Allume SolShare SOLSHARE-3P-35A-03 User manual

1
SolShare
Installation Manual

2

3
Australia - AE-PN-101-V5.0
This manual is intended for installations in Australia of SolShare model
SOLSHARE-3P-35A-03.
It is subject to change. Please check our website at
https://allumeenergy.com/document-library for the most up-to-date manual version.
Version Date released Updates
V3.0 23/03/2021
V4.0 27/07/2021 – Addition of linked documents for additional information
– Updated Installation Overview section
– Updated switch and isolator names to align with Australian Standards
– Updated Installation Site Selection section
– Updated Electrical connection section
– Updated advice about current transformers
– Added Labeling section
– Updated Commissioning section
V4.1 18/08/2021 – Updated links
– Updated Commissioning Document
V5.0 23/08/2021 – Updated to reect product changes associated with the removal of
4G dongle and addition of Wi-Fi access point.
– Addition of CT connection aid
AE-PN-101-V5.0
© Copyright – Allume Energy - All rights reserved.
This manual accompanies our equipment for use by the end users.
The technical instructions and illustrations contained in this manual are to be treated as condential and no part may be reproduced without the prior
written permission of Allume Energy and end users may not divulge the information contained herein or use this manual for purposes other than those
strictly connected with correct use of the equipment.
All information and specications are subject to change without notice.

4
Summary
Commissioning Document
I/ What’s in the box
II/ Mounting the SolShare
A. Installation site selection
B. Installation
III/ Electrical connection
A. Input / output connections
B. Running current transformer tails
C. Labeling
IV/ Commissioning
A. Preparing the SolShare for commissioning
B. Commissioning the SolShare
p06
p08
p10
p10
p11
p12
p12
p16
p17
p18
p18
p18

5
Hello
Thank you for purchasing a SolShare system.
You are supporting the growth of cutting edge Australian
made solar technology. Due to the novelty of this product,
this installation will likely be dierent from any other piece
of solar technology you have installed in the past. As a
result, please follow the guidelines in this manual carefully.
Installations that contravene these guildelines are not
covered under warranty unless a written exemption from
Allume is provided.
Your system is designed to meet all Australian conditions,
regulations and codes. This guide provides the general
instruction of the installation procedure of the SolShare.
If you have questions or feedback on the product or this
manual, feel free to reach out to Allume on +61 3 7038 0686
and ask for a technical representative. Otherwise, you can
email support@allumeenergy.com.au with any queries.
List of supplementary documents available online
For most up to date versions of all
documents (including this Installation
Manual), scan this QR code or go to
https://allumeenergy.com/document-library/
https://allumeenergy.com/wp-content/up-
loads/2021/07/%0A01-Allume-SolShare-35-Datasheet.pdf
https://allumeenergy.com/wp-content/uploads/2021/07/
07-SolShare-Installer-Training-pre-installation-checklist.pdf
https://allumeenergy.com/wp-content/uploads/2021/07/
0355_A2_SolShare_Labelling_Advice.pdf
https://allumeenergy.com/wp-content/uploads/2021/08/0332
_A5_Commissioning-App-V2.0-Screenshots-Instructions.pdf
https://allumeenergy.com/wp-content/uploads/2021/07/0121_
B11_SolShare-System-SLD-Design-Guidelines.pdf
https://allumeenergy.com/wp-content/up-
loads/2021/07/0339_A1_Changing-Wi-Fi-credentials.pdf
SolShare labelling advice
SolShare system and SLD design guidelines
Commissioning app guide
SolShare pre-installation checklist
How to set-up/change Wi-Fi credentials
SolShare 35-AU datasheet

6
Commissioning Document
To be completed during installation and entered to commissioning app
Serial Number: 3P_35A_
Installer name: Company:
Electrician license number:
Allume SIP training
certication number:
SolShare Connection
Unit Connected (eg: Apt 1, Unit B, Common light & power, No connection)
Single-Phase Three-Phase
R1
W1
B1
R2
W2
B2
R3
W3
B3
R4
W4
B4
R5
W5
B5
Unit Connection Identier
OR
OR
OR
OR
OR
Installation Address:
State: Postcode: Country:

