Proteco PMXM01 User manual

PROTECO S.r.l.
Via Neive,77 - 12050 CASTAGNITO (CN) ITALY
Tel. +39 0173 210111 - Fax +39 0173 210199
[email protected] - www.proteco.net
PMXM01
Twinning card for Matrix
Introduction
The Twinning function is used to synchronize twin gates:
therefore there will be a Master gate and a Slave gate.
However it is possible to command each gate individually (to allow
pedestrian opening for example).
The synchronization expects the gates to work at the same speed and
same slow down, no matters if gates have different legth.
Speed will adjust automatically during cruise.
However it is also possible to programm the two Matrix systems
independently, every one with its own working times.
In order to synchronize the two systems and activate the TWINNING
function, it is necessary to plug the TWINNING cad on each system.
In this way both motors will be able to exchange mutual communication.
Both cards shall be wired together using a shielded bipolar cable, while each
Matrix shall be set up, through parameter H.6. one as MASTER and the
other as SLAVE.
Master and slave
The Master system is the main one: any safety device, start wired contact,
and remote control shall be connected here. It starts any duty cycle.
The Slave system is free of any safety device, start wired contact and
remote control, but it can stop the Master gate when encountering an
obstacle. In this case both motors will reverse.
The Slave system starts just when the Master system starts and stops
when the Master system stops. If the Master gate has completed the duty
cycle and the Slave not yet, the Slave will be allowed to complete it anyhow.
Under these conditions, the following two scenarios may be set up (the
Master gate commands)
1Full opening: Master and Slave start opening together and stop when
opening is completed; if automatic closing is set, both Master and Slave will
start closing together.
2Pedestrian/partial opening: the Master will activate the pedestrian
partial opening while the Slave will remain still.
If automatic closing has been set, the Master will close.
The Slave can open and close independently (step-by-step mode),
remaining the Master still. The automatic closing even if set up, will remain
OFF. In any moment the MASTER may command over the SLAVE.
The Master works even when the Slave is OFF or temporarily
disconnected. It is important to choose which motor will be MASTER and
which will be SLAVE since they behave in a different way.
Installation manual
Wiring diagram
Above a TWINNING card top view showing wirings (a shielded or RG58
cable is required). A small section cable will be sufficient, since it is used
just for signal tranfer.
The TWINNING card has to be plugged in the proper seat included in the
control unit: the according wire can come out from terminals block,
INTERFACE CARD or antenna slot, or it is possible to drill a hole on the
plastic housing.
Here below some possible suggestions about where the card wire may
come out:
GND
SHIELD
CORE
DATA
ANTENNA
INTERFACE CARD
After outlining the wiring plan, proceed to remove the plastic cover: pull
out the antenna connector, loose the 2 screws and open the housing.
If you decided to drill a hole to let the wires pass through, do it at this
stage.
Wire the signal and core of the shielded cable to the TWINNING card
terminals, and then plug the card in the slot.
Matrix is available in different models, but the card location is the same
and has just one plug orientation that prevents incorrect insertion.
TERMINAL BLOCK
PROTECO S.r.l.
Via Neive,77 - 12020 CASTAGNITO (CN) ITALY
Tel. +39 0173 210111 - Fax +39 0173 210199
[email protected] - www.proteco.net
Programming
Standard programming must be performed for each motor; since no
safety devices will be wired to the Slave system, it is necessary to set
parameter P.2 to 0 (for SLAVE only).
Remember, being mirror gates, motors will open to opposite direction.
When programming is completed check the good operation of both
systems, using key "+" on board to give a START command.
Do not forget that at this stage both motors work individually.
Now proceed to connect the two motors, activating the TWINNING
function, through parameter H.6. as follows:
•MASTER = set parameter H.6 to 1
•SLAVE = set parameter H.6 to 2 (or 3).
Normally we suggest to set to 2, in order to synchronize both
gates (they open and close together at the same time).
•Option 3, may be rarely used: if gates are of different length, they
will open and close with different opening and closing times.
Now the Slave programming is completed.
The Master programming is not completed and it can follow on connecting
wired start commands, remote control storage, adjustment of working
times and so on.
In any moment it is possible to deactivate the Twinning function if
necessary (when maintenance service is required or the installation has
to be inspected).
If parameter H.6 is set to 0, the system will be separated from the other
one even if still wired together.
Be carefull,Slave has no safety devices nor start commands wired: it
can be commanded just using keys on board and the gate area will not
be protected during operation.
TWINNING CARD
SLOT
PMXM01_01_2021
MATRIX 2500/1800 (230V) MATRIX bldc/hi-Speed (brushless 48V)
TWINNING CARD
SLOT
Additional tips
Function “Dead Man”
This setting cannot be used, neither on the Master nor on the Slave
system.
Photocells, Safety edges and STOP emergency button
As previously mentioned, any safety device shall be wired to the Master.
However it is possible (but not recommended) to wire safety devices to
the Slave too. In this case, if Slave stops, Master will as well, showing a
fault message on the control unit's display.
There is an exception for safety edges and stop emergency buttons: it
would be recommended to wire them to the gate they serve.
In this case a permanent safe operation shall be granted even if the
communication between Master and Slave for some reason cuts.
Flashing light
It is possible to fit just one single flashing light in this kind of installation
and it has to be fitted to the Master system.
However it is possible to wire more than one if connected in parallel.
If Slave is set up to be activated on its own, or if gates have different
working times, it would be wise to fit 1 flashing light to each gate.

