
Clamping
– Short module side, h./v.–
Lay-in system
– Long side, h./v. –
Lay-in system
– Short side, h. / v. –
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Fig.16 Mounting drawing for module X59, X79 at load level I
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level II
Fig.17 Mounting drawing for module X59, X79 at load level II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Clamping
– Long module side, h/v –
Clamping
– Short module side, h./v.–
Load level III
(pressure)
Up to 5400 Pa (approx. 540 kg/m²)
Fig.18 Mounting drawing for module X59, X79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
8On lower frame part against sliding show.
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Clamping
– Long module side, h/v –
Clamping
– Short module side, h./v.–
Lay-in system
– Long side, h./v. –
Load level II
(pressure)
Up to 3900 Pa (approx. 390 kg/m²)
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
Quick Reference Manual Rel. 3.0, 07/2014, en-GB-DE (1) Page 13/19
10.8 Mounting drawings for modules with standard frames
10.8.1 Modules S18, S19, S79
■ Load levels I and II
Fig.9 Mounting drawing for modules S18, S19, S79 at load levels I and II
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
■ Load level III
Fig.10 Mounting drawing for module S18, S19, S79 at load level III
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1: Option 2: Asymmetrical
clamping
only for on-roof
or free-field installation
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS028f2-en-GB
200 200
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
990
430 800 430
1660
Mounting hole
430 800 430
430430
For 430 ≤ a ≤ 560 select:
b ≥ 300 and c ≥ 800
a and b can be exchanged.
abc
Load level I
(pressure, suction)
Up to 2400 Pa (approx. 240 kg/m²)
Load level II
(pressure, suction)
Up to 3900 Pa (approx. 390 kg/m²)
430430
200 200
only for on-roof
or free-field installation
Bolting Clamping Clamping Lay-in system Lay-in system
Option 1:
∆H < 45 mm
∆H ≥ 45 mm
– Short module side, h. / v. –
– Short side, h. / v. – – Long side, h. / v. –
GID AS029f2-en-GB
– Long module side, horizontal / vertical –
– horizontal / vertical –
Mounting hole
730
730
830830
200
Mounting hole
430430 800
200200 130130
For a < 200
For 330 ≤ a ≤ 430
430430
200
830830
a
a
Up to 5400 Pa (approx. 540 kg/m²)
Load level III (pressure, suction)
730
730 200
830830
Note: max. permitted
suction load 3900 Pa!
730730 200
830830
Max. suction load 3900 Pa!
430430
Option 2: Asymmetrical
clamping
200 200
200 200
Only for on-roof
or free-field installation
Only for on-roof
or free-field installation
Note: max. permitted
suction load 3900 Pa!
Max. suction load 3900 Pa!
only for on-roof or
free-field installation
min. 1 brace⁸
min. 1 brace⁸

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 17/21
■ Load level IV
Clamping
– Long module side, h/v –
Load level IV
(pressure)
Up to 8000 Pa (approx. 800 kg/m²)
min. 1 brace⁸
aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Deutschland | info@aleo-solar.de Kurzanleitung Ausg. 4.0, 05/2015, de-DE-DE (1)
Seite 18 von 23
10.8.3 Modul P18
Laststufe I
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Klemmsystem
-kurze Modulseite, h./v.-
Einlegesystem
-kurze Seite, h./v.-
Einlegesystem
-Lange Seite, h./v.-
Laststufe I (Druck, Sog)
Bis 2400 Pa
(ca. 240 kg/ m²)
Abb. 13 Montage-Zeichnung für das Modul P18 bei Laststufe I
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
Laststufen III
Klemmsystem
-Lange Modulseite, horizontal/ vertikal-
Laststufe III (Druck)
bis 5400 Pa (ca. 540 kg/ m²)
a---------------------------------
a ----------------------------------
Abb. 14 Montage-Zeichnung für das Modul P18 bei Laststufen III
Maße in mm. Beachten Sie bei einem Einlegesystem auch Kap. 10.5: „Einlege-Montage“.
a = 250
±
40
min. 1 Stüt-
ze
Fig.19 Mounting drawing for module X59, X79 at load level IV
Dimensions in mm. For a lay-in system, also refer to Ch. 10.5: „Insertion mounting“.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 18/21
11 For operators: maintenance
NOTE
Inspect and maintain your system to:
• Keep it safe and reliable
• Achieve top output
• Prevent damage and
• Protect your investment.
aleo solar recommends carrying out regular inspections
and maintenance so that any problems can be discovered
reliably, and rectified.
RECOMMENDATION
• aleo solar explicitly recommends annual
inspections and a more thorough inspection and
measurement every 4 years.
