manuals.online logo
Brands
  1. Home
  2. •
  3. Brands
  4. •
  5. GE
  6. •
  7. Industrial Electrical
  8. •
  9. GE AKD-8 User manual

GE AKD-8 User manual

GEH
-
5687
A
Installation
Manual
#
:
'
•
:
I
GE
AKD
-
8
Low
Voltage
Switchgear
MODS
Installation
And
Maintenance
Instructions
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
Table
of
Contents
CONTENTS
o
.
Page
Page
Description
Description
4
SECTION
IV
—
(
Cont
’
d
)
SECTION
I
—
Introduction
C
.
Foundation
Preparation
C
-
1
.
Indoor
Equipment
C
-
2
.
Outdoor
Equipment
4.2
Assembly
and
Installation
of
Switchgear
Equipment
A
.
General
Requirements
B
.
Detailed
Assembly
and
Installation
Instructions
.
39
B
-
1
.
Indoor
Equipment
B
-
2
.
Outdoor
Equipment
C
.
Anchoring
Switchgear
Equipment
C
-
1
.
Indoor
Equipment
C
-
2
.
Outdoor
Equipment
D
.
Busway
Connections
E
.
Control
Wire
Connections
F
.
Power
Cable
Connections
G
.
Relays
and
Control
Devices
H
.
Breaker
Hoist
H
-
1
.
Indoor
Equipment
H
-
2
.
Outdoor
Equipment
I
.
Final
Inspection
35
4
1.1
General
Information
1.2
Instruction
Book
Arrangement
1.3
Related
Publications
35
4
38
5
SECTION
II
—
Receiving
,
Handling
,
and
Storage
39
6
39
6
2.1
Receiving
A
.
Equipment
Packages
B
.
Inspecting
for
Damage
C
.
Filing
a
Claim
2.2
Handling
A
.
Lifting
B
.
Rollers
C
.
Forklifts
D
.
Jacks
2.3
Storage
A
.
Switchgear
B
.
Circuit
Breakers
SECTION
III
—
Description
3.1
General
3.2
Summary
Description
3.3
Compartment
Area
3.4
Instrument
Tray
3.5
Breaker
Compartment
3.6
Circuit
Breakers
A
.
AKR
-
30
Breaker
B
.
AKRU
-
30
Fused
Breaker
C
.
AKR
-
30
L
Breaker
D
.
AKR
-
50
Breaker
E
.
AKRU
-
50
Fused
Breaker
F
.
AKRT
-
50
Breaker
G
.
AKR
-
75
Breaker
H
.
AKR
-
100
Breaker
I
.
AKR
-
125
Breaker
3.7
Fuse
Rollout
Elements
A
.
AKR
-
75
Fuse
Rollout
Carriage
B
.
AKR
-
100
Fuse
Rollout
Carriage
3.8
Compartments
for
Future
Breakers
3.9
Auxiliary
/
Transition
Sections
3.10
Bus
Area
A
.
Busing
System
B
.
INSUL
-
BAR
Bus
Insulation
System
..
.
.
3.11
Feeder
Cable
and
Busway
Compartment
3.12
Ground
Bus
3.13
AKD
-
8
Outdoor
Switchgear
39
6
46
6
47
6
48
7
49
7
49
9
49
9
50
11
50
12
51
12
51
12
53
13
53
I
)
13
13
SECTION
V
—
Installing
and
Removing
Circuit
Breakers
16
54
16
54
18
5.1
General
A
.
Inspection
and
Preparation
of
Circuit
Breakers
B
.
Circuit
Breaker
Installation
C
.
Rejection
Feature
24
5.2
Installing
the
AKR
Circuit
Breaker
A
.
Prior
to
Installation
B
.
Installation
Procedures
25
5.3
Mounting
the
AKR
-
75
/
100
/
125
Circuit
Breaker
on
the
Drawout
Mechanism
25
5.4
Removing
the
AKR
-
30
/
50
/
T
50
and
AKRU
-
30
/
50
Circuit
25
5.5
Removing
the
AKR
-
75
/
100
/
125
Circuit
Breakers
25
5.6
Installing
and
Removing
AKRU
-
30
/
50
Fused
Circuit
Breaker
26
5.7
Installing
Fuses
to
AKRU
-
30
/
50
Circuit
Breakers
26
5.8
Installing
and
Removing
Fuse
Rollout
Elements
(
FRO
)
—
30
-
inch
Wide
Compartments
3
Q
SECTION
VI
—
Testing
and
Inspection
32
6.1
General
33
6.2
Key
Interlocks
33
6.3
Breaker
Operation
Test
6.4
MicroVersaTrip
RMS
-
9
Programmer
35
6.5
Epic
MicroVersaTrip
Programmer
35
6.6
Final
Steps
to
Be
Taken
Before
Energizing
Equipment
54
24
54
24
54
24
55
55
25
55
25
58
25
59
25
59
60
25
60
62
28
64
64
64
64
64
SECTION
IV
—
Equipment
Installation
65
4.1
General
A
.
Site
Location
B
.
Foundation
Requirements
65
35
35
2
Courtesy of NationalSwitchgear.com
Table
of
Contents
c
>
CONTENTS
Description
Description
Page
Page
SECTION
VII
—
Operating
the
Switchgear
.
.
.
.
66
SECTION
IX
—
Maintaining
the
Switchgear
74
7.1
Circuit
Breaker
Operation
A
.
General
B
.
Manually
Operated
Breakers
B
-
1
.
Closing
Manually
Operated
AKR
Circuit
Breakers
B
-
2
.
Tripping
Manually
Operated
AKR
Circuit
Breakers
C
.
Electrically
Operated
Breakers
D
.
Electrical
Tripping
of
AKR
Breakers
7.2
Circuit
Breaker
Drawout
Operation
A
.
Breaker
Positions
B
.
Drawout
Operation
7.3
Front
Doors
A
.
Operation
B
.
Removal
and
Installation
B
-
1
.
Door
Removal
B
-
2
.
Door
Installation
7.4
AKD
-
8
Switchgear
Accessories
A
.
Future
Circuit
Breaker
Key
Interlock
B
.
Circuit
Breaker
Key
Interlock
B
-
1
.
General
B
-
2
.
Key
Interlock
Operation
Check
C
.
Rackout
Mechanism
Padlock
Device
C
-
1
.
General
C
-
2
.
Padlocking
the
AKR
-
30
/
50
/
T
50
and
AKRU
-
30
/
50
Breakers
C
-
3
.
Padlocking
the
AKR
-
75
/
100
/
125
Breakers
.
.
.
.
69
D
.
Installing
and
Removing
Metering
CT
'
s
E
.
Removing
Shutter
Units
E
-
1
.
Removing
an
AKR
-
30
/
50
or
AKRU
-
30
/
50
Shutter
Unit
E
-
2
.
Removing
an
AKR
-
75
/
100
or
Fuse
Rollout
Shutter
Unit
F
.
Installing
a
Shutter
Unit
F
-
1
.
Installing
an
AKR
-
30
/
50
or
AKRU
-
30
/
50
Shutter
Unit
F
-
2
.
Installing
an
AKR
-
75
/
100
Fuse
Rollout
