8. The Robar 7400/7500 series dismantling joints uses through
bolts which act as a flange bolt and as well as a end ring bolt.
9. Attach the flanged spigot to the opposite mating flange. Fasten
together with flange bolts (not supplied by Robar). Be sure to place
the flange gasket in between the mating flanges prior to inserting
flange bolts (not supplied by Robar).
10. The pipe spool piece should have the same center line as the
flanged coupling body. If not check to ensure both flanges on the
dismantling joint are flush with the mating flange ends. At the same
time ensure that the coupling gasket is seated properly into the
flange coupling body; if not properly seat the gasket.
11. Slide follower ring into position and hand tighten the follower
bolts and nuts.
12. Insert supplied tie rods (for restrained applications). Each tie
should have a total of 4 nuts when fully assembled. When inserting
the tie-rod, thread the nuts into position. The tie-rod must pass
through the flanges on each end of the dismantling joint. Make sure
the tie-rod lengths are equal for all rods supplied. Tighten the nuts
that secure the flanges. (**DO NOT TIGHTEN THE FOLLOWER
RING BOLT AND NUTS BEFORE PROPER TORQUE HAS BEEN
APPLIED TO THE FLANGE BOLTING**)
Robar Recommended Torque
Bolt Size Follower Ring Bolts Flange Bolts
5/8” 70-80 ft-lbs. 70-80 ft-lbs.
3/4” 80-90 ft-lbs. 90-100 ft-lbs.
7/8” 90-100 ft-lbs. 150-160 ft-lbs.