Farmers Biogas System Installation Protocol
The Farmers Biogas System installation team is composed of a team leader, technician, and helper.
The installation process is divided into two parts: biodigester installation and pipeline installation.
Biodigester Installation Steps:
1.
Check that all conditions are suitable for installation (team leader).
2.
Level the ground (installer + helper).
3.
Compact the ground (installer + helper).
4.
Spread and check the quality of the system (installer + helper).
5.
Mark and excavate for rigid piping and docking straps (team leader).
6.
Install the rigid pipe, docking straps, sink, and 4’’ T connection (technician).
7.
Inflate the system and spread the inner liner.
8.
Place the wooden posts.
9.
Mark and dig the fertilizer pit (customer helper).
10.
Fill the system with water (installation team).
11.
Activate the system (installation team).
Pipeline Installation Steps:
1.
Select the path for the gas pipeline layout (team leader).
2.
Spread and bind the gas piping and cable (team leader).
3.
Connect the stove and water trap (team leader/technician).
4.
Connect the filter (team leader/technician).
5.
Install the pressure release (team leader/technician).
6.
Provide instructions to the customer until commissioning (team leader).
By following these steps, you can ensure that the Farmers Biogas System is installed correctly and efficiently.
Biodigester Installation
1.
Confirm that the installation location is ready (team leader). The installation requires two technicians and a helper
Make sure the customer has:
• 5000 liters of water available.
• Cleared and leveled an area of 9*2.5 meters (if the chosen location is on a slope or a cliff, add a meter on the slope side for
a total of 9 x 3.5 meters).
• Make sure the site is the right size for the biodigester.