SITE PREPARATION
5
SERIES 4 & SERIES 5 CENTER ISLAND CABINET
Installation Instructions
FIRST STEPS
AIR
Pipe: 1/2” n.p.t. Protruding 1” from the oor. Supplied by contractor.
Air supply: pressure 80-100 psi. Air should be free from contaminants.
Pipe: 1/2” n.p.t. Protruding 1” from the oor. Supplied by contractor.
Water supply: pressure 40-80 psi. Water should be ushed clean before connecting to this equipment.
ELECTRICAL
Electrical: 4 x 4 x 2-1/4” Connection Box with 1/2” conduit knockouts (supplied by contractor).
Wire box as per local code with top of the box no higher than 4-1/2” above nished oor. Voltage: 115 VAC, 3 wire,
20 amp with ground fault circuit interrupter (Series 5 cabinet only).
Second circuit if optional x-ray unit is being installed: 115 VAC, 3 wire, 20 amp circuit
3rd Party x-rays must be connected to the provided hospital grade outlet inside the X-Ray Module.
Pipe: supplied by contractor. Terminated with 5/8” OD tube protruding 1” from the nished oor.
Pipe: 5/8” OD tube protruding 1” from the oor. Place trap in-line and use vented tting to conform to local codes.
Supplied by contractor.
CENTRAL VACUUM
GRAVITY DRAIN
WATER
1
Lay the installation template over plumbing stub-ups and check the position in the operatory.
2Install air and water shut-off valves (not supplied).
3Install 4 x 4 electrical connection box (not supplied).
4Mark the two cabinet mounting points according to the template.
Wood: Drill two 1/2” holes, 3-1/2” deep into oor (provided in hardware kit).
Concrete: Install 1/2” anchor bolts leaving 1” above oor (provided in hardware kit).
WARNING: Ensure the cabinet is
properly grounded to protective earth.
WARNING: 3rd party x-ray systems must be
connected to a dedicated electrical circuit.
CAUTION: Electrical utilities must be installed according to local codes and by a licensed electrician.