9. Work area has been blocked off to pedestrians, unprotected personnel, &
untrained personnel. In the eventpedestrians, unprotected personnel, or untrained
personnel enter the work area, blasting operations are to be stopped immediately.
10.Fire extinguishers are nearby. Also, take note of the location & the contact
information of fire departments close to the work site.
11.All guards & protective shields are properly installed & secured.
12.All glass & equipment, including vehicles, are protected from steel shot. This can
be done by loosely hanging a sheet of visqueen or other protective materialin front
of the glass or equipment in a curtain-like fashion. The importance of protecting
glass & equipment from steel shot cannot be overemphasized.
13.Plug or cover all floor drains to prevent steel shot from falling into the drains.
14.This equipment is onlyto be used for commercial purposes. This equipment is only
to be operated by professional, trained, & competent operators.
15.The operator must be aware of their surroundings & use common sense. The
operator is not to operate the equipment if he is tired, distracted, or under the
influence of drugs, alcohol, or medication that decreases awareness.
Start-Up Procedures
After performing the site assessment safety procedures listed above, bring the shot
blasting machine to the work area & perform the following procedures:
•Verify that personnel are competent & that they have read & understood the safety
information in this manual. Staff must also be familiar with how to operate the
machine & with all of its components. Make certain that all personnel follow all
safety instructions & programs required by their company & by the worksite.
•Before putting the BP-9-SP in operation, make certain that the belt guards are in
good condition.
•Inspect the BP-9-SP & dust collector for damage, tears, or other signs of wear.
•Verify that all fittings & hoses are tight.
•Inspect the dust collector. Verify that the dust bin is empty, filters are clean & clear
of debris, & motors & fansare in working order. The dust collector must be emptied
at the end of each job.
•Make certain that the shot valve control lever is closed except when the machine
is actually in operation.
•Inspect all electrical cords on the BP-9-SP for damage, tears, or other signs of
wear. If electrical cords are damaged, then do not attempt to perform blasting
operations until cords have been repaired or replaced.
•Inspect the duct hose leading from the BP-9-SP to the dust collector. Make sure
hose is free of debris, hose is not cracked & that holes do not exist. If necessary,
replace hose.
•Make certain that all screws & other fasteners are tight.
•Check the shot storage hopper, the feed spout, & the blast wheel for foreign bodies
& remove them if present.