7
IMPORTANT SAFETY INSTRUCTIONS
WARNING: Opening of the SolShare must only be performed by a certied electrician.
WARNING: This equipment is connected to multiple sources of supply. Isolate all supplies before working on this equipment.
Each input circuit and each output circuit represent a source of supply.
WARNING: The specied shutdown procedure must be followed prior to working on this equipment.
WARNING: This equipment must be permanently earthed.
WARNING: This product relies on passive cooling, install in a well-ventilated location in accordance with the mounting instructions.
CAUTION: HEAVY OBJECT – This product has a weight of approximately 38kg. Un-boxing and mounting the product requires
2 people.
CAUTION: Residual Current Devices and Earth Leakage Breakers must not be used as Overcurrent Protection devices in Solshare
Output circuits.
CAUTION: The SolShare will impose a current dependent voltage drop/rise which should be taken into account during design of
the installation. Specications are given in the Technical Data sheet.
CAUTION: The unit must be operated according to the technical specication datasheet provided with the unit.
CAUTION: Installations may vary depending on the existing electrical infrastructure and local electrical safety standard. It is the
responsibility of the electrician to ensure their installation meets the local electrical safety standard.
NOTE: Use only copper conductors rated for a minimum of 90 degrees Celsius.
NOTE: The symbol appears at grounding points within the SolShare equipment. This symbol is also used in the manual.
Handling and Safety Instructions
SAFETY SYMBOLS INFORMATION
The following safety symbols are used in this document. Familiarise yourself with the symbols and their meaning before
installing or operating the system:
Important:
xxxxx xxxx xxxx xxx xxxx xx xxxx xxx xxxx
Important:
xxxxx xxxx xxxx xxx xxxx xx xxxx xxx xxxx
Warning:
xxxxx xxxx xxxx xxx xxxx xx xxxx xxx xxxx
This symbol denotes a critical safety instruction that must
be followed to ensure safety of installer and safe operation
of the SolShare once commissioned. This box is sometimes
denoted in green to provide further emphasis.
This symbol indicates an instruction which will ensure
proper operation of the SolShare once commissioned or
will help with the installation efficiency. This same box is
sometimes denoted in green to provide further emphasis.
This guide is provided to help the installer understand
the standard SolShare installation procedure.
Installations may vary depending on the existing electrical
infrastructure and local electrical safety standard. It is the
responsibility of the electrician to ensure their installation
meets the local electrical safety standard.
During installation, testing and inspection, adherence to all
the handling and safety instructions is mandatory. Failure
to do so may result in injury or loss of life and damage
to the equipment.
Warning:
xxxxx xxxx xxxx xxx xxxx xx xxxx xxx xxxx
SAVE THESE INSTRUCTIONS. This manual contains important instructions for the SolShare 3P-35A that shall be
followed during installation and maintenance of the power division control system.

8
Check for Transport Damage
Make sure the SolShare is intact following transportation. If there are any signs of visible damage, please contact
your dealer immediately. Carefully check that all of the components have been supplied. If anything is missing,
contact your dealer.
I/ What’s in the box
Mounting bracketSolShare unit Label pack
Warning:
- Make sure to read over, fully understand and strictly follow the detailed instructions
of this installation manual and other related regulations before installing the equipment.
- Any violation could result in personal death or injury, or damage to the device.
- Installation is only to be conducted by a certied electrician.
- This guide is provided to help the installer understand the standard SolShare installation procedure.
Installations may vary depending on the existing electrical infrastructure and local electrical safety
standard. It is the responsibility of the electrician to ensure their installation meets the local
electrical safety standard.
- This product has a weight of approximately 38kg. Un-boxing and mounting the product requires 2 people.
x 1 x 2
Fastener Locking
plate
Split current transformer
with 10m tails
CT connection aidCT connector block
x 1 x 15
x 4 x 1x 3