Shutter
Unit
66
66
74
9.1
Maintenance
Requirements
A
.
General
9.2
Breaker
and
Instrument
Compartments
A
.
Breakers
A
-
1
.
Test
for
Proper
Operation
A
-
2
.
Checks
after
Breaker
is
De
-
energized
A
-
3
.
Lubrication
B
.
Instruments
,
Instrument
Transformers
,
and
Relays
C
.
Breaker
Compartment
Interiors
9.3
Bus
Area
9.4
Cable
and
Busway
Compartment
9.5
Over
-
all
Switchgear
9.6
Paint
Refinishing
9.7
Circuit
Breaker
Lifting
Mechanism
66
74
74
66
74
74
66
74
66
75
66
66
75
66
75
67
75
67
75
76
67
76
67
67
76
67
APPENDICES
68
68
Page
Description
68
68
77
A
.
Torque
Values
B
.
Circuit
Breaker
Rejection
Features
C
.
Circuit
Breaker
Ratings
D
.
Circuit
Breaker
Accessory
Device
Ratings
E
.
Circuit
Breaker
Weights
F
.
Circuit
Breaker
Repetitive
Duty
Data
G
.
Fuses
for
AKRU
-
30
/
50
and
FRO
Elements
68
77
68
81
68
82
84
68
84
85
69
69
70
l
71
72
These
instructions
do
not
purport
to
cover
all
details
or
variations
in
equipment
nor
to
provide
for
every
possible
contingency
to
be
met
in
con
-
nection
with
installation
,
operation
or
mainte
-
nance
.
Should
further
information
be
desired
or
should
particular
problems
arise
which
are
not
covered
sufficiently
for
the
Purchaser
’
s
purposes
,
the
matter
should
be
referred
to
the
General
Elec
-
tric
Company
.
These
instructions
are
intended
for
use
by
qualified
personnel
only
.
72
73
SECTION
VIII
—
Energizing
the
Switchgear
73
8.1
Before
Energizing
8.2
Energizing
A
.
Energizing
Procedures
73
73
73
3
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
I
—
Introduction
1.1
—
General
Information
This
manual
contains
procedures
for
receiving
,
handling
,
storage
,
equipment
installation
,
operation
,
and
maintenance
and
service
of
AKD
-
8
Low
-
voltage
Switchgear
.
1.2
—
Instruction
Book
Arrangement
Information
and
procedures
in
this
instruction
book
are
divided
into
sections
as
follows
:
•
SECTION
I
,
INTRODUCTION
,
gives
a
brief
account
of
the
equipment
’
s
function
and
provides
for
general
information
,
and
applicable
data
for
the
equipment
and
its
components
.
•
SECTION
II
,
RECEIVING
,
HANDLING
AND
STORAGE
,
describes
procedures
required
for
receiving
and
han
-
dling
the
equipment
and
how
to
prepare
it
for
short
-
or
long
-
term
storage
.
•
SECTION
III
,
DESCRIPTION
,
describes
the
AKD
-
8
Low
-
voltage
Switchgear
and
its
various
components
.
Included
are
the
section
enclosure
,
breaker
compart
-
ment
,
circuit
breakers
,
instrument
panels
and
instru
-
ment
trays
,
bus
bar
arrangement
,
incoming
cable
and
busway
,
ground
and
neutral
bus
,
outdoor
equipment
,
and
auxiliary
section
.
This
section
also
explains
how
the
electrical
and
mechanical
components
perform
their
assigned
functions
.
•
SECTION
IV
,
EQUIPMENT
INSTALLATION
,
provides
the
information
needed
prior
to
installation
,
site
location
and
foundation
requirements
,
and
how
to
anchor
the
equipment
properly
and
safely
.
It
also
covers
installation
of
peripheral
equipment
and
includes
information
on
electrical
connections
and
mechanical
construction
.
•
SECTION
V
,
INSTALLING
AND
REMOVING
CIRCUIT
BREAKERS
,
gives
a
step
-
by
-
step
procedure
for
lifting
the
breaker
from
the
floor
,
installing
it
on
rackout
rails
,
and
moving
it
into
the
connected
position
.
A
further
pro
-
cedure
is
given
to
withdraw
a
breaker
,
remove
it
from
the
rackout
rails
,
and
lower
it
to
the
floor
.
Also
included
is
a
description
of
the
rejection
system
provided
to
avoid
the
inadvertent
use
of
an
incorrect
breaker
in
a
breaker
compartment
.
•
SECTION
VI
,
TESTING
AND
INSPECTION
,
reviews
items
which
should
be
tested
or
inspected
prior
to
energizing
and
operating
the
switchgear
.
•
SECTION
VII
,
OPERATING
THE
SWITCHGEAR
,
covers
how
to
operate
the
breakers
,
and
contains
information
concerning
draw
-
out
provisions
,
doors
,
and
various
accessories
.
•
SECTION
VIII
,
ENERGIZING
THE
SWITCHGEAR
,
outlines
the
steps
to
be
taken
before
and
during
the
electrical
energization
of
the
equipment
.
NOTE
:
The
personnel
responsible
for
installing
,
operating
,
and
servicing
this
equipment
should
be
thoroughly
familiar
with
the
contents
of
this
manual
.
Before
any
installation
work
is
performed
,
thoroughly
read
and
understand
the
material
in
this
instruction
manual
and
the
drawings
furnished
with
the
equipment
.
The
documenta
-
tion
shipped
with
the
equipment
includes
the
Summary
,
Front
View
,
Elementary
Diagram
,
and
Instruction
Book
.
This
material
is
located
in
a
forward
compartment
tagged
“
INSTRUCTIONS
IN
THIS
COMPARTMENT
.
”
The
documen
-
tation
provides
all
of
the
information
necessary
for
installa
-
tion
of
the
switchgear
.
When
requesting
information