• We also recommend the use of a monitoring system
to identify any outages or problems quickly.
• Inspecting the output of your photovoltaic system
regularly can help to discover problems promptly,
and ensures your photovoltaic system operates at
top performance, preventing loss of output.
For the proper maintenance and repair of your aleo solar
photovoltaic system, contact your aleo solar dealer or get
in touch with aleo solar directly (see Ch. 2.2: „Contact“).
11.1 Inspections
aleo solar recommends an inspection every year. This
should be a visual inspection. Refer to Ch. 11.3: „Details
for the inspections“.
The inspection includes the following aspects.
11.1.1 Inspecting the generator
• Strings: condition of the insulation and mounting
• Condition of the junction box
• Condition of the visible connectors
• Condition of the earthing conductors
• for direct earthing: connection of the earthing
conductors on the frames
• for indirect earthing: connection of the frames to
the sub-structure and the earthing conductors to
the sub-structure
• Condition of the mounting system (in peripheral
area)
• Dirt on modules: type and degree of dirt
• Shade circumstances (e.g. from trees or
neighbouring houses)
Clean the components, if necessary.
11.1.2 Inspecting the documentation and drawings
• Checking the module string plan9,
• Check the inverter's status reports
• Determine and archive the annual output
• Create and archive the inspection report.
11.2 Review
aleo solar recommends carrying out a thorough review at
least every 4 years. This includes the following work in
addition to the inspection:
• Measure the characteristics of individual strings
(MPP current IMPP, open-circuit voltage UOC, power
output PMPP);
• Measure the insulation resistance RIS
10, 11;
• Evaluate the annual power output and compare the
data with earlier readings;
• Create and archive a review report.
Check, repair or replace components, if required. Refer to
Ch. 11.3: „Details for the inspections“.
11.3 Details for the inspections
11.3.1 Mechanical inspection
■ Safety precautions
Refer to the notes in Ch. 6.2.2: „Mechanical safety precau-
tions“.
■ Work steps
During the inspection, check that the mechanical connec-
tions are clean, securely fitted and properly intact.
11.3.2 Electrical inspection
■ Safety precautions
Make sure you refer to the notes in Ch. 6.2.1: „Electrical
safety precautions“.
■ Work steps
During the inspection, check that the electrical connec-
tions are clean, securely fitted and properly intact.
Identify any defects or irregularities in the electrical instal-
lation and make a record of them. Then rectify the problem
as quickly as possible.
11.4 Cleaning
Depending on the ambient conditions, modules are likely to
get soiled more or less heavily over time. This can cause
reduced output.
9Suggestion for external inspectors: perform a spot check to ensure that the
module string plan matches the installation.
10 According to the standard IEC 61215, a photovoltaic module should have an insulation
resistance of at least 40 M! • m².
11 Some inverters provide the measured insulation resistance via an interface.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN Page 19/21
NOTE
Dirt- or water-repellent coatings subsequently ap-
plied to the modules can negatively affect the effici-
ency of the aleo modules and therefore the power
output of the whole photovoltaic system. We the-
refore advise against the use of these agents.
RECOMMENDATION
For cleaning the glass module surfaces, aleo solar
recommends:
• Rainwater without additives13 with its temperature
matching the temperature of the module.14
• A so sponge or a so brush.
• If necessary, use a telescopic rod with a sponge or
so brush attached on the end. The rod can have a
water pipe integrated.
• For stubborn patches of dirt, use the following to
help:
• Isopropanol:
aleo solar recommends a mixture of isopropanol
and rainwater to the ratio of 1:1.
• Glass cleaner:
As an alternative, aleo solar recommends clear,
colourless glass cleaner with no ethanol or
denaturants (e.g. Bitrex®)15.
■ Anti-reflex glass
aleo modules have an anti-reflex layer on the glass surface
to achieve a higher output. This means that some marks
(e.g. fingerprints) are more visible than on normal glass.
These marks are mostly seen as shimmering patches.
These kinds of marks do not have any measurable effect on
the module output and fade away aer about 2 weeks of
being exposed to weather conditions, as sunlight and rain
break them down.
11.4.3 Insulating back sheet
The insulating back sheet must not be cleaned. Neverthel-
ess, if you still need to perform work behind the modules
(e.g. to remove leaves):
• Make sure you refer to Ch. 6.2.1: „Electrical safety
precautions“ and Ch. 6.2.2: „Mechanical safety pre-
cautions“.
• Avoid damaging the insulating back sheet.
Dirt could be:
• Dust, pollen or seed
• Leaves or twigs
• Deposits from stable vapour
• Moss, algae, fungi or bacteria growing on depo
sits (in short: biofilms)
• Salt (in coastal regions)
11.4.1 Safety precautions
CAUTION!