9
Installation overview
Electricity Meter Panel
Tenancy main switches
XXXXXX
M1
XXXXXX
M2
XXXXXX
M3
XXXXXX
M4
654321 7 8 9 10 11 12 13 14 15
XXXXXX
M5
XXXXXX
M6
XXXXXX
M7
XXXXXX
M8
XXXXXX
M9
XXXXXX
M10
XXXXXX
M11
XXXXXX
M12
XXXXXX
M13
XXXXXX
M14
XXXXXX
M15
3 phase
from
inverter
Tenancy Main Switches
(Normal Supply)
Tenancy Main Switches
(Inverter Supply)
SolShare Maintenance
Isolators (Grid)
minimum
150mm
A single SolShare unit can distribute the power generated
from a single solar system to up to 15 single-phase or 5
three-phase units (or a combination of the two).
The SolShare takes a single three-phase input from a grid-
connected solar inverter(s) and connects to each participating
unit on the load side of their retail electricity meter at the unit
main switchboard.
A Tenancy Main Switch (Inverter Supply) is required on each
output (ideally located within the unit main switchboard)
between the SolShare and each unit’s main switch. In series
with this, additional SolShare Maintenance Isolators (Grid) are
recommended to allow for the isolation of the SolShare and
the solar supply of any of the connected units.
A typical installation conguration is displayed below. The
conguration displayed below may dier from your installation
conguration. Please refer to your Project Single Line Diagram
(SLD) for the connection and switchgear conguration for
your specic project. Guidance on this is covered below
and in the supporting SolShare System and SLD Design
guidelines document that is available from Allume. It is highly
recommended that a hardcopy of the project SLD be kept
onsite at all times.
More information about labelling can be found in the SolShare
Labelling Advice document.
Explained
on p16
Explained
on p14
Warning:
The neutral for the SolShare must be wired directly to the main neutral bar inside the main switchboard,
i.e. at the MEN link.

10
II/ Mounting the SolShare
A. Installation site selection
To minimise cabling required, the SolShare should be mounted as close to the main switchboard (tenancy
isolator board) as possible.
To allow for easy installation and maintenance, ensure that there is adequate space surrounding the SolShare and
that it is mounted at a convenient height. Please ensure the following mounting requirements are also met when
selecting the location of the SolShare.
Note: Where possible, do not install the
SolShare below a cable tray - this may affect
the SolShare’s ability to connect reliably with
the Wi-Fi at site.
Internet communications
A Wi-Fi network must be
available at the site to
enable commissioning
and ongoing monitoring.
Do not mount the SolShare
on ammable wall material
90˚
Mounted Vertically
Do not mount the SolShare
near ammable material or
gases
90˚
Mounted Vertically
Environmental boundaries
90˚
Mounted Vertically
Max ambient
temperature:
50°C (+122°F)
Min ambient
temperature:
-10°C (-13°F)
Relative humidity:
0-90%
90˚
Mounted Vertically
Mount vertically
90˚
Mounted Vertically
Install a shade cover over the
SolShare when installed outdoors
in direct sunlight or when in the
path of debris (e.g. under a tree
with falling leaves)
90˚
Mounted Vertically
Install in an easy to observe
and operate location
≈1200 mm
Ensure there is
adequate space in
front of the SolShare
for an electrician
to work (both for
installation and for
future service).
≈500mm
Requirement for
installation space
150 mm150 mm
500 mm500 mm
SolShare
dimensions:
920 x 485 x 270 mm
(H x W x D)

11
43
780 mm
21
Important:
- The mounting wall and fastener selection is at the discretion of the installer. Allume Energy take no responsibility
in the appropriate site selection for the SolShare or the appropriate bracket fastener choice.
- Weight rating fasteners should be rated to at least 30kg of shear force per fastener.
B. Installation
Follow the steps below to mount the brackets and enclosure:
1. Firmly secure the mounting brackets to the chosen wall for installation. Allume Energy recommend using the
provided fasteners to attach the brackets into a suitable stone or masonry wall. If another wall material has been
chosen for installation, please use suitable fasteners with at least 30kg shear force per fastener.
2. Lift the SolShare onto the mounting brackets as directed in the diagram. Check both top and bottom brackets are
secure.
3. Insert the locking bolt through the SolShare top mounting bracket as shown and secure at both ends.
4. Ensure the SolShare is securely fastened to the wall and locked into place.

