6.3.3 Heating Circuit menu (User) BS-06-03-03-00-01-BAEN
The Thermal Store HP0 menu allows you to enter settings for
thermal store management.
19) Options →Auto Thermal store pump is switched ON/OFF according to demand and timer programme.
→Off The thermal store pump is switched off
→Constant The thermal store pump runs continuously
20) Options →Full The thermal store is fully charged
Charging switches off when the required thermal store temperature at T3 is reached and also the
required thermal store temperature minus the parameter TSbtm-Boff (-10°C) is reached at T2
→Part The thermal store is partially charged
Charging switches off when the required thermal store temperature is reached at T3 (= parameter
TS top-B off)
21) Thermal store only charged during charging times enabled in "Thermal store timer programme"
6.3.4 Boiler Cascade menu (User) PH-06-03-03-00-01-BAEN
On the Boiler Cascade Parameters menu (only visible on
boiler "A") you can make settings for sequential boiler control.
Second boiler in the cascade system = boiler "B", third boiler =
boiler "C", etc. Boiler "A" must be at address "0" on the router
module, boiler "B" at 1, boiler "C" at 2, etc. After reassigning
addresses on the router module, the boilers have to be
disconnected entirely from the power supply. Only after that
are the settings activated on the boiler.
22) Example 1: Boiler cascade system with one biomass boiler and one external boiler
→10% The external boiler is switched off as soon as the biomass boiler is running at only 90% of its
possible total output of 100%
→50% The external boiler is switched off as soon as the biomass boiler is running at only 50% of its
possible total output of 100%
Example 2: Boiler cascade system with two biomass boilers and one external boiler
→10% The external boiler is switched off as soon as the biomass boilers are running at only 180% of their
combined possible total output of 200%
(Possible total output of biomass boilers = 200% minus 2 x 10% for two boilers = 180%)
→50% The external boiler is switched off as soon as the biomass boilers are running at only 100% of their
combined possible total output of 200%
(Possible total output of biomass boilers = 200% minus 2 x 50% for two boilers = 100%)
19) Status of special output HP0
20) Facility for setting thermal store charging programme
21) Facility for setting thermal store charging times
Facility for setting the thermal store required temperature →Sensor (T3)
Facility for setting the thermal store minimum temperature →Sensor (T3)
For setting time until boiler changeover →0h = no boiler changeover
For setting time delay before second-stage boiler cuts in
Min. output of 1st stage for cut-in of 2nd stage after delay
Max. output of all stages for cut-out of last stage to cut in
For setting time delay before third-stage boiler cuts in
Min. output of all stages for cut-in of 3rd stage after delay
Max. output of all stages for cut-out of last stage to cut in
For setting time delay before fourth-stage boiler cuts in
Min. output of all stages for cut-in of 4th stage after delay
Max. output of all stages for cut-out of last stage to cut in
For setting time delay before cut-in of EXT boiler stage
Min. output of all stages for cut-in of EXT stage after delay
Max. output of all stages for cut-out of last stage to cut in
Facility for switching off external boiler stage →OFF = Ext. boiler stage is switched off
22) For setting cut-out hysteresis for external boiler stage