
GEK-721 01, Low V oltoge Swifchgeor
ASSEMBLY OF EQUIPMENT
Before assembly of the equipment is begun all com-
ponents should be on hand to facilitate installation. The
individual shipping packages must be connected togefher
on the foundation. If there is no transformer in the lineup
and the equipment has been split for shipment, place the
middle package on the foundation first and assemble in
both directions. If the equipment is part of a Load Center
Unit Substation. the transformer section should be set on
its pad in accordance with the instructions furnished with
the transformer, and then packages of equipment added.
NOTE: WHEN AKD-6 SWITCHGEIR IS IN-
STALLED IN THE SAME LINEUP WITH
TRAIVSFORM E RS AND OTHE R EqU I PM E NT,
IT IS IMPERATIVE THAT ALL MOUNTING
SURF.ACES BE LEVEL.
Proceed to assemble the equipment as follows:
1. The switchgear packages should be placed on the
foundation with the aid of cranes or jacks as shown in
Figure I for indoor equipment or Figure 2 for outdoor
equipment.
2. For Indoor Equipment, the packages should be fas-
tened together at the shipping splits by bolting the front
and rear upright channels together. Use 3/a-16 hardware
furnished with the equipment at the end of the packages,
Ilta transformer is in the lineup, hardware for connecting
the flange to the switchgear is supplied with the equipment.
3, For Outdoor Equipment, remove the lifting plates
from front and fear of the switchgear base at both ends of
the shipping split joint and assemble the front and rear
splice plates as shown in Figure 14.
When joining shipping packages, special procedures for
weather-proofing must be followed as indicated in Figure
14. The joint in the roof at shipping splits must be weather-
proofed, This is done as shown in Figure 14 by placing a
rubber seal on each side of the top edge of the roof sup-
port batten so that the roof sections butt up against this
seal on both sides. Bolt this joint togeher, using 7a-16
hardwaie. A roof cap is placed over this seam and held in
place by the roof trim. Joints between transformer throat
and switchgear and between shipping splits must be
weather-proofed as shown in Figure 14. Install a front and
rear batten and rubber seal at the shipping split joints and
bolt them together with the furnished 3/e-16 hardware.
The gasket for an outdoor transformer is furnished with
the transformer, and hardware for connecting the trans-
former flange to the switchgear is supplied with the equip-
ment. Check alignment of doors on the outdoor equipment
to see that the weatherproof seal has not been disturbed.
4, Bolt the main buses, ground buses, and neutral buses
of adjacent shipping packages together using the splice
bars furnished with the equipment. See Figure 13 and 14
for details of splice bar connections. The ground bus is
mounted directly on the rear upright channels, It is par-
ticularly important that this bus be connected since it pro-
vides an integral ground for all the equipment that should
be connected to the station ground. Neutral buses are
mounted on molded insulators that are attached to the
rear upright channels. If a transformer is present in the
Iineup, make the necessary connections from the equipment
to the flexible connectors furnished with the transformer as
shown in Figures 13 and 14. Connection hardware is sup-
plied with the equipment. The ground connection bar in
the bus'entrance compartment will be shipped turned in.
This bar should be reassembled in the correct position and
connected at the offset portion to the transformer ground
pad with a 1/z inch bolt. Consult transforiner instructions
for proper connection procedure.
All bolted bus joints should be made up using the proper
torque values as shown in Table A.
5. Bolt or weld the equipment to the foundation as
specified under "Anchoring."
6. All shipping supports must be removed from the
switchgear. These are painted yellow.
7. Busway runs must be lined up and connected to the
equipment. Hardware for this joint is furnished with the
busway.
8. Connect control cables between units at the shipping
splits. A tag at the top of the unit adjacent to the split
will indicate where the wires that cross the split are
located. These wires are all tagged and should be laid
across the split and connected to the shipping split terminal
blocks as indicated.
9. Connect control cables to the switchgear unit as follows:
a. When control conduits enter the switchgear from
below, they should not extend more than one inch
above the floor. The control cables may be pulled
through the conduits before or after the switchgear
is installed.
b. Route the control cables from the conduits through
the wiring trough at the side of the cable compart-
ment and connect the cables to the terminal blocks
in accordance with the connection diagrams for the
equipment.
c. If the control conduits enter from above, drill the
top cover within the available space indicated. Con-
trol cables should be routed to the wiring trough
and connected to the terminal blocks as above.
10. Connect the main cables to the units. Before any
main cable connections are made, the cables should be
identified to indicate their phase relationship with equip-
ment. Adequate electrical and mechanical clearances must
be provided between conduits, cables and bus. Where the
cables enter the unit, they can be lashed to cable supports
at the rear of the cable compartment as required. See
Figure 9.
Cable terminals are included with the switchgear, and
are mounted at the ends of the bars in the cable compart-
ment. Check to see that the proper size and quantity of
terminals are located at each connection point, and that
they are positioned correctly to receive cables coming from
above or below. In all cases, carefully follow the cable
manufacturer's recommendations for installation of cable,
as well as the instructions contained in this book.
12