12
III/ Electrical connection
1 2
To reveal the lower section, slide cover up about 15cm.
Whilst sliding cover upwards, pull cover gently towards
you. This will ensure it nds the locking slot.
Box as you nd it, closed. Unscrew the 4 screws on the
underside of the SolShare to allow access to connection
terminals. Retain screws to replace later.
Important:
The cover should lock into place when it’s pulled up properly. Before beginning wiring, ensure cover is
locked in place by pulling down rmly.
To bring cover back to initial position, lift cover upwards and away from you, then allow to slide down
back into place.
Caution:
Risk of crush hazard if cover dislodged while in service position.
A. Input / Output Connections
1. Lift up cover to reveal the lower section of the box, where the electrical connections are made.

13
SolShare underside view
Each output membrane gland will correspond to the output of 3 single-phase units or 1 three-phase unit.
The leftmost membrane gland corresponds to the solar input.
Vent: do
not remove
input
solar
output
R1, W1, B1
output
R2, W2, B2
output
R3, W3, B3
output
R4, W4, B4
CT
conduit
gland
output
R5, W5, B5
Cover
retainer
screws
Area of input / output:
The 4c+e cables should be inserted
through the appropriate glands, as
per the ‘SolShare underside view’
diagram above.
Warning:
The SolShare may divert all
solar energy to any one unit
in a point in time. As a result,
all input / output cables
should be sized for maximum
solar energy output.
The AC cables
Please choose appropriately
gauged cables as per solar
system size. The use of
four core and earth (4c+e)
is recommended. All input
and output cables should
be rated to total generation
capacity of inverter.
Warning: Outdoor Use requirements
Outdoor installation requires use of minimum
IP56 rated liquid tight cable or conduit gland
suitable for panel hole dimensions below.
Panel thickness: 4mm | Hole diameter: 32mm
Replace tted membrane glands in base
panel with conduit tting

14
Input Connection
All wiring is conducted on the AC side of the inverter. The SolShare requires a three-phase, grid-connected inverter
to be used in the PV installation. The solar input cable must come from an Inverter Supply Main Switch, ideally
located in an accessible location from the main switchboard.
To wire the input cable into the SolShare, the following steps should be taken:
1. Measure out the 4c+e cable and cut to appropriate length.
2. Strip cable sheath back by approximately 100mm.
3. If outdoors, select appropriate cable/conduit gland and use these to replace membrane glands. Insert 4c+e into
SolShare via this cable/conduit glands.
4. Cut and connect earth and neutral from input to their respective connection points.
5. Cut and connect phase cables as per the diagram above.
Output Connections
Please refer to your Project Single Line Diagram (SLD) on how to connect the SolShare to the main
switchboard.
Your project SLD should have been designed in accordance to the SolShare System and SLD Design Guidelines.
If no project SLD exists please contact project owner or system design engineer.
For ease of isolation of the SolShare, it is highly recommended that an enclosure be installed below the SolShare
containing SolShare Maintenance Isolators (Grid). As the SolShare is a 3-phase device, it is recommended that
these Maintenance Isolators are 3 pole with the same current rating as the Tenancy Main Switches (Inverter Supply).
The outputs from the SolShare must be wired to the SolShare Maintenance Isolators (Grid). The outputs of the
SolShare Maintenance Isolators (Grid) must be wired to their respective Tenancy Main Switch (Inverter Supply).
Ensure each cable is labelled with the tenancy number. This will help later on in the installation when wiring the
current transformers to each unit.
CONNECTORS
EARTH BAR
R1 W1 B1 R2 W2 B2 R3 W3 B3 R4 W4 B4
N N R W B
ONLY CONNECT THE NEUTRAL
AND EARTH CABLES OF THE
INPUT AND OUTPUT 1
INPUT SOLAR OUTPUT 1 OUTPUT 2 OUTPUT 3
NEUTRAL
MINIMUM CONNECTION POINTS
FOR CORRECT OPERATION OF
SOLSHARE. OUTPUT R1, W1, B1
MUST BE CONNECTED.

15
Important:
It is recommended to label both ends of each cable with the appropriate tenancy name (e.g. Unit 21) and
SolShare output name (e.g. R1 or W4, etc.) to ensure the correct cable is wired into the correct tenancy in
the main switchboard.
Important:
For maintenance and troubleshooting purposes, it is requested to write the tenancy names corresponding
to each output on the bottom plate of the SolShare (with permanent marker).
Important:
SolShare must have output connection (with grid connection) to R1, W1, B1 for correct operation.
If possible, wire these to common power connection.
Important:
Check the order of the SolShare outputs carefully. The SolShare terminal block is congured to wire in
the order R1, W1, B1, R2, W2, B2, R3, ... etc. Ensure the connections from the Tenancy Main Switches
(Inverter Supply) via any SolShare Maintenance Isolators (Grid) are connected in this order. Ensure the
switches are labeled clearly and logically.
Follow these steps to complete the output wiring:
1. Complete the Unit Connected column of the Commissioning Document on page 6, allocating a SolShare output
to a unit/apmt number.
2. If using SolShare Maintenance Isolators (Grid): Cut output power cables to appropriate length to reach from
SolShare Maintenance Isolators (Grid). Label both ends of these cables with the tenancy number.
3. If using SolShare Maintenance Isolators (Grid): Run cables between SolShare and SolShare Maintenance
Isolators (Grid). Terminate cables to appropriate SolShare output connectors as per the conguration in step 1.
4. Cut the power cables to appropriate length to run from the SolShare Maintenance Isolators (Grid) to the Tenancy
Main Switches (Inverter Supply) in the Main Switchboard. Run and terminate these cables.
Warning:
Only one neutral and ground shall be wired out of the SolShare, as shown in the diagram on page 14.
Output neutral and ground must be wired to main neutral bar and main earth bar respectively, located in
the main switchboard.
Warning:
- Ensure the phase of the solar supply correctly matches the phase of the unit’s supply from the grid.
- Additional circuit breakers must be sized to perform overload protection for SolShare output cables.
- The solar system max output must be less than the main circuit breaker rating of every connected unit.
- The neutral for the SolShare must be wired directly to the main neutral bar inside the main switchboard,
i.e. at the MEN link.
- Point of connection of solar should be on the service side of tenancy main switch unless specied
otherwise by your Project SLD.

16
W1
B. Running current
transformer tails
1. Run CT conduit from Solshare to main switchboard
(the CT conduit gland is the pre-installed CT conduit
gland on the underside of the SolShare - see the
underside view diagram on p. 13 to ascertain where
the CT conduit gland is).
2. Look for labels on current transformers and current
transformer tails. Ensure these match the
corresponding tenancy.
3. Run tails of CTs from main switchboard to SolShare
through conduit.
Electricity Meter panel
Unit main switches
XXXXXX
M1
XXXXXX
M2
XXXXXX
M3
XXXXXX
M4
654321 7 8 9 10 11 12 13 14 15
XXXXXX
M5
XXXXXX
M6
XXXXXX
M7
XXXXXX
M8
XXXXXX
M9
XXXXXX
M10
XXXXXX
M11
XXXXXX
M12
XXXXXX
M13
XXXXXX
M14
XXXXXX
M15
Area of focus:
Conduit cable
Current transformers to SolShare connections
Wiring tails to Solshare:
1. Connect the CT cabling to the CT connector
block, as per the diagram to the right. To do this:
- Push the orange tab in and hold.
- Feed the CT cable into the hole.
- Once inserted, release the orange tab.
- Conrm cable is secure by giving it a gentle tug.
2. Repeat for all CT cables of the red phase.
3. Repeat steps 1 & 2 for white and blue phase
connector blocks.
4. Plug each CT connector block into the
corresponding socket of the SolShare.
Important:
Make sure colours and orientation of connectors
are identical to the image above. To ensure you
are positioning them correctly, check that the
orange tabs are above your plugged in cables,
and labels read as above.
W1
W2
W3
W4
W5
1- 1+ 2- 2+ 3- 3+ 4- 4+
5- 5+
1- 1+ 2- 2+ 3- 3+ 4- 4+ 5- 5+
Important:
If you are using the standard 75A CTs provided
with the SolShare, their 10m tails cannot be
extended.
If you require tail lengths of more than 10m,
an additional upgraded CT set should have
been ordered at the time of ordering the
SolShare. Please call Allume on the phone
number provided on the back page of this
manual to order the upgraded CT kit.
Important:
The SolShare has come with a CT connection
aid. Place the CT connecter into the connection
aid to help with the termination of the CT tails.
Important:
If you are using the upgraded CT set, these come with 10m tails but can be extended to a total of up to 50m.
The tail extension can be done for each CT separately using the following recommended parts:
- Butt splice connector (appropriate size for cable)
- Twisted shield cable, minimum 24 AWG size (to the length required on top of 10m to make the run
between SolShare and main switchboard)
CT
CONNECTION
AID
CT CONNECTOR
BLOCK

17
Current transformer clipping
Clipping the current transformers onto the service
side cable:
1. Match the labelled CTs with their corresponding
labelled service supply cable.
2. Conrm correct polarity of the CT by ensuring
the arrow on the CT head matches the current
ow direction on the service supply cable.
3. Clip CT over service supply cable.
Important:
Make sure that each CT is clipped
to the corresponding unit.
Important:
The CT must be connected on the service
side of the point of connection of solar
supply, as per diagram.
POLARITY
OF CURRENT
TRANSFORMERS
DOWN TOWARDS
LOAD
R1
R1
FROM
SOLAR
SERVICE SIDE
LOAD SIDE
*
* The point of connection of the solar may appear
dierent in your case depending on the Project SLD.
In any case, the CT must be on the line side of the point
of connection of the solar supply.
C. Labeling
The SolShare comes with a Label Pack for you to use
where appropriate. Other labelling will also be required
based on your installation and local requirements. For
more information, refer to the SolShare Labelling Advice
document. Please refer below for information about
SolShare-specic labelling.
Leave a copy of the Project SLD at site to provide guidance
to any other electrician working on the switchboard.
XXXXXX
M1
XXXXXX
M2
XXXXXX
M3
XXXXXX
M4
654321 7 8 9 10 11 12 13 14 15
XXXXXX
M5
XXXXXX
M6
XXXXXX
M7
XXXXXX
M8
XXXXXX
M9
XXXXXX
M10
XXXXXX
M11
XXXXXX
M12
XXXXXX
M13
XXXXXX
M14
XXXXXX
M15
WARNING
Solar wired on the line/service side
ofTenancyMain Switches
Follow Solar Shutdown Procedure,
locatedon inverter(s), before
workingon meter panel
Warning
SharedSolar System
Toisolatea single unit:
1.Turn off theirMAIN SWITCH INVERTER SUPPLY
2.Turn offtheir MAIN SWITCH NORMAL SUPPLY
XXXXXX
M1
XXXXXX
M2
XXXXXX
M3
XXXXXX
M4
654321 7 8 9 10 11 12 13 14 15
XXXXXX
M5
XXXXXX
M6
XXXXXX
M7
XXXXXX
M8
XXXXXX
M9
XXXXXX
M10
XXXXXX
M11
XXXXXX
M12
XXXXXX
M13
XXXXXX
M14
XXXXXX
M15
WARNING
Solar wired on the line/service side
ofTenancyMain Switches
Follow Solar Shutdown Procedure,
locatedon inverter(s), before
workingon meter panel
Warning
SharedSolar System
Toisolatea single unit:
1.Turn off theirMAIN SWITCH INVERTER SUPPLY
2.Turn offtheir MAIN SWITCH NORMAL SUPPLY
Area of focus:
Labeling
Line side wiring
WARNING
Solar wired on the line/service side
of Tenancy Main Switches
Follow Solar Shutdown Procedure,
located on inverter(s), before
working on meter panel
NOTE: This must be visible from all meters (contact
Allume if additional labels are required). Do not apply this
label if SolShare connections have been made on the load
side of the Main Switch (Normal Supply). Instead, use a
standard multiple supplies warning label)).
Warning tenancy shutdown
Warning
Shared Solar System
To isolate a single unit:
1. Turn off their MAIN SWITCH INVERTER SUPPLY
2. Turn off their MAIN SWITCH NORMAL SUPPLY
NOTE: This must be visible from all Tenancy Main
Switches (contact Allume if additional labels are required).
Add these additional labels as suitable:
- SolShare Maintenance Isolator (Inverter) label
- SolShare Maintenance Isolator (Grid) labels
- Tenancy Main Switch (Inverter Supply) labels
- Tenancy Main Swtich (Normal Supply) labels
(not provided with SolShare)
South Australia only:
- Multiple supplies label next to each meter
- SolShare Inverter Supplies tags

18
A. Preparing the SolShare
Important:
- Before commissioning, re-check all CTs and output cables are connected as per their labels.
- Record connection information on commissioning notes page, you will need to enter this
while commissioning the unit after the cover is closed.
To power on the SolShare:
1. Pull down cover of SolShare. Fasten shut by replacing the 4 screws on the underside of the SolShare, that were
removed in section III/A.1. Maximum torque for cover fasteners is 1.5Nm
2. Turn on Inverter AC Isolator located next to inverter
3. Turn on Inverter Supply Main Switch
4. Ensure Main Switches (Normal Supply) are on
5. Turn on Main Switches (Inverter Supply)
To connect the SolShare to Wi-Fi (must be done within 5 mins of powering on the SolShare):
1. Using a laptop or phone (your device), connect your device to the SolShare SSID (this will appear as
SolShare3P_35A_XXXX where XXXX is the last 4 digits of the SolShare serial number).
2. Open an internet browser on your device and navigate to 192.168.4.1.
3. Once the page loads in the browser, enter the SSID and password of the Wi network that you want the
SolShare to connect to.
4. Once you see a conrmation page in the browser, wait for the SolShare to reboot.
5. Disconnect your device from the SolShare SSID and reconnect it to the internet in preparation for the
commissioning steps below.
If you are having troubles with this process or need more detail, consult the How to set-up/change Wi-Fi credentials
document.
B. Commissioning the SolShare
1. To commission the SolShare, scan the QR
code on the right side of the SolShare or go to
https://commissioning.allumeenergy.com.au to
access the SolShare Commissioning App.
2. Follow the steps in the Commissioning App to
commission each SolShare. The Commissioning
App Guide provides more information on the
commissioning process.
NOTE: The SolShare requires a fully operational
inverter in order to complete commissioning. During
the SolShare commissioning process, you will be
prompted to commission the inverter. Please make
sure that the inverter is ready to be commissioned
prior to starting the commissioning process for the
SolShare.
3. If you experience issues with the commissioning
process contact Allume Service on +61 3 7038 0686
or support@allumeenergy.com.au
IV/ Commissioning

19
Table of contents
Other Allume Inverter manuals
Popular Inverter manuals by other brands

Mitsubishi Electric
Mitsubishi Electric FR-A872-P instruction manual

Clarke
Clarke IG3500F Operation & maintenance instructions

Pleion
Pleion Eclipse user manual

Fujitsu
Fujitsu Waterstage WOYG160LJL installation manual

Hitachi
Hitachi SJ100DN DeviceNet Series Addendum instruction manual

Wacker Neuson
Wacker Neuson GPi 3200 Operator's manual

Growcol
Growcol DY-LG300S manual

Leroy-Somer
Leroy-Somer DIGIDRIVE Series Installation and commissioning

Turbo Energy
Turbo Energy Lithium Slim Series Quick installation guide

Pyle
Pyle Power Inverter PNVU400 owner's manual

Istore
Istore HYBRID 5000/6000 3 Phase user manual

Generac Power Systems
Generac Power Systems Guardian 04389-2 Installation and owner's manual