from
the
General
Electric
Company
,
include
the
complete
data
appearing
on
the
equipment
nameplate
,
requisition
number
,
summary
number
,
and
elementary
diagram
number
.
The
nameplate
is
located
inside
one
of
the
following
four
locations
:
1
.
the
left
-
hand
auxiliary
/
transition
compartment
(
if
included
with
the
equipment
)
,
2
.
the
right
-
hand
auxiliary
/
transition
compartment
(
if
a
left
-
hand
auxiliary
/
transition
compartment
is
not
included
)
,
3
.
the
left
-
hand
main
breaker
compartment
(
if
no
auxiliary
/
transition
compartment
is
included
)
,
or
4
.
the
right
-
hand
main
breaker
compartment
(
if
the
equip
-
ment
is
supplied
without
a
main
breaker
compartment
located
on
the
left
-
hand
end
of
the
equipment
)
.
When
requesting
information
concerning
any
specific
item
furnished
with
the
switchgear
,
refer
to
that
item
by
descrip
-
tion
,
part
number
,
its
location
within
this
manual
,
and
any
applicable
drawing
number
.
Any
material
external
to
the
equipment
,
which
may
be
required
to
meet
local
codes
(
such
as
mats
,
screens
,
railings
,
etc
.
)
,
is
not
furnished
by
the
General
Electric
Company
.
If
there
are
any
questions
or
requirements
not
covered
in
this
manual
or
in
the
accompanying
drawings
,
please
contact
the
local
sales
office
of
the
General
Electric
Company
.
4
Courtesy of NationalSwitchgear.com
SECTION
I
—
Introduction
•
SECTION
IX
,
MAINTAINING
THE
SWITCHGEAR
,
pro
-
vides
instructions
for
all
preventive
maintenance
,
ser
-
vicing
,
and
lubrication
information
for
the
switchgear
equipment
.
Included
is
service
and
maintenance
data
for
the
circuit
breakers
,
instrument
compartments
,
instruments
,
bus
bar
joints
,
and
cable
and
busway
con
-
nections
.
This
section
also
includes
paint
refinishing
requirements
.
•
APPENDICES
A
through
G
contain
information
concern
-
ing
screw
and
bolt
torque
values
,
circuit
breaker
ratings
,
rejection
features
,
accessory
device
ratings
,
repetitive
duty
data
,
and
fuse
data
.
In
addition
to
instruction
books
,
the
following
drawings
will
be
supplied
as
required
for
each
order
of
AKD
-
8
switchgear
equipment
:
1
.
General
arrangement
drawings
,
including
front
view
and
floor
plan
.
2
.
Elementary
and
connection
drawings
(
or
wiring
routing
tables
)
which
indicate
and
identify
test
and
connection
points
including
terminal
blocks
,
device
studs
,
switch
con
-
tact
developments
,
and
remote
connections
.
3
.
Summary
of
switchgear
equipment
which
is
a
list
of
all
the
components
furnished
with
the
switchgear
,
including
the
breakers
,
identified
by
catalog
number
.
These
are
all
the
documents
necessary
to
install
,
operate
,
and
maintain
the
equipment
.
One
complete
set
of
drawings
and
instruction
books
is
shipped
with
the
equipment
.
!
1.3
—
Related
Publications
I
Addendums
to
this
instruction
book
are
the
available
service
and
maintenance
publications
supplied
separately
for
circuit
breakers
,
relays
and
other
devices
not
described
in
this
instruction
book
.
Fig
.
1
-
1
.
General
Electric
AKD
-
8
Low
-
voltage
Switchgear
5
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
II
—
Receiving
,
Handling
,
and
Storage
2.1
—
Receiving
A
.
Equipment
Packages
Every
package
leaving
the
factory
is
plainly
marked
with
the
case
number
,
requisition
number
,
and
customer
’
s
order
number
.
If
the
equipment
has
been
split
for
shipment
,
the
section
numbers
of
the
equipment
enclosed
in
each
shipping
package
are
identified
.
NOTE
:
To
avoid
the
loss
of
any
parts
when
unpacking
,
the
contents
of
each
container
should
be
carefully
checked
against
the
packing
list
before
discarding
the
packing
material
.
The
contents
of
each
shipping
package
are
listed
on
the
Master
Packing
List
.
In
addition
,
this
list
includes
the
number
of
the
shipping
crate
in
which
miscellaneous
parts
needed
to
install
and
operate
the
equipment
(
such
as
hardware
,
con
-
tact
lubricant
,
touch
-
up
paint
,
breaker
closing
devices
,
etc
.
)
are
located
.
Normally
,
such
devices
are
packed
in
a
card
-
board
carton
and
the
carton
secured
in
an
empty
switchgear
compartment
.
See
Fig
.
2
-
1
.
If
such
items
are
packed
in
a
switchgear
section
instead
of
a
separate
crate
,
the
list
will
indicate
the
appropriate
section
number
in
which
they
are
stored
.
Large
items
(
such
as
hoist
dollies
and
hoist
carriages
used
with
indoor
equipment
)
will
always
be
shipped
in
sepa
-
rate
crates
or
cartons
.
See
Fig
.
2
-
2
.
B
.
Inspecting
for
Damage
All
equipment
leaving
the
factory
is
carefully
inspected
and
packed
by
personnel
experienced
in
the
proper
handling
and
packing
of
electrical
equipment
.
Upon
receipt
of
any
equip
-
ment
,
immediately
perform
a
visual
inspection
to
ascertain
if
any
damage
has
been
sustained
in
shipping
or
if
there
are
any
loose
parts
.
All
circuit
breakers
are
shipped
separately
in
individual
con
-
tainers
with
the
breaker
in
the
open
position
.
Circuit
break
-
ers
should
be
unpacked
and
visually
inspected
for
damage
or
loose
parts
as
soon
as
possible
after
they
have
been
received
.
Be
sure
to
inspect
all
devices
mounted
or
packed
inside
compartments
of
each
section
to
see
if
any
have
been
dis
-
lodged
or
damaged
.
C
.
Filing
a
Claim
If
any
damage
is
evident
,
or
indication
of
rough
handling
is
visible
,
file
a
claim
for
damage
at
once
with
the
transporta
-
tion
company
and
notify
the
nearest
General
Electric
Company
Sales
Office
immediately
.
Information
on
dam
-
aged
parts
,
part
number
,
case
number
,
requisition
number
,
etc
.
,
should
accompany
the
claim
.
Fig
.
2
-
1
.
Packaging
of
loose
material
for
shipment
Fig
.
2
-
2
.
Carton
containing
breaker
lifting
device
6
Courtesy of NationalSwitchgear.com
SECTION
II
—
Receiving
,
Handling
,
and
Storage
2.2
—
Handling
Utilize
four
equal
length
cables
and
an
overhead
crane
,
each
with
a
minimum
load
rating
of
twice
the
weight
of
the
switchgear
.
Example
:
Switchgear
Section
Weight
=
5
,
000
pound
.
The
crane
and
the
four
lift
cables
must
have
a
minimum
load
lifting
capacity
of
10
,
000
pounds
.
NOTE
:
It
is
preferable
to
leave
the
shipping
skids
in
place
under
the
switchgear
until
it
reaches
its
final
location
.
The
equipment
should
be
installed
in
its
final
location
prior
to
installing
the
circuit
breakers
.
NOTE
:
The
angle
between
the
cables
and
the
top
of
the
equipment
must
be
at
least
45
degrees
.
If
this
is
not
possible
because
of
lack
of
headspace
,
spreader
bars
must
be
used
.
Also
,
lift
cables
with
greater
load
capability
may
be
necessary
,
depending
upon
the
angle
between
the
cables
and
the
crane
hook
.
A
.
Lifting
The
switchgear
sections
are
best
handled
by
lifting
with
a
crane
as
shown
in
Fig
.
2
-
3
.
Removable
lifting
plates
are
pro
-
vided
,
as
standard
equipment
,
on
the
top
of
each
switchgear
section
.
To
preserve
the
external
appearance
of
the
equip
-
ment
,
it
is
suggested
that
the
lifting
plates
be
left
in
place
except
where
adjacent
equipments
must
be
bolted
together
,
i
.
e
.
shipping
splits
,
etc
.
Connect
a
cable
from
the
crane
to
the
four
lifting
plates
lo
-
cated
on
the
top
-
front
and
rear
of
the
switchgear
(
Fig
.
2
-
3
)
.
Fig
.
2
-
3
.
Recommended
method
of
lifting
AKD
-
8
enclosure
7
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
II
—
Receiving
,
Handling
,
and
Storage
ft
Fig
.
2
-
4
.
Location
of
lifting
plates
AKD
-
8
outdoor
enclosure
Fig
.
2
-
5
.
Recommended
method
of
lifting
AKD
-
8
outdoor
enclosure
by
crane
using
cable
spreader
8
Courtesy of NationalSwitchgear.com
SECTION
II
—
Receiving
,
Handling
,
and
Storage
Take
up
the
slack
in
the
lifting
device
very
carefully
and
man
-
ually
stabilize
the
switchgear
to
prevent
it
from
rotating
.
NOTE
:
Do
not
attempt
to
lift
or
move
the
equip
-
ment
with
a
forklift
positioned
in
the
front
or
rear
of
the
equipment
.
WARNING
:
DO
NOT
STAND
UNDER
SWITCH
-
GEAR
WHILE
IT
IS
BEING
MOVED
.
SERIOUS
INJURY
MAY
OCCUR
IF
THE
CABLES
OR
LIFT
-
ING
DEVICE
FAIL
.
3
.
Position
one
man
in
the
front
and
one
man
in
the
rear
of
the
switchgear
to
stabilize
the
equipment
as
it
is
being
raised
.
4
.
Position
one
roller
under
the
skids
close
to
the
raised
end
of
the
line
-
up
.
5
.
Carefully
lower
the
gear
until
it
rests
on
the
roller
as
shown
in
Fig
.
2
-
7
.
6
.
Repeat
the
lifting
process
at
the
other
end
and
place
the
appropriate
number
of
rollers
under
the
skids
spacing
them
evenly
across
the
width
of
the
line
-
up
.
2
CAUTION
:
GENTLY
LOWER
THE
SWITCHGEAR
SECTION
ONTO
THE
LEVEL
SITE
LOCATION
.
IF
THE
SWITCHGEAR
IS
ROUGHLY
HANDLED
OR
JARRED
,
IT
IS
POSSIBLE
TO
DAMAGE
OR
MIS
-
ALIGN
INTERNAL
COMPONENTS
.
Methods
of
lifting
outdoor
switchgear
sections
are
much
the
same
as
for
indoor
equipment
except
the
lifting
plates
are
provided
at
the
base
of
the
structure
.
See
Fig
.
2
-
4
.
If
lifting
outdoor
switchgear
sections
,
side
support
timbers
must
be
placed
along
the
sides
to
prevent
any
damage
that
could
be
caused
by
the
lifting
cables
.
In
addition
,
a
spreader
bar
must
be
inserted
between
each
lift
cable
,
both
front
and
rear
,
above
the
switchgear
equipment
as
shown
in
Fig
.
2
-
5
.
Proceed
to
lift
and
place
the
outdoor
switchgear
utilizing
all
the
precautions
and
requirements
that
apply
to
lifting
the
indoor
switchgear
.
The
lifting
plates
,
Fig
.
2
-
4
,
should
be
removed
after
the
equipment
is
permanently
anchored
so
passageways
at
the
ends
of
the
equipment
will
not
be
obstructed
.
Fig
.
2
-
6
.
Placing
forklift
tines
under
AKD
-
8
equipment
shipping
skid
B
.
Rollers
c
;
3
If
crane
facilities
are
not
available
,
the
equipment
may
be
moved
into
position
by
means
of
construction
rollers
placed
under
the
shipping
skids
.
The
switchgear
may
be
raised
enough
for
the
placement
of
rollers
by
means
of
a
fork
lift
or
jack
.
There
should
never
be
less
than
four
rollers
under
the
equip
-
ment
unless
the
line
-
up
is
less
than
five
feet
long
.
Use
one
roller
for
each
18
inches
of
equipment
length
.
9
C
.
Forklifts
When
using
a
forklift
to
raise
the
line
-
up
to
position
rollers
underneath
,
proceed
as
follows
:
1
.
Expand
forklift
tines
to
their
maximum
(
widest
)
extension
.
2
.
Carefully
insert
tines
of
forklift
below
one
side
of
the
switchgear
line
-
up
at
the
approximate
center
of
the
panel
as
shown
in
Fig
.
2
-
6
.
Fig
.
2
-
7
.
Placement
of
rollers
under
shipping
skid
9
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
II
—
Receiving
,
Handling
,
and
Storage
LIFTING
PLATES
MUST
BE
REMOVED
WHERE
SECTIONS
ARE
JOINED
ROLLER
v
£
E
o
KS
FRONT
VIEW
SIDE
VIEW
v
Fig
.
2
-
8
.
Method
of
rolling
equipment
into
place
;
WOOD
BEAM
SIDE
VIEW
Fig
.
2
-
9
.
Recommended
method
of
jacking
AKD
-
8
outdoor
equipments
10
Courtesy of NationalSwitchgear.com
SECTION
II
—
Receiving
,
Handling
,
and
Storage
JACKING
TIMBER
NOT
FURNISHED
WITH
SWITCHGEAR
REAR
OR
FRONT
v
CABLE
r
~
W
|
]
1
JACK
HERE
PARTIAL
SIDE
VIEW
FOR
JACKING
PARTIAL
FRONT
OR
REAR
VIEW
OF
JACKING
C
_
2
iJ
=
=
V
888
A
FRONT
VIEW
Fig
.
2
-
10
.
Recommended
method
of
jacking
AKD
-
8
outdoor
enclosure
7
.
Carefully
lower
the
gear
until
it
rests
on
the
rollers
(
Fig
.
2
-
7
)
.
CAUTION
:
DO
NOT
PLACE
JACKS
IN
ANY
OTHER
LOCATION
OTHER
THAN
THE
FRONT
AND
REAR
CORNERS
OF
THE
SWITCHGEAR
.
DOING
SO
MAY
RESULT
IN
SERIOUS
DAMAGE
TO
THE
SWITCHGEAR
EQUIPMENT
.
NOTE
:
If
shipping
skids
are
removed
prior
to
final
placement
of
equipment
,
rollers
may
only
be
used
to
move
the
equipment
in
a
direction
parallel
to
the
front
.
2
.
Raise
the
switchgear
evenly
and
just
enough
to
position
a
roller
beneath
the
equipment
.
Gently
lower
the
switchgear
onto
the
roller
.
Repeat
the
procedure
at
the
opposite
end
of
the
switchgear
,
raising
the
gear
far
enough
to
place
the
appropriate
number
of
rollers
under
the
skids
,
spacing
them
evenly
across
the
width
of
the
line
-
up
.
Gently
lower
the
gear
onto
the
rollers
.
3
.
While
carefully
pushing
the
switchgear
to
its
final
site
position
,
the
rollers
that
are
freed
from
the
rear
of
the
switch
-
gear
are
then
repositioned
at
the
forward
end
.
This
proce
-
dure
should
be
continued
until
the
switchgear
is
in
its
final
location
.
4
.
When
the
switchgear
is
in
its
final
position
,
remove
all
lug
bolts
holding
the
shipping
skids
to
the
switchgear
line
-
up
.
5
.
Place
one
jack
at
each
corner
,
front
and
rear
,
of
the
switchgear
.
Carefully
raise
the
line
-
up
evenly
and
remove
the
rollers
and
the
shipping
skids
.
Evenly
lower
the
line
-
up
to
the
floor
and
remove
the
jacks
.
8
.
While
carefully
pushing
the
switchgear
to
its
final
site
position
,
the
rollers
that
are
freed
from
the
rear
of
the
switch
-
gear
are
then
repositioned
at
the
forward
end
.
This
proce
-
dure
should
be
continued
until
the
switchgear
is
in
its
final
location
.
See
Fig
.
2
-
8
.
9
.
When
the
switchgear
is
in
its
final
position
,
remove
all
lug
bolts
holding
the
shipping
skids
to
the
switchgear
line
-
up
.
10
.
Insert
the
tines
of
the
forklift
at
one
end
of
the
line
-
up
,
raise
slightly
,
and
remove
the
loose
rollers
.
11
.
Lower
the
end
of
the
gear
carefully
to
the
floor
.
12
.
Raise
the
other
end
of
the
line
-
up
slightly
and
remove
the
remaining
roller
at
that
end
.
D
.
Jacks
Jacks
may
be
used
in
place
of
forklifts
to
raise
and
lower
switchgear
.
1
.
Place
a
jack
under
the
front
and
rear
corners
of
one
end
of
the
line
-
up
.
Figures
2
-
9
and
2
-
10
illustrate
the
use
of
jacks
with
outdoor
equipment
.
11
Courtesy of NationalSwitchgear.com
\
AKD
-
8
Low
-
voltage
Switchgear
SECTION
II
—
Receiving
,
Handling
,
and
Storage
$
2.3
—
Storage
A
.
Switchgear
each
section
and
supported
so
the
bulb
will
not
touch
adja
-
cent
materials
.
On
outdoor
switchgear
equipment
,
this
may
be
accomplished
by
making
a
temporary
power
supply
con
-
nection
to
the
heaters
already
installed
in
the
equipment
.
If
it
is
necessary
to
store
the
switchgear
equipment
for
any
length
of
time
,
the
following
precautions
should
be
taken
to
prevent
corrosion
or
deterioration
.
1
.
Remove
protective
covering
.
Check
thoroughly
for
damage
.
2
.
Store
in
a
clean
,
dry
,
rodent
-
free
location
with
moder
-
ate
temperature
and
provide
protective
coverings
to
prevent
dirt
,
water
,
or
other
foreign
substances
from
entering
the
switchgear
.
CAUTION
:
IF
THE
SPACE
HEATERS
ARE
TO
BE
TEMPORARILY
ENERGIZED
FROM
EXTERNAL
SOURCE
,
IT
IS
IMPORTANT
TO
REMOVE
THE
FUSES
ON
THE
SECONDARY
SIDE
OF
THE
CONTROL
POWER
TRANSFORMER
.
THIS
PRECAUTION
IS
TO
PREVENT
A
FEEDBACK
OF
HIGHER
VOLTAGE
TO
OTHER
PORTIONS
OF
THE
EQUIPMENT
THROUGH
THE
CPT
PRIMARY
.
CAUTION
:
REMOVE
ALL
CARTONS
,
CONTAIN
-
ERS
AND
ANY
OTHER
MISCELLANEOUS
PACK
-
AGING
AND
PACKING
MATERIAL
FROM
INSIDE
THE
SWITCHGEAR
SECTIONS
BEFORE
ENER
-
GIZING
ANY
INTERNAL
HEATERS
.
TO
PREVENT
FIRE
,
REMOVE
ANY
PLASTIC
OR
POLYETHYL
-
ENE
SHROUDING
FROM
THE
SWITCHGEAR
SECTIONS
BEFORE
ENERGIZING
ANY
INTER
-
NAL
HEATERS
.
B
.
Circuit
Breakers
If
circuit
breakers
are
not
to
be
placed
into
service
at
once
,
remove
them
from
their
shipping
cartons
and
thoroughly
inspect
them
for
damage
.
If
the
breakers
are
in
satisfactory
condition
,
replace
the
breakers
in
their
shipping
cartons
for
storage
.
Do
not
remove
the
circuit
breaker
shipping
mem
-
bers
at
this
time
.
Store
the
circuit
breakers
in
a
clean
,
dry
location
in
an
upright
position
.
They
must
be
properly
supported
to
pre
-
vent
bending
of
the
studs
or
damage
to
any
of
the
breaker
parts
.
Do
not
remove
any
protective
grease
until
the
circuit
breakers
are
ready
to
be
installed
.
A
plastic
or
canvas
-
type
cover
should
be
provided
to
reduce
the
possibility
of
dam
-
age
to
the
breakers
due
to
dust
and
water
.
3
.
If
dampness
or
condensation
may
be
encountered
in
the
storage
location
,
heaters
must
be
placed
inside
the
switchgear
sections
to
prevent
moisture
damage
.
Approxi
-
mately
250
watts
of
heat
in
each
section
is
required
.
Incan
-
descent
lamps
may
be
used
for
this
purpose
.
These
lamps
should
be
located
in
the
bottom
breaker
compartment
of
12
Courtesy of NationalSwitchgear.com
SECTION
III
—
Description
3.2
—
Summary
Description
General
Electric
AKD
-
8
Low
-
voltage
Switchgear
is
a
free
-
standing
assembly
of
metal
-
enclosed
sections
containing
low
-
voltage
power
circuit
breakers
,
bus
bars
,
cable
termina
-
tion
provisions
,
auxiliary
power
circuit
protective
devices
,
controls
,
and
instrumentation
.
It
may
also
be
an
integral
part
of
a
load
center
unit
substation
,
either
single
-
ended
or
double
-
ended
.
3.1
—
General
This
section
contains
a
description
of
the
General
Electric
AKD
-
8
Low
-
voltage
Switchgear
.
It
also
describes
the
func
-
tions
of
the
electrical
and
mechanical
systems
.
Figure
3
-
1
shows
the
installation
of
a
typical
single
-
ended
load
center
unit
substation
.
Fig
.
3
-
1
.
Installation
of
a
typical
AKD
-
8
Load
Center
Unit
Substation
13
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
III
—
Description
Figure
3
-
2
is
a
side
view
of
a
typical
section
showing
compartmentation
.
Figure
3
-
3
is
an
outline
of
a
typical
single
-
ended
load
center
unit
substation
illustrating
the
nomenclature
used
for
all
equipment
.
INTER
-
SECTIONAL
CONTROL
WIRING
TROUGH
I
T
COMPARTMENT
DOOR
NEUTRAL
BUS
BREAKER
OR
INSTRUMENT
COMPARTMENT
INSTRUMENT
TRAY
VERTICAL
RISER
BUS
BARS
CABLE
TERMINATION
AREA
1
BREAKER
COMPARTMENT
RUN
BACK
AND
CABLE
TERMINATION
A
CABLE
COMPARTMENT
DOORS
VERTICAL
CONTROL
WIRE
GUTTER
BREAKER
COMPARTMENT
u
-
V
INSTRUMENT
TRAY
N
B
MAIN
BUS
BARS
COMPARTMENT
DOORS
BREAKER
COMPARTMENT
RUN
BACKS
AND
CABLE
TERMINATION
BREAKER
COMPARTMENT
J
1
C
INSTRUMENT
TRAY
}
ENCLOSED
TROUGH
-
CONTROL
CIRCUIT
(
WHEN
REQUIRED
)
L
BREAKER
COMPARTMENT
C
%
GROUND
2
BUS
D
Fig
.
3
-
2
.
Side
-
view
section
of
AKD
-
8
switchgear
14
Courtesy of NationalSwitchgear.com
SECTION
III
—
Description
All
of
the
primary
circuit
switching
and
protective
devices
,
secondary
control
and
metering
devices
,
control
fuses
,
and
instrument
transformers
are
mounted
in
the
enclosure
.
The
breaker
compartments
include
drawout
rails
,
stationary
breaker
contacts
,
interlocks
,
and
necessary
control
and
indi
-
cating
devices
.
The
breakers
are
provided
with
self
-
aligning
primary
and
secondary
disconnecting
contacts
,
breaker
locking
mechanism
,
and
integral
trip
programmer
.
The
indi
-
vidual
sections
,
compartments
,
and
devices
are
described
in
the
following
paragraphs
.
—
LOAD
CENTER
UNIT
SUBSTATION
TRANSFORMER
PRIMARY
SECTION
SHIPPING
PACKAGE
AKD
-
8
LOW
-
VOLTAGE
SECTION
-
SHIPPING
PACKAGE
SHIPPING
PACKAGE
TRANSITION
SECTION
SWITCH
UNIT
BREAKER
SECTIONS
q
A
A
A
B
B
B
A
B
C
C
C
B
f
;
il
1
D
D
D
B
TT
+
H
1
II
O
Fig
.
3
-
3
.
Outline
of
typical
AKD
-
8
Load
Center
Unit
Substation
15
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
III
—
Description
r
'
r
i
j
3.4
—
Instrument
Tray
A
standard
slide
-
out
instrumentation
tray
,
Fig
.
3
-
4
,
is
located
above
each
breaker
compartment
eliminating
cross
-
hinge
wiring
.
When
required
,
optional
feeder
instrumentation
may
be
included
and
mounted
on
the
front
face
of
the
tray
such
as
a
horizontal
-
edgewise
ammeter
,
ammeter
switch
,
pilot
lights
or
annunciator
,
and
test
switches
.
3.3
—
Compartment
Area
The
front
enclosure
of
each
section
is
divided
into
individual
compartments
.
These
compartments
house
either
a
low
-
voltage
power
circuit
breaker
or
are
used
to
mount
instru
-
ments
,
control
components
and
other
ancillary
devices
.
WARNING
:
WITH
THE
STANDARD
SLIDE
-
OUT
INSTRUMENTATION
TRAY
IN
THE
OPEN
POSI
-
TION
,
LIVE
TERMINALS
ARE
EXPOSED
.
TOUCH
-
ING
THESE
TERMINALS
MAY
RESULT
IN
ELECTRICAL
SHOCK
OR
BURN
.
i
i
Fig
.
3
-
4
.
Slide
-
out
instrument
tray
16
Courtesy of NationalSwitchgear.com
SECTION
III
—
Description
Fuses
for
the
close
and
trip
circuits
of
the
electrically
oper
-
ated
breakers
are
mounted
inside
the
tray
and
are
fully
accessible
when
the
tray
is
pulled
out
.
Routine
wiring
inspections
and
fuse
checks
or
fuse
replacements
can
be
performed
with
the
breaker
compartment
door
in
the
closed
position
so
that
operators
are
protected
from
the
energized
primary
circuits
.
The
instrument
tray
also
permits
the
flow
of
ventilating
air
to
the
breaker
compartment
.
The
grille
,
(
5
)
,
Fig
.
3
-
4
,
on
the
tray
face
with
the
openings
(
6
)
in
the
stationary
cover
provide
an
indirect
path
for
the
entrance
of
cooling
air
.
An
instrument
compartment
with
a
recessed
swinging
instru
-
ment
panel
,
Fig
.
3
-
5
,
is
available
as
a
standard
feature
.
These
panels
can
be
used
to
mount
meters
and
/
or
instruments
and
other
devices
associated
with
the
incoming
supply
circuit
.
Switches
used
in
various
control
circuits
may
also
be
installed
on
these
panels
.
Relays
,
fuse
cutouts
and
similar
devices
may
be
installed
in
the
compartment
behind
the
swing
-
out
instrument
panel
or
in
adjacent
compartments
.
Fig
.
3
-
5
.
Recessed
swinging
instrument
panel
17
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
III
—
Description
3.5
—
Breaker
Compartment
Closed
-
door
drawout
circuit
breaker
compartments
,
Fig
.
3
-
6
,
are
standard
construction
with
all
AKD
-
8
switchgear
equip
-
ment
.
The
circuit
breaker
compartment
doors
remain
closed
and
latched
while
the
breaker
is
racked
out
from
the
con
-
nected
position
,
through
test
,
to
the
disconnected
position
.
Breaker
compartment
doors
do
not
have
any
ventilation
slots
,
thus
protecting
operators
from
hot
ionized
gases
which
may
be
vented
by
the
breaker
during
circuit
interrup
-
tion
.
Additionally
,
the
breaker
compartment
,
Fig
.
3
-
7
,
is
enclosed
by
grounded
steel
barriers
on
the
top
,
sides
,
bot
-
tom
,
and
front
.
In
the
back
a
flame
-
retardant
,
arc
track
resis
-
tant
glass
-
filled
polyester
base
minimizes
the
possibility
of
fault
communication
between
compartments
or
to
the
bus
.
Fig
.
3
-
6
.
AKR
-
75
circuit
breaker
compartment
18
Courtesy of NationalSwitchgear.com
SECTION
III
—
Description
*
Fig
.
3
-
7
.
Circuit
breaker
compartment
(
22
-
inch
)
showing
rollout
carriage
for
AKR
-
30
/
50
/
T
50
breakers
19
Courtesy of NationalSwitchgear.com
AKD
-
8
Low
-
voltage
Switchgear
SECTION
III
—
Description
Primary
disconnect
shutters
,
Figs
.
3
-
8
and
3
-
9
,
are
available
as
options
to
provide
protection
against
contact
with
the
energized
stationary
primary
disconnects
when
the
breaker
is
removed
from
its
compartment
.
Shutters
are
supplied
as
standard
components
in
the
main
and
tie
breaker
compart
-
ments
of
double
-
ended
substations
or
dual
-
fed
switchgear
;
additionally
,
they
are
standard
components
in
compartments
containing
reverse
-
fed
devices
(
i
.
e
.
those
compartments
where
the
line
terminals
are
the
bottom
primary
stabs
)
.
The
shutters
are
constructed
from
glass
-
reinforced
polyester
insulating
material
.
NOTE
:
If
a
fuse
rollout
(
FRO
)
carriage
is
used
with
an
AKR
-
75
or
AKR
-
100
circuit
breaker
whose
compartment
is
equipped
with
shutters
,
the
FRO
compartment
will
also
be
equipped
with
shutters
.
Referring
to
Fig
.
3
-
8
,
the
combination
of
the
stationary
bar
-
rier
(
1
)
and
the
shutters
(
movable
barriers
)
prevent
frontal
access
to
the
primary
disconnect
line
and
load
power
stabs
.
Fig
.
3
-
8
.
AKD
-
8
primary
disconnect
shutter
assembly
(
30
-
inch
wide
rollout
carriage
and
compartment
for
AKR
-
75
/
100
breakers
20
Courtesy of NationalSwitchgear.com

Other manuals for AKD-8

2

Other GE Industrial Electrical manuals

GE GTP0060U0101 User manual

GE

GE GTP0060U0101 User manual

GE Entelliguard TU Conversion Kit User manual

GE

GE Entelliguard TU Conversion Kit User manual

GE AKD-6 User manual

GE

GE AKD-6 User manual

GE AF-650 GP Series Operating instructions

GE

GE AF-650 GP Series Operating instructions

GE MicroVersaTrip Plus User manual

GE

GE MicroVersaTrip Plus User manual

GE DS-19 User manual

GE

GE DS-19 User manual

GE PowerMark Plus DEH40228 User manual

GE

GE PowerMark Plus DEH40228 User manual

GE Entellisys 4.0 User guide

GE

GE Entellisys 4.0 User guide

GE QuiXtra 630 Quick start guide

GE

GE QuiXtra 630 Quick start guide

GE RSTi-EP Instructions for use

GE

GE RSTi-EP Instructions for use

GE AKD-6 User manual

GE

GE AKD-6 User manual

GE Spectra Series User manual

GE

GE Spectra Series User manual

GE A-Series II Panelboard User manual

GE

GE A-Series II Panelboard User manual

GE AF-650 GP Series User manual

GE

GE AF-650 GP Series User manual

GE Spectra Series AMC6EB User manual

GE

GE Spectra Series AMC6EB User manual

GE Fuji Electric MICRO-SAVER AF-300 User guide

GE

GE Fuji Electric MICRO-SAVER AF-300 User guide

GE PHI 530.1425.2500 Manual

GE

GE PHI 530.1425.2500 Manual

GE Spectra Series User manual

GE

GE Spectra Series User manual

GE QuiXtra 4000 Quick start guide

GE

GE QuiXtra 4000 Quick start guide

GE THQ Series User guide

GE

GE THQ Series User guide

GE QuiXtra 630 Quick start guide

GE

GE QuiXtra 630 Quick start guide

GE ABB ReliaGear SB User manual

GE

GE ABB ReliaGear SB User manual

GE Entellisys User manual

GE

GE Entellisys User manual

Popular Industrial Electrical manuals by other brands

OEZ CS-BD-T011 Instructions for use

OEZ

OEZ CS-BD-T011 Instructions for use

Mono FG177 Operating and maintenance manual

Mono

Mono FG177 Operating and maintenance manual

Audi 739 964 operating instructions

Audi

Audi 739 964 operating instructions

Murata GRM0225C1E120JA03 Series Reference sheet

Murata

Murata GRM0225C1E120JA03 Series Reference sheet

Murata GRM0225C1E9R6WA03 Series Reference sheet

Murata

Murata GRM0225C1E9R6WA03 Series Reference sheet

Murata GRM155R61A105KE01 Series Reference sheet

Murata

Murata GRM155R61A105KE01 Series Reference sheet

Murata GRM0335C1E2R7WA01 Series Reference sheet

Murata

Murata GRM0335C1E2R7WA01 Series Reference sheet

Circutor Optim EMS-C Series instruction manual

Circutor

Circutor Optim EMS-C Series instruction manual

LEGRAND Bticino 60280036R installation manual

LEGRAND

LEGRAND Bticino 60280036R installation manual

Murata GRJ188R71H224KE11 Series Reference sheet

Murata

Murata GRJ188R71H224KE11 Series Reference sheet

Murata GRM022R60J104ME15 Series Reference sheet

Murata

Murata GRM022R60J104ME15 Series Reference sheet

Murata GRM188R6YA225MA12 Series Reference sheet

Murata

Murata GRM188R6YA225MA12 Series Reference sheet

Eltek Valere PSS30 user manual

Eltek Valere

Eltek Valere PSS30 user manual

Murata GRM0225C1E9R5DA03 Series Reference sheet

Murata

Murata GRM0225C1E9R5DA03 Series Reference sheet

Siemens 8PQ9800-0AA54 operating instructions

Siemens

Siemens 8PQ9800-0AA54 operating instructions

Murata GRM033R71A122KA01 Series Reference sheet

Murata

Murata GRM033R71A122KA01 Series Reference sheet

Murata GRM188R60J105MA01 Series Reference sheet

Murata

Murata GRM188R60J105MA01 Series Reference sheet

Murata GJM0335C1HR20WB01 Series Reference sheet

Murata

Murata GJM0335C1HR20WB01 Series Reference sheet

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.