Contact of live parts with water. Risk of electric
shock!
• Never use a high pressure cleaner.
_______________________________________________
NOTE
You will also retain the manufacturer's warranty as a
result of this measure.
11.4.2 Glass surfaces
NOTE
• The glass surfaces of aleo modules have
microscopic structures or anti-reflex coatings.
Ensure that these do not get damaged. Do not use
any cleaning agents which will polish or scratch the
surface.
• Avoid the use of very hard water.
• Also avoid the use of distilled or demineralised
water if possible.12
• Avoid the use of acids, bases or other aggressive
cleaning agents.
12 Distilled or demineralised water is oen used by cleaning services but can damage
glass surfaces with frequent intensive use over long periods of time. aleo solar there
fore advises against the use of distilled or demineralised water.
13 Rainwater has a low level of water hardness. It is beneficial to use it because a build up of
deposits is avoided.
14 This prevents mechanical tension in the glass and ensures the module a longer service life.
15 Ethanol contains denaturants. Some denaturants can leave streaks behind or damage
an anti-reflex layer.

aleo solar GmbH | Marius-Eriksen-Straße 1 | 17291 Prenzlau | Germany | info@aleo-solar.com
Quick Reference Manual Rel. 4.4, 12/2018, EN
Page 20/21
11.4.4 More frequent cleaning
RECOMMENDATION
• In environments subject to heavy soiling, we re
commend making the intervals for inspections and
cleaning shorter than just once a year.
• For example, this applies to environments with a
high exposure to dust, especially close to:
• Large livestock farms
• Grain reloading stations
• Green areas with heavy foliage, seeds or pollen
• Factories with high levels of dust emission.
aleo solar recommends contracting a specialised company
to clean your photovoltaic generator properly without trea-
ding on the modules, if frequent cleaning is necessary.
11.5 Repairs
11.5.1 Modules
For repairing aleo modules, only contract technicians who
have been authorised by aleo solar to avoid loss of warranty.
A defective module can cause loss of output, as well as
consequential damage. If an aleo module needs repairing,
first get in touch with aleo solar (see Ch. 2.2: „Contact“).
Never, under any circumstances, repair an aleo module your-
self.
Improper repairs can cause damage which may have reper-
cussions years later, such as failure of electrical insulation.
This could be fatal. Therefore, report any necessary repairs
immediately.
Before you carry out any maintenance work on aleo modules,
deactivate the module string or the whole generator if
necessary. Observe the warnings and notes in Ch. 6.2.2:
„Mechanical safety precautions“ and Ch. 6.2.1: „Electrical
safety precautions“.
11.5.2 System parts
For repairing other system parts (e.g. substructure, connec-
tion boxes), contract authorised technicians to do the work
or contact aleo solar directly (see Ch. 2.2: „Contact“).
12 For operators: decommissioning
12.1 Safety precautions
Make sure you refer to the notes in Ch. 6.2.1: „Electrical
safety precautions“. If you would like to continue using the
aleo module, also refer to Ch. 7.1: „Handling aleo modules“
12.2 Disposal
NOTE
• Dispose of the aleo modules at the end of their
service life in the proper manner.
• To do this, contact a disposal company.
• Never dispose of aleo modules with household
waste.
12.3 Returns
Aleo solar is member of PV Cycle, used or damaged PV mo-
dules from aleo are covered by PV Cycle scheme without any
costs.
12.4 PV Cycle
PV CYCLE offers a comprehensive collection network for your
PV module waste. From fixed collection points to on-site pick-
up, find your collection service here.
Our collection and recycling service is free-of-charge* for mo-
dules of our members’ brands. For free disposal, please first
consult our brands search. For non-members’ brands, please
send the quotation request form to
1 – 40 MODULES
PV CYCLE offers a broad network of fixed collection points for
the disposal of small quantities.
1. Find your nearest PV CYCLE Collection Point under:
http//germany.pvcycle.org/ --> Find collection point
2. Schedule an appointment with your preferred collection
point
3. Download and complete the Delivery Request Form
4. Deliver your PV modules to the collection point
5. Receive a signed copy of your Delivery Request Form
80 – MORE MODULES
PV CYCLE offers on-site pick-up for the disposal of large
quantities. The minimum quantity for the PV CYCLE direct
pick-up service is 80 modules. For quantities between 40 and
* Free service limited to max.10t per request/pick-up. Special conditions apply to
quantities larger than 10t (i.e. replacement or decommissioning of large installations,
etc.).
This manual suits for next models
2
Table of contents