13. Inspection of the device
13.1. Initial review
After reading and understanding this manual, the technical service employee responsible for
commissioning the device at the user’s premises is required to:
•verify the delivery and structural integrity,
•set up the lever in the operating position,
•inspection of screw connections and eccentric function,
•test operation with a load of the selected manhole cover (up to 170 kg).
The result of inspection (positive/negative) should be recorded by the inspector in the Review Card
(according to the form –Annex No. 2
After a positive result of the inspection, the lever should be handed over to an employee
(organizational unit) responsible for current operation of the device. The operating personnel should
perform the activities provided for in the initial review andtest work for conducted detachments of the
grate/hatches as part of the training. Any irregularities, the removal of which is beyond the
qualifications of the operating personnel, should be reported to the supervisor.
13.2. Review during setting the structure to the working position
After checking whether the conditions for using the lever in accordance with the intended use, as
described in this manual, have been met, the operator is obliged to:
•verify the structural and equipment integrity and completeness,
•set up the lever structure in the operating position,
•inspection of screw connections and eccentric function.
Any irregularities that are beyond the qualifications of the operating personnel must be reported to
their supervisor.
13.3. Annual review/maintenance after repair
Follow the steps provided for the initial review.
The result of inspection (positive/negative) should be recorded by the inspector in the Review Card
(according to the form –Annex No. 3).