Batteries are delivered in separate transport packages. They should be connected with wires
delivered by the manufacturer. Before the connection the batteries have to be put on the bottom of the
box. First, connect the batteries to the main circuit pack of the power supply, and then connect each
with other. One has to pay due attention to the right polarity of the connection. In case of erroneous
connection of the battery circuit a fuse shall blow.
2.3. Implementation of the collective fault indication
Relay outputs of faults USZ SIECI (MAINS FLT) and USZ BATERII (BATTERY FLT) can be used to
implement the output of the collective fault indication. This will indicate on a single line occurrence of
any event covered by both signals. Either NO or NC contacts of the relays can be used. Both options
are shown on the picture below.
USZ SIECI
USZ BATERII USZ SIECI
USZ BATERII
The visible pictograms representing the contacts of the relays refer to the state when the relays are
not activated (voltage free state). By the fail safe rule this is the state indicating a fault.
3. Switching on for the first time
If all connections have been carried out correctly, then after having the power supply connected to
the mains the indication LEDs ZASILANIE (MAINS), PRACA (OPERATION) (diodes 8 and 9 inside the
box on the circuit pack – see the picture and table in the section 2.2) and POWER (the diode no. 11)
should light up. Additionally, one should hear the sound of the relay attaching the battery bank to the
system. The attaching of the battery happens only when the battery bank voltage is greater than 20.5V.
During the switching on one should perform two checks.
3.1. Checking ability to back up output voltage.
Use a breaker in the electrical installation before the power supply ZSP135-DR to cut off the mains
power. The power supply should switch to the battery mode, keeping voltage on its both outputs. Check
it by whatever probe, e.g. a voltmeter or electric bulb.
This state is indicated by the blinking LED POWER in the door of the power supply. The relay USZ SIECI
(MAINS FLT) shall switch to the inactive state (contacts connected as on the pictogram next to the
terminal). The relay USZ BATERII (BATTERY FLT) shall remain activated. The state of a relay could be
checked, e.g. by an ohmmeter connected to appropriate contacts of the relay.
3.2. Checking the battery circuit
When the power supply operates at presence of the mains power, break the battery circuit by
disconnecting one of its wires. This state shall be detected during the first next test. It could last up to 10
minutes. Similarly, having the circuit connected again, the triggered fault indication shall be cleared
automatically, but no sooner as after the first successful test – which may require another 10 minutes
waiting.
This state should also trigger the indication FAULT in the door of the box and the indication BAT (the red
LED) on the circuit pack of the power supply. The relay USZ BATERII (BATTERY FLT) shall switch to the
inactive state (contacts connected as on the pictogram next to the terminal). The relay USZ SIECI
(MAINS FLT) shall remain activated. The state of a relay could be checked, e.g. by an ohmmeter
connected to appropriate contacts of the relay.