Other Proteco Control System manuals

Proteco Q52 Guide

Proteco

Proteco Q52 Guide

Proteco BARRY User manual

Proteco

Proteco BARRY User manual

Proteco Park Plus Series Operating and maintenance manual

Proteco

Proteco Park Plus Series Operating and maintenance manual

Popular Control System manuals by other brands

Raven AccuBoom Parallel Installation Manual

Raven

Raven AccuBoom Parallel Installation Manual

GE Mark VIe System guide

GE

GE Mark VIe System guide

CAME G4040Z installation manual

CAME

CAME G4040Z installation manual

Data Aire dap4 touch user manual

Data Aire

Data Aire dap4 touch user manual

WAREMA Wisotronic installation instructions

WAREMA

WAREMA Wisotronic installation instructions

ShowPro K2 user manual

ShowPro

ShowPro K2 user manual

Pilz PSS67 IO1 16FDI operating manual

Pilz

Pilz PSS67 IO1 16FDI operating manual

Norac UC4+ Apache 1010 2005+ installation manual

Norac

Norac UC4+ Apache 1010 2005+ installation manual

Tigo TS4-R Installation & quick start guide

Tigo

Tigo TS4-R Installation & quick start guide

Neptune Systems EnergyBar 6 Setup guide

Neptune Systems

Neptune Systems EnergyBar 6 Setup guide

Siemens SINUMERIK 840D sl Programming manual

Siemens

Siemens SINUMERIK 840D sl Programming manual

BACHMANN EUROPE Plc E-Z COMMAND DIGITAL COMMAND CONTROL SYSTEM user manual

BACHMANN EUROPE Plc

BACHMANN EUROPE Plc E-Z COMMAND DIGITAL COMMAND CONTROL SYSTEM user manual

PMV P5 manual

PMV

PMV P5 manual

Reliance Foundry R-7651-EM Installation

Reliance Foundry

Reliance Foundry R-7651-EM Installation

OPTO 22 SNAP PAC MOTION CONTROL user guide

OPTO 22

OPTO 22 SNAP PAC MOTION CONTROL user guide

Eaton CCS 5 instruction manual

Eaton

Eaton CCS 5 instruction manual

Sutter Lambda VF-5 Operation manual

Sutter

Sutter Lambda VF-5 Operation manual

PACH & COMPANY AeGIS AFGR9 Installation and programming manual

PACH & COMPANY

PACH & COMPANY AeGIS AFGR9 Installation and programming